Item Description Called Scheduled Projected Actual

1 Get Permits 6/1 6/3 Days Days


2 Plot Plan & Stake-Out 6/4 6/5
3 Order Temporary Power 6/1 6/7 2 2
4 Order Trusses, metal, wood beams 6/1 6/15
5 Order windows 6/1 6/20
6 Order Exterior Doors 6/2 6/22
7 Excavation 6/1 6/7
8 Footings 6/7 6/15
9 Inspection: Footings / Steel 6/15 6/17
10 Foundation 6/7 6/20
11 Inspection: Foundation / Steel 6/15 6/21
12 Waterproof Foundation 6/20 6/25
13 Flatwork: Basement & Garage 6/17 6/28
14 Flatwork: Outside 6/17 6/30
15 Backfill & Rough Grade 6/20 7/1
16 Lumber 6/20 7/2
17 Framing 6/20 7/2
18 Plumbing Rough 7/2 7/20
19 HVAC Rough 7/2 7/21
20 Electric Rough 7/2 7/23
21 Order Interior & Exterior Handrails 7/2/ 7/23
22 Fireplace box Installation 7/2 7/23
23 Tub & Shower Installation 6/20 7/15
24 Truss Delivery 7/2 7/15
25 Roof Load Materials 7/2 7/15
26 Masonry/Dry-in Installation 7/5 7/25
27 Window Installation 7/20 7/30
28 Siding Installation 7/20 7/30
29 Gutter & Soffit Installation 7/30 8/5
30 Insulation 7/25 8/3
31 Drywall Stock 7/30 8/7
32 Inspect: Framing/Plumbing Rough/Elec Rough 7/30 8/2
33 Garage Door Installation 8/1 8/8
34 Drywall Hanging 7/25 8/9
35 Inspect: Drywall 8/13 8/15
36 Drywall Taping 8/13 8/16
37 Order Showerdoors and Mirrors 8/13 9/10
38 Order Countertops 8/13 9/10
39 Order Cabinets 8/13 9/10
40 Interior Paint 8/13 9/1
41 HVAC Final 9/10 9/15
42 Hang Interior Doors 9/10 9/16
43 Shelving Installation 9/16 9/18
44 Tile Installation 9/17 9/25
45 Countertop Installation 9/24 9/30
46 Plumbing Final/Install fixtures 9/30 10/2
47 Electric Final / Install fixtures 10/2 10/5
48 Install Electric Meter and perm power 10/5 10/10
49 Interior & Exterior hand rails 10/5 10/12
50 Interior trim and Rehang doors 10/10 10/15
51 Shower and Mirror Installation 10/15 10/17
52 Carpet Installation 10/12 10/20
53 Paint Touch Up 10/15 10/22
54 Trim Carpenter 10/20 10/25
55 Construction clean 10/25 10/28
56 Occupancy Inspection 10/28 11/1
Days Needed to
Complete According to
Bid
Release for Start
2 Permits
Connect Temporary
1 Power

2 Stake Out

5 Excavation

3 Footings

4 Foundation

2 Waterproofing

1 Backfill

Lumber Delivery

7 Start Framing

10 Finish Framing

3 Roofing
Rough Plumbing,
6 Electric, HVAC

2 Insulation

5 Drywall Hang

9 Drywall Tape/Sand

5 Paint

3 Hang Doors

5 Tile

2 Carpet

15 Cabinets/ Final Trim


Final
3 Plumbing/Electrical

2 Carpenter Final
2 Carpenter Final

1 Drywall Touchup

1 Paint Touchup

1 Windows

1 Final Inspection

1 Walk Through