5. You are working on a large project which has several smaller projects within it.

This is:

Program

Project Life Cycle

Project Subprojects

6. Which of the following is not true about Process Group.

Process Groups are not discreet, one time event

Process Groups are linked by the results they produce

Process Groups are Project Phases

Where large or complex projects may be separated into phases or sub-projects, all of the Process
Group processes would normally be repeated

7. The five project management process groups as described in the PMBOK® Guide and discussed in
the preceding lesson are:
Define, measure, analyze, improve, control
Kickoff, requirements, plan, schedule, control
Initiating, planning, executing, monitoring and controlling, closing
Requirements, design, development, testing, implementation

8. The PMBOK® Guide describes 10 Project Management Knowledge Areas. Identify 3 out of the 10
a.Cost, Integration, Process
b.Cost, Scope, Time
c.Contracts, Process, Risk
d.Quality, Process, Scope

9. What is a work breakdown structure?


A. A list of the activities making up the higher levels of the project
B. A definition of the hierarchy of project tasks, subtasks, and work packages
C. A depiction of the activities making up a project
D. A Gantt chart
E. A structure that is incompatible with the Critical Path Method

10. According to current PMI standards, Work Breakdown Structures are:


a. Task-oriented
b. Process-oriented
c. Deliverable-oriented
d. Time-oriented Correct

11. The elements at lowest level of the WBS are called ?


a. Control Accounts
b. Work Packages
c. WBS Deliverables
d. Lowest Level WBS Elements