1. When is the project completion date?

16/1/2022

2. List all the critical activities for this project.

Task Name ID Number


Retaining system 1.1.1
Soil improvement 1.1.2
Excavation 1.1.3
Piling 1.2.1
Pile cap and stump 1.2.2.1
Ground beam and slab 1.2.2.2
Column 1.2.2.3
Roof beam and flat roof 1.2.2.4
Brick Laying 1.2.3.1
Plastering 1.2.3.2
Tiling 1.2.3.3
Drains 1.2.5.1
Access road 1.2.5.2
RI inspection 1.3.1

3. What is the start date for architectural work?


16/11/2021

4. How long does it take to complete the structural work?


23 days

5. What is the WBS ID number for External Work?

1.2.5