Working Hours for the Document Preparation for Lusail Stadium - Lifting Documents and Drawing
Preparation for Arches
Working Sl.No Description of Works Start Date Finish Date Hours 1 Meetings & Documents writeups 4th May 2021 4th May 2021 4 2 Total 7 types of Lifting Analysis including 05th May 2021 07th May 2021 24 Connection Design. 3 Document Writeups. 08th may 2021 08th May 2021 8 4 Revision of Lifting Analysis based on the Height 09th May 2021 09th May 2021 8 Restrictions. 5 Lifting Drawing Preparations total 3 Dwgs 10th May 2021 10th May 2021 8 6 Document Writeups. 11th May 2021 11th May 2021 8 7 Meetings 0.5 8 Document Revision 2nd Jun 2021 03rd Jun 2021 8