Professional Documents
Culture Documents
Home / Technical Articles / Automatic bus transfer scheme in thermal and nuclear power stations
Contents:
1. Automatic bus transfer scheme
1. Unit switchgear
2. Station switchgear
3. Modes of bus transfer
1. Manual changeover without voltage interruption
2. Manual changeover with voltage interruption
1. Slow changeover
2. Fast changeover
1. How phase comparison relay works?
3. Automatic changeover with voltage interruption,
under fault condition
Go back to contents ↑
Go back to contents ↑
Once the unit starts generating power, the unit switchgear bus is
disconnected from the station switchgear bus, and starts taking power from
the unit itself, through UAT.
Thus the power plant is run from the output of its own generating unit. In
case the unit is tripped due to some fault or planned shutdown, the incoming
supply to the unit switchgear bus fails. In this condition also, it is essential
to keep the power plant auxiliaries in a running condition.
Hence the power supply to the unit switchgear bus is again taken from SAT,
through the tie connection to the station switchgear bus.
The medium voltage unit and station switchboards are provided with bus
transfer facility which could come into operation either manually (planned
operation) and/or automatically. During the normal running of the unit, unit
board is supplied from the unit transformer and the station board from the
station transformer, as explained above. Both the switchboards are provided
with bus tie breakers for inter-connection.
The bus transfer could be manual (pre-planned) in the event of the transfer
of unit load from station to the unit transformer as is the case immediately
after the unit has been started. The operation could also be vice versa.
Similarly, in the event of one station transformer being taken out for some
reason, the corresponding section of the station board is fed from the other
station board. The transfer could also be automatic in the event of a fault
characterised by the operation of protection relay.
The manual and automatic bus transfer can be arranged in such a way that
any of the following modes of operation is possible.
Go back to contents ↑
Go back to contents ↑
This signal for closing the new supply source breaker goes only after the
residual voltage has reached the pre-set value, which is about 20% of
the rated voltage.
Necessary VTs and fast acting voltage sensing relays are used for sensing
the appropriate voltage condition for bus transfer. This ensures that at the
moment of changeover, even if the residual voltage of motor is in phase
opposition to the voltage of the new source of supply, the motors will not
be subjected to magnetic shocks which could prove dangerous.
Reduction of residual motor voltage to 20% of the rated voltage ensures that
the closure of new supply even in phase opposition to the residual motor
voltage will be harmless.
Since the residual motor voltage has dropped down to as low a level as 20%,
it pre-supposes that the motors have slowed down considerably. As such, on
closure of the new sources of supply, there will be a danger of heavy
inrush of starting current which will last till the motors are accelerated to
the normal speed.
This starting current inrush, though somewhat lower than when starting from
standstill, will yet be high enough to cause a heavy voltage drop in the
transformer impedance of the new source which may be severe enough to
cause the motors to pull out.
b) Fast Changeover
This changeover ensures that the bus transfer takes place so rapidly that
the residual motor voltage vector has fallen behind the incoming
voltage vector only so little.
On one hand, closure against phase opposition is ruled out, on the other
hand, at the time of the closure, the connected motor speed has dropped
down only marginally with the result that at the moment of transfer of
connected motors to the new source of supply, there is only a small rise of
current as compared to the normal running current (this marginal rise could
be of the order of 50%).
The voltage drop during the bus transfer is therefore marginal and the bus
transfer is satisfactory.
A sensitive phase comparison relay, which is the most vital element of the
fast changeover scheme, should be used to permit the rapid changeover
in the event of the two source voltage difference, phase angle difference
and frequency difference is in pre-set limit before issuing closing command
to the new source.
This relay otherwise blocks the closing command thereby preventing the
changeover under unfavourable conditions of the new source and the
residual voltage of the decaying bus.
After delaying the local signal to align with the received signal, the states of
the two signals are compared (see Figure 3).
For normal load flow or for an external fault, the situation is as shown on the
right. Current flows into one end, and out the other. If the CT circuits are
consistently polarized at the two ends, then the local and remote mark
signals (positive phase position of respective current signals) have little or no
coincidence – if we combine them with an AND gate, its output will be false,
or will have at most two short true pulses per power cycle if the current
waves are not exactly out of phase.
Go back to contents ↑
Go back to contents ↑
References //
1. Switchgears book by BHEL – Bharat Heavy Electricals Limited
2. Phase Comparison Relaying by Bogdan Kasztenny, Ilia Voloh
(General Electric) and Eric A. Udren (KEMA T&D Consulting)
Related EEP's content with sponsored links