Major Delays (Rehabilitation of One Million Reservoir in Makkah Al Mukarramah) 23-12-2021
Activity Name Original Start Finish % (23-12-2021) % (30-12-2021)
Repair Concrete Materials 176 31-Oct-21 12-May-22 18.54% 22.79% Submittal Submittal for material 14 31-Oct-21 15-Nov-21 100.00% 100.00% Approval Approval for material 14 16-Nov-21 1-Dec-21 100.00% 100.00% PO PO for material 14 2-Dec-21 18-Dec-21 100.00% 100.00% Delivery Delivery for material 120 19-Dec-21 12-May-22 4.17% 9.17% Waterproofing Materials 150 6-Dec-21 13-Jun-22 2.29% 3.00% Submittal Submittal for material 7 6-Dec-21 13-Dec-21 100.00% 100.00% Approval Approval for material 7 14-Dec-21 21-Dec-21 100.00% 100.00% PO PO for material 7 22-Dec-21 29-Dec-21 28.57% 100.00% Excavation and General Fill 250 17-Nov-21 17-Sep-22 11.43% 13.57% Submittal Submittal for material 14 17-Nov-21 2-Dec-21 100.00% 100.00% Approval Approval for material 14 4-Dec-21 19-Dec-21 100.00% 100.00% PO PO for material 14 20-Dec-21 4-Jan-22 28.57% 71.43% Asphalt 139 17-Nov-21 30-Apr-22 13.67% 16.62% Submittal Submittal for material 7 17-Nov-21 24-Nov-21 100.00% 100.00% Approval Approval for material 14 25-Nov-21 11-Dec-21 100.00% 100.00% PO Major Delays (Rehabilitation of One Million Reservoir in Makkah Al Mukarramah) 23-12-2021 Activity Name Original Start Finish % (23-12-2021) % (30-12-2021) PO for material 15 12-Dec-21 28-Dec-21 73.33% 100.00% Delivery Delivery for material 105 29-Dec-21 30-Apr-22 0.00% 9.17%