SECTION XI
INTERPRETATIONS
Volume 46
The Interpretations to the Code will be issued twice a year (July and December) up to the
publication of the 2001 Edition of the Code. The Interpretations for each individual Section are
published separately and are part of the update service to that Section; Interpretations of Section
III, Divisions 1 and 2, are part of the update service to Section III, Subsection NCA.
Interpretations Volumes 36 through 41 were included with the update service to the 1995 Edition
of the Code; Volume 42 is the first Interpretations volume to be included with the update service
to the 1998 Edition.
FOREWORD
General Information
This publication includes all written interpretations issued between the indicated dates by the ASME
Staff on behalf of the ASME Boiler and Pressure Vessel Committee in response to inquiries concerning
interpretations of the ASME Boiler and Pressure Vessel Code. A contents is also included that lists
subjects specific to the interpretations covered in the individual volume.
These interpretations are taken verbatim from the original letters, except for a few typographical
and editorial corrections made for the purpose of improved clarity. In some instances, a review of the
interpretation revealed a need for corrections of a technical nature. In these cases, a revised interpretation
is presented bearing the original Interpretation Number with the suffix R and the original file number
with an asterisk. Following these revised interpretations, new interpretations and revisions to them
issued during the indicated dates are assigned Interpretation Numbers in chronological order. Interpretations
applying to more than one Code Section appear with the interpretations for each affected Section.
ASME procedures provide for reconsideration of these interpretations when or if additional information
is available that the inquirer believes might affect the interpretation. Further, persons aggrieved by an
interpretation may appeal to the cognizant ASME committee or subcommittee. As stated in the Statement
of Policy in the Code documents, ASME does not “approve,” “certify,” “rate,” or “endorse” any item,
construction, proprietary device, or activity.
Each interpretation applies to the Edition and Addenda stated in the interpretation, or if none is
stated, to the Edition and Addenda in effect on the date of issuance of the interpretation. Subsequent
revisions to the Code may supersede the interpretation.
For detailed instructions on preparation of technical inquiries to the ASME Boiler and Pressure
Vessel Committee, refer to Appendix V in Division 1, Appendix III in Division 2, and Appendix VI
in Division 3.
401
403
Interpretation: XI-1-92-29R
Subject: IWF-2500(a), Boundary Interface (1977 Edition With the Summer 1978 Addenda
Through the 1998 Edition With the 1999 Addenda)
File: IN92-006A*
Question: Is it the intent of IWF-2500(a), for a pipe-clamp-type support, that the “mechanical
connections to the pressure retaining components” requiring examination include the bolting or pins
and their interface to the clamp, but exclude the component-to-clamp interface?
Reply: Yes.
Interpretation: XI-1-98-48R
Subject: Code Case N-416-1, Alternative Pressure Test Requirement for Welded Repairs or
Installation of Replacement Items by Welding, Class 1, 2, and 3
File: IN99-004*
Question (1): When using Code Case N-416-1, is it a requirement of Section XI that a reconciliation
concerning NDE requirements and acceptance criteria between two Codes (e.g., B31.7-1969 and ASME
Section III, 1992 Edition, 1992 Addenda) be performed by a Level III for the applicable examination
method?
Question (2): When using Code Case N-416-1, is it a requirement of Section XI that the
reconciliation of an NDE procedure between two Codes (e.g., B31.7-1969 to ASME Section III, 1992
Edition, 1992 Addenda) for requirements and acceptance criteria be performed by a Level III for the
applicable examination method?
405
Interpretation: XI-1-98-51R
Subject: IWA-4540(c), Pressure Testing of Class 1, 2, and 3 Items (1995 Addenda Through
the 1998 Edition)
File: IN99-011*
Question: Does IWA-4540(c) require a pressure test when installation of the item(s) does not
involve any replacement pressure-retaining items?
Reply: No.
Interpretation: XI-1-98-52R
Subject: IWA-4700, Pressure Tests; IWA-5120, System Pressure Tests for Repair/Replacement
Activities (1992 Edition With the 1992 Addenda)
File: IN99-013*
Question: Is it a requirement of IWA-4700 and IWA-5120 that the entire system be subjected to
a VT-2 examination when the area of a repair/replacement activity that is required to be pressure
tested is not isolable within a portion of a system?
Reply: No.
406
Interpretation: XI-1-95-48R
Subject: IWA-5214, Repair and Replacement (1980 Edition With the Winter 1980 Addenda
Through the 1989 Edition With the 1990 Addenda); and IWA-4710(c), Pressure Tests
(1989 Edition With the 1991 Addenda Through the 1992 Edition With the 1994
Addenda)
File: IN95-007A*
Question (1): When replacing a valve disc, do the requirements of IWA-5214(e) apply?
Question (2): When replacing any pressure retaining part of a valve that is internal to the valve
body/bonnet, do the requirements of IWA-5214(e) apply?
Question (3): When replacing a valve disc, do the requirements of IWA-4710(c) apply?
Question (4): When replacing a valve bonnet and/or body that requires installation by mechanical
joints, do the requirements of IWA-4710(c) apply?
Question (5): When replacing any pressure retaining part of a valve that is internal to the valve’s
body/bonnet, do the requirements of IWA-4710(c) apply?
407
Interpretation: XI-1-98-54
Subject: IWA-4300, Welding and Welder Qualifications for Repairs (1980 Edition Through
the 1986 Edition With the 1987 Addenda); IWA-7320, Welding and Welder Qualifica-
tions for Replacements (1980 Edition Through the 1989 Edition With the 1990
Addenda)
File: IN98-024
Question (1): Is it the intent of IWA-4300 for repair welding to components and their supports,
which were originally constructed to welding requirements other than Section IX (e.g., AWS D1.1),
to be performed with welders and welding procedure specifications qualified in accordance with Section
IX and the additional requirements of Section III and XI?
Reply (1): No, the welding requirements from the original construction code may be used.
Question (2): Is it the intent of IWA-7320 for replacement welding to components and their
supports, which were originally constructed to welding requirements other than Section IX (e.g., AWS
D1.1), to be performed with welders and welding procedure specifications qualified in accordance with
Section IX and the additional heat treating and impact tests required by IWB-4000?
Reply (2): No, the welding requirements from the original construction code may be used.
Interpretation: XI-1-98-55
File: IN98-006
Question (1): Is it a requirement of IWC-3516 and IWD-3000 to apply IWB-3522 to Class 2 and
3 components?
408
Interpretation: XI-1-98-56
Subject: IWE-1220(d), Components Exempted From Examination (1992 Edition With 1992
Addenda)
File: IN99-014
Question: Does IWE-1220(d) require that portion of piping that penetrates the containment vessel
to be classified as Class 1 or 2?
Interpretation: XI-1-98-57
Subject: IWA-7330, Procurement of Material (Summer 1978 Addenda Through 1990 Addenda);
IWA-4920 (1991 Addenda Through the 1995 Edition); IWA-4143 (1995 Addenda
Through the 1999 Addenda)
File: IN99-018
Question (1): When using the original Construction Code (Section III), is it a requirement of
IWA-4143(a) that Repair/Replacement Organizations (including the Owner, when the Owner acts as
the Repair/Replacement Organization) that fabricate parts, appurtenances, piping subassemblies and
supports for use by the Owner, at the Owner’s facility, be an N-Type Certificate Holder or Quality
System Certificate Holder in order to procure, store, handle, and use the material from which such
items are fabricated?
Reply (1): No. However, if the Construction Code invokes NA-3700 or NCA-3800, a Repair/
Replacement Organization that is not accredited by ASME must procure materials from an accredited
Materials Organization or Certificate Holder. (Applicability: 1997 Addenda and Later)
Question (2): When using the original Construction Code (Section III), is it a requirement of
IWA-4143(b) (IWA-7330 for Editions and Addenda Through the 1990 Addenda, and IWA-7330 From
the 1991 Addenda Through the 1995 Edition) that Repair/Replacement Organizations (including the
Owner, when the Owner acts as the Repair/Replacement Organization) that install items at the Owner’s
facility be an N-Type Certificate Holder or Quality System Certificate Holder in order to procure,
store, handle, and use the material used in the installation?
Reply (2): No. However, if the Construction Code invokes NA-3700 or NCA-3800, a Repair/
Replacement Organization that is not accredited by ASME must procure materials from an accredited
Materials Organization or Certificate Holder. (Applicability: Summer 1978 Addenda Through 1999
Addenda)
409
Interpretation: XI-1-98-58
Subject: IWF-2500, Examination of Component Supports; Code Case N-491, -2500, (1989
Edition)
File: IN99-022
Question (1): Do IWF-2500 and Code Case N-491, -2500, require the examination of clearances
only when examining guides and stops, and the examination of settings only when examining spring
and constant load supports?
Interpretation: XI-1-98-59
Subject: IWL-4000 Installation — Concrete Anchors (1992 Edition With the 1992 Addenda
Through the 1998 Edition)
File: IN99-002
Question: Is it the intent of IWL-4000 that the installation of concrete anchors be exempt from
the rules of IWL-4000 provided the installation affects only the cover concrete external to the outermost
layer of structural reinforcing steel or the post-tensioning system?
Reply: Yes.
410
Interpretation: XI-1-98-60
Subject: IWF-1300(e), Table IWD-2500-1, VT-3 — Insulation Removal (1983 Edition With
the Winter 1983 Addenda Through the 1989 Edition, No Addenda)
File: IN98-014B
Reply: Yes.
Interpretation: XI-1-98-61
Subject: IWA-4000, -7000, Subassembly — Installation (1997 Edition With the Summer 1978
Addenda up to and Including the 1995 Edition With the 1996 Addenda) and Code
Case N-416-1
File: IN99-010
Question: Does the Section XI term “installation” allow the joining of items, by the Owner or
Repair/Replacement Organization, into a piping subassembly at a location other than its final location
in the piping system?
Reply: Yes.
Interpretation: XI-1-98-62
File: IN99-024
Question: Does IWA-4000 (or IWA-7000, as applicable) permit an Owner to contract repair/
replacement activities to be controlled in accordance with the Owner-approved Quality Assurance
Program of the contractor (Repair/Replacement Organization), with ANII services to be subcontracted
by the Repair/Replacement Organization and a Data Report to be prepared and certified by the Repair/
Replacement Organization and the subcontracted ANII certifying that the applicable requirements of
Section XI have been met?
Reply: Yes.
411
Interpretation: XI-1-98-63
Subject: Mandatory Appendix IV, IV-3110(f), Eddy Current Instrument Channel Application
(1989 Edition With the 1990 Addenda up to and Including the 1992 Edition With
the 1992 Addenda)
File: IN99-025B
Question: Does Mandatory Appendix IV, IV-3110(f) require amplification for all channels of the
eddy current instrument to be within 5% of the mean value, at all sensitivity settings, at any single
frequency?
Reply: Yes.
Interpretation: XI-1-98-64
File: IN99-026
Question: When performing a system leakage test in lieu of a Section XI hydrostatic test in
accordance with Code Case N-416-1 following installation of a NPT-stamped Class 1 replacement part
by welding, may the NDE specified in NB-5410 be performed prior to the system leakage test?
Reply: Yes.
Interpretation: XI-1-98-65
Subject: Code Case N-522, “Pressure Testing of Containment Piping, Section XI, Division 1”
File: IN99-027
Question: Is it a requirement of Code Case N-522 that the pressure test following repairs or the
installation of replacements by welding in containment penetration piping that is otherwise outside the
scope of Section XI, be performed in accordance with 10 CFR 50, Appendix J?
Reply: No. The scope of N-522 only applies to the periodic pressure tests of Table IWC-2500-
1, Category C-H.
412
Interpretation: XI-1-98-66
Subject: IWA-4180, IWA-4220, Report of Reconciliation (1995 Edition With the 1995 Addenda
Through the 1998 Edition With the 1999 Addenda; IWA-4410 in the 1995 and 1996
Addenda); IWA-4421 (1995 Edition With the 1997 Addenda Through the 1998 Edition
With the 1999 Addenda)
File: IN99-031
Question: Is it a requirement of IWA-4180, IWA-4220, (IWA-4410 in the 1995 and 1996 Addenda)
and IWA-4421 that the Report of Reconciliation be a separate and unique document?
Reply: No. Any documents that satisfy the evaluation requirements contained in IWA-4220 may
be used to record reconciliation activities.
Interpretation: XI-1-98-67
File: IN96-015
Question (1): Is it the intent of Table IWC-2500-1, Examination Category C-H, that nozzle-to-
nozzle vessel welds (i.e., nozzle extension) be visual, VT-2-examined in accordance with the frequency
specified for Examination Category C-H?
Question (2): Is it the intent of Table IWC-2500-1 that full penetration nozzle-to-nozzle vessel
welds be included in Examination Category C-B?
413
Interpretation: XI-1-98-68
Subject: Code Cases N-498, N-498-1, and N-498-2, Alternative Requirements for 10 Year
Hydrostatic Testing For Class 1, 2, and 3 Systems
File: IN97-004
Question: When conducting a Class 1 system leakage test under the provisions of Code Case N-
498, including N-498-1 and N-498-2, is it the intent of para. (a)(2) to pressurize all Class 1 piping
(including portions isolated during normal operation), to the reactor coolant system nominal operating
pressure?
Reply: Yes.
Interpretation: XI-1-98-69
Subject: IWB-3516.1(a), Allowable Planar Flaws (1989 Edition Through the 1992 Addenda)
File: IN98-002B
Question: Is it the intent of IWB-3516.1(a) that referenced Figs. IWB-2500-14 and IWB-2500-15
have the same examination boundary location sequence A-B-C-D as Fig. IWB-2500-13?
Reply: Yes.
414
Interpretation: IX-1-98-70
Subject: Table IWB-2500-1, Examination Category B-J (1983 Edition and Later Editions and
Addenda)
File: IN98-009
Question (1): Does Table IWB-2500-1, Examination Category B-J, Footnote (1) require 25% of
the total nonexempt weld population of each item number listed (i.e., B9.11, B9.21, B9.31, B9.32, or
B9.40) be selected for examination during an Inspection Interval?
Question (2): Does Table IWB-2500-1, Examination Category B-J, Footnote (1) require 25% of
the total nonexempt weld population of Examination Category B-J be selected for examination during
an Inspection Interval?
Question (3): Is it the intent of Table IWB-2500-1, Examination Category B-J, Footnote (2) to
require the reexamination of B-J welds initially selected during the previous inspection interval only
to the extent practical?
Reply (3): Yes. This was clarified in a code change in the 1993 addenda.
Interpretation: XI-1-98-71
Subject: Table IWE 2500-1, Examination Category E-A, Accessible Surface Areas (1992 Edition
With the 1992 Addenda Through the 1998 Edition With the 1999 Addenda)
File: IN99-001
Question: Is it the intent of Table IWE-2500-1, Category E-A, Accessible Surface Areas, that
surface areas may be considered inaccessible if visual access by line of sight with adequate lighting
from permanent vantage points is obstructed by permanent plant structures, equipment, or components,
provided these surface areas do not require examination in accordance with the inspection plan for
IWE-1240?
Reply: Yes.
415
Applicability
alternative weld repair — removal cavity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-25 IN95-001 313
XI-1-95-29 IN95-001B 315
corrective measures — of new bolting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-01 IN90-023 242
fabrication of replacements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-72 BC81-568A 72
flaws detected outside of an inservice examination . . . . . . . . . . . . . . . . . . . . . . XI-1-89-67 IN89-017C 232
installation requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-85 BC84-683 81
instrument tubing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-52 BC83-625 55
leakage — not found during a system pressure test . . . . . . . . . . . . . . . . . . . . . . XI-1-92-03 IN91-017 242
material removal process — considered as thermal . . . . . . . . . . . . . . . . . . . . . . XI-1-95-60 IN-95-018 348
material removal process — nonwelded . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-70 IN91-005 233
XI-1-89-70R IN91-005 351
metal removal to prepare surface for NDE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-56 IN90-022 227
owner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-83 BC83-179 79
preventive maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-19 IN88-009 188
redundant canopy seal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-19 IN88-009 188
repair program — installing replacements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-42 BC84-123 43
repair / replacement activities — off site. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-09 IN94-014 302
XI-1-98-44 IN98-020 395
repair subsequent to N-Stamping — prior to N-3 . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-10 BC82-277 17
XI-1-83-46 BC83-595 51
shot peening . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-73 IN91-006 234
small items — replacement of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-60 IN93-024 283
storage tank — examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-51 IN90-017 218
through wall leakage. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-64 IN89-017B 231
use of AIA for installing replacements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-38 BC84-122 41
Calibration
angle beam . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-11 IN88-016 175
confirmation — period of use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-05 IN88-005 167
demonstration of equivalence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-28 IN86-008 111
XI-1-86-61 IN86-030 146
electronic memory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-17 IN92-001 252
interim check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-62 IN90-033 230
of gages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-49 BC82-776 53
series of test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-49 BC82-776 53
standard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-28 IN86-008 111
Calibration Blocks
different specification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-61 IN86-030 146
material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-72 IN87-005B 156
notch reflectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-09 IN87-019 168
reactor vessel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-71 IN87-005 156
reflectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-62 IN97-006 349
reflectors—alternative layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-19 IN97-006A 369
side drilled holes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-11 IN88-016 175
ultrasonic examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-12 IN89-001A 175
V path . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-21 IN89-004A 190
Classification of Systems
exclusion of components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-56 IN96-022 346
high pressure safety injection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-42 IN86-011 124
instrument tubing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-78 BC84-682 76
penetrates the containment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-44 BC83-448 50
piping — visual examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-67 IN87-022 154
Component Supports
additional examinations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-32 IN95-004B 322
associated supports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-49 IN86-026B 128
XI-1-86-50 IN86-026C 128
coiled wire rope device . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-55 IN93-016 281
corrective measures — additional examinations . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-17 BC85-253B 105
XI-1-95-30 IN95-004A 316
examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-58 IN99-022 410
examination requirements — exemptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-27 BC83-437 31
XI-1-92-22 IN92-010 254
integral attachments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-47 IN90-009 210
XI-1-89-59 IN90-026 228
XI-1-98-69 IN98-002B 414
interfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-29 IN92-006A 257
XI-1-92-29R IN92-006A 405
integrally attached . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-69 IN87-008 155
XI-3-98-21 IN97-026 375
integrity by analyses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-30 IN86-013 112
XI-1-86-30R IN86-013* 321
leakage at threaded connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-55 IN98-006 408
multiple components. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-26 IN86-002 110
XI-1-86-63 IN87-004 147
not constructed to Section III . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-30 BC82-522 32
preservice examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-48 IN86-026A 127
XI-1-86-50 IN86-026C 128
XI-1-89-44 IN90-004 209
removal of insulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-69 IN90-027 233
XI-1-92-20 IN92-006B 254
Repair / Replacement Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-23 BC85-525D 108
repair — requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-28 IN89-021 195
representative sample . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-72 IN90-035 234
Construction Code
certificate requirement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-57 IN99-018 409
hydrostatic test. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-83 BC83-179 79
XI-1-86-22 IN86-010 108
XI-1-86-52R BC85-524* 187
material manufacturers and suppliers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-50R BC84-175* 68
XI-1-89-24 IN89-014 193
reconciliation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-41 IN89-025 207
repair activities — removal cavity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-25 IN95-001 313
XI-1-95-29 IN95-001B 315
repair / replacement — design requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-01 IN93-003 299
replacement of Section III components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-68 IN90-015 232
replacement pressure vessel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-46 IN90-008 210
XI-1-89-46R IN90-008* 225
surface examination — acceptance criteria. . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-52 BC85-524 135
use of later editions of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-12 BC85-098 103
XI-1-86-38R BC85-141* 143
XI-1-86-39R BC85-525C* 144
XI-1-86-44R IN86-015* 144
XI-1-89-20 IN88-014 189
use of later editions of — stamping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R BC82-434* 117
XI-1-86-44R IN86-015* 144
welding requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-51 IN86-027 129
Inspection Interval
deferral of required examinations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-65 IN96-019 346
extended or decreased . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-57 IN93-002 282
XI-1-95-55 IN96-019 346
extension of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-54 IN87-001 136
hydrostatic test — interval extension . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-58 IN90-025 228
inspection completion percentages — calculation of . . . . . . . . . . . . . . . . . . . . . XI-1-95-11 IN94-024 303
multiple components — NDE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-26 IN86-002 110
scheduling requirements — applied by . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-74 IN86-003A 157
successive inspections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-46 IN98-027 396
XI-1-98-49 IN99-008 398
support examinations — percentage requirements . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-10 IN94-023 303
visual examination — multiple stream. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-68R BC83-441* 101
volumetric examination — successive . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-50 IN90-014 218
Installation
concrete anchors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-59 IN99-002 410
Nonwelded Work
maintenance — requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-21 IN86-004 107
XI-1-86-21R IN86-004* 186
mechanical tube plugging. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-41 IN86-005 124
XI-1-92-44 IN91-031B 273
modification — hydrostatic test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-03R BC83-112* 103
pressure retaining material — requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-21 IN86-004 107
XI-1-86-21R IN89-004* 186
repair program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-42 BC84-123 43
replacement — documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-14R BC85-112* 118
sleeving of heat exchanger tubes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-32 IN91-031 263
sleeving of steam generator tubes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-41 IN86-005 124
use of an AIA. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-13 BC82-407 18
XI-1-83-38 BC84-122 41
Piping
component connected to NPS 4 and smaller — NDE . . . . . . . . . . . . . . . . . . . . XI-1-86-43R IN86-012* 125
containment vessels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-56 IN99-014 409
multiloop system — inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-15R BC85-130* 135
NDE — installation welds. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-51 IN86-027 129
pressure retaining welds — NDE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-57 IN87-007 138
XI-1-92-56 IN93-013 281
pressure retaining welds — selection criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-17 IN97-017 368
subassembly — installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-61 IN99-010 411
supports — examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-49 IN86-026B 128
XI-1-86-63 IN87-004 147
supports — exempted . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-65 IN87-031 147
Pressure Retaining
bolting — documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-22 IN89-009 191
bolting — manways . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-11 BC82-304 17
bolting — removal of insulation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-39R IN89-013A* 289
bolting — visual examination. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-68R BC83-441* 101
XI-1-86-45 IN86-020 126
XI-1-92-64 IN93-038 290
bolts and studs — examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-76 BC84-390 75
XI-1-98-45 IN98-022 395
boundary — alternative test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-25 BC85-528 110
boundary — flaw evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-35 IN92-023 265
boundary — machining of sealing surface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-08 IN97-021 365
component — through-wall leakage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-64R IN89-017B* 241
components and their supports — summary report . . . . . . . . . . . . . . . . . . . . . . XI-1-83-03 BC82-406 6
components — exempt from visual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-53 IN90-019 219
electrical containment penetrations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-35 IN98-015 387
material — nonwelded work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-21 IN86-004 107
XI-1-86-21R IN86-004* 186
material — sealants. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-26 IN95-002 314
parts — hydrostatic test. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-83 BC83-179 79
parts — ordered as spares. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R BC82-434* 117
welds — examination schedule requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-14 IN86-003B 176
welds in piping — NDE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-57 IN87-007 138
XI-1-92-56 IN93-013 281
welds in vessels — examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-70 IN87-011 155
welds — preservice examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-24 BC85-526 109
Procurement of
material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-55R IN87-002* 153
material — MM and MS qualification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-50R BC84-175* 68
XI-1-89-24 IN89-014 193
parts as material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R BC82-434* 117
parts by non-Certificate Holder . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-29 IN89-008 202
pipings, valves, and fittings — NPS 1 and smaller . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-04 IN88-004 166
pressure retaining part — Code Data Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R BC82-434* 117
replacements — later edition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-12 BC85-098 103
replacements — perform work on it . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-59 BC85-550 145
replacement — stamping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-20 BC82-430 27
spares . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R BC82-434* 117
XI-1-86-18 BC85-254 106
spares — transfer of custody. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-07 IN88-011 167
Pumps
Class 2 and 3 — exemption from examination. . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-12 IN95-017 366
Shutdown
cold . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-73 BC82-665A 73
XI-1-83-74 BC82-752 74
extended — valve testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-41R IN92-025A* 273
valve testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-74 BC82-752 74
Stamping
installation of replacement parts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-02 BC81-476 6
of replacement parts — ordered as spares. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R BC82-434* 117
of replacement parts — valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-20 BC82-430 27
Section III. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-72 BC81-568A 72
Surfaces
accessible surface areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-71 IN99-001 415
Ultrasonic Examination
bolts and studs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-24 IN94-026 313
XI-1-98-22 IN97-028 376
calibration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-17 IN92-001 252
detection specimens — orientation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-36 IN92-026 265
equalized sensitivity — recording of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-22 BC80-567 28
evaluation of flaws . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-29 BC82-050 32
full penetration weld of nozzles. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-56 BC84-388 56
material attenuation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-17 IN89-004B 179
nozzle-to-safe end welds — extent of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-49 IN90-013 217
performance demonstration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-36 IN92-026 265
piping — outer surface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-58 IN93-021 282
procedure qualification — search unit. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-21 IN94-013 312
IN94-025
qualification outside agency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-31 IN95-008 321
qualified by performance demonstration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-09 IN91-027 245
reflectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-84 BC83-654 80
requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-84 BC83-654 80
search unit overlap . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-13 IN89-005 176
sweep display . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-23 IN89-010 192
three-point DAC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-31 BC82-630 33
welds > 2 inches in thickness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-51 IN95-011 345
welds in piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-24 IN94-026 313
V path . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-23 IN89-010 192
Valve
Class 2 and 3 — exemption from examination. . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-12 IN95-017 366
classification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-59R BC83-439 90
XI-1-83-62 BC84-178 59
XI-1-92-13 IN91-026 251
disc and seat — hard facing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-35R IN92-023 289
examination — bolts and studs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-76 BC84-390 75
Visual Examinations
components exempt — volumetric and surface . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-40 IN92-022A 267
core support structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-46 IN92-043 274
exempt from . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-53 IN90-019 219
leakage. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-19 IN92-005 253
XI-1-92-48 IN93-001 274
XI-1-92-51 IN93-011 275
liquid-metal containing components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-3-89-01 IN86-024C 169
multiple stream — pressure retaining bolting . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-68R BC83-441* 101
near-distance acuity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-07 IN97-031 364
piping system — classification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-67 IN87-022 154
pressure test — pressure requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-46 IN86-023 127
removal of insulated . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-39 IN89-013A 206
XI-1-98-32 IN98-014 386
reactor vessel — spaces below the core . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-28 IN94-006B 315
reactor vessel — spaces within . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-27 IN94-006A 314
vessels — pressure retaining welds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-70 IN87-011 155
VT categories — requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-26 BC80-231* 194
VT-1 — base metal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-33 IN91-043 264
VT-1, VT-3 — interchangeable. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-69 BC84-616 69
VT-1 — pressure retaining bolting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-45 IN86-020 126
VT-2 — containment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-15 IN97-015 367
VT-2 by direct examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-06 IN97-034 364
VT-2 during a functional test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-75 IN91-010 235
VT-2 of borated water systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-39 IN89-013A 206
VT-2 of buried components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-19 BC82-607 27
XI-1-92-34 IN92-020 264
VT-2 — exemption from open-ended portions of Class 2 and 3. . . . . . . . . . . . . XI-1-98-13 IN97-007 367
VT-2 — personnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-63R BC84-310* 101
VT-2 — removal of insulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-47 IN92-046 274
VT-2, VT-3 — piping system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-67 IN87-022 154
VT-2 — surrounding areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-06 IN97-034 364
VT-2 — system leakage test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-45 IN96-009 336
VT-3 — bolted connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-48 IN93-001 274
VT-3 — bolting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-39 IN97-033 388
VT-3 — class 3 components. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-51 IN93-011 275
XI-1-95-36 IN94-012 329
VT-3 — insulation removal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-60 IN98-014B 411
VT-3 — disassembly & reassembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-47 IN99-003 396
Volumetric Examinations
and surface — exemptions to. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-43R IN86-012* 125
XI-1-92-40 IN92-022A 267
XI-1-92-45 IN92-022B 273
XI-1-95-03 IN93-042 300
as an alternative to surface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-21 IN89-004A 190
XI-1-89-27 IN89-004C 195
Code Case N-460 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-32 IN89-026 203
fabrication defects — additional examinations . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-04 BC82-427 7
or surface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-11 IN88-016 175
XI-1-92-43 IN92-033 268
piping — outer surface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-58 IN93-021 282
prior to hydrostatic test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-63 IN90-034 230
required volume to be examined . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-32 IN89-026 203
successive inspection intervals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-50 IN90-014 218
Weld
accessible — preservice examination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-24 BC85-526 109
additional examinations — similar components . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-61 IN93-027A 283
alternate rules for the selection and examination . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-02 IN95-023 362
between different P-numbers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-39 BC83-527 42
connecting NPS 1 and less — hydrostatic test . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-35 IN86-019 120
examination — austenitic welds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-18 IN97-023 369
XI-1-98-33 IN95-025 386
examination — dissimilar metal welds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-13 IN91-026 251
examination — full penetration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-43 IN90-003 208
XI-1-98-67 IN96-015 413
examination of integrally welded attachments . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-05 IN91-016 243
examination — nozzle-to-nozzle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-67 IN96-015 413
examination — nonexempt weld population . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-70 IN98-009 415
examination of pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-80 BC84-685 77
XI-1-83-80R BC84-685* 241
examination — partial . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-12 IN91-025 251
examination — partial penetration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-43 IN90-003 208
examination schedule requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-14 IN86-003B 176
examination volume — Category B-B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-44 IN96-008 336
flow size — acceptance standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-35 IN96-007 329
examination volume — Class 1 and 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-43 IN96-004 336
XI-1-92-24 IN91-014 255
fusion welding — repair of tube or tubesheet. . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-95-33 IN94-031 322
half bead weld repair — automatic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-09 BC82-604 9
XI-1-83-09R BC82-604* 10
items NPS 1 and smaller — exemption from examination . . . . . . . . . . . . . . . . . XI-1-98-09 IN97-018 365
items NPS 1 and smaller — requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-86 BC85-113A 82
XI-1-83-86R BC85-113A* 102
multiple components — NDE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-15R BC85-130* 135
XI-1-86-26 IN86-002 110
multiple loop piping — inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-15R BC85-130* 135
NDE examination requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-51 IN86-027 129
nonpressure retaining . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-28R BC83-344* 185
nozzle-to-vessel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-98-36 IN98-025 387
overlay cladding to replacement parts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-36 IN86-021 121
Welder
qualification. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-55 BC84-322 56
XI-1-98-53 IN99-015 400
qualification of — simultaneously . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-35 IN89-006 204
requalification — change in contractor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-43 BC84-179 44
required qualification — Section IX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-01 IN87-036 165
supervision. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-81 BC84-687 78