L/V28/32H
Description:
Hand tools:
Related procedure:
Data:
97.24 - ES0S
MAN Diesel
L/V28/32H
Cleaning and Inspection of Big-end Bore. Screws, which are damaged as mentioned above or
cannot be turned into the threaded holes by hand,
The connecting rod is cleaned on all machined must be renewed.
surfaces.
The serrated joint faces and threaded screw holes Measurement of Big-end Bore.
are to be degreased with a volatile solvent and blown
dry with working air.
The connecting rod screws are to be carefully clean- Five different diameters are measured in the middle
ed. of the boring, see fig. 1 and registered in the scheme
"Connecting Rod Inspection". See page 4.
The threads are inspected for seizures and tested
in the threaded holes in the connecting rod. The test The maximum ovalnees is calculated as the dif-
must confirm, that the screws can be turned into ference between biggest and smallest diamenter
bottom position by hand. The contact surface of the measured. For maximum allowable ovalness see
screw heads is inspected for seizure and pittings. page 600.35.
97.24 - ES0S
MAN Diesel
Working Card 606-01.15
Page 3 (4) Connecting Rod Edition 04H
L/V28/32H
If the ovalness exceeds this value, reuse must be Please note that squares for statement of information
rejected and a new complete connecting rod, inclu- and identification, should also be properly filled in.
ding new screws and new bearing shells has to be
mounted in the engine.
Connecting Rod Bush.
to be to be
reused rejected
97.24 - ES0S
MAN Diesel
L/V28/32H
08028-0D/H5250/94.08.12