You are on page 1of 4

Safe Use of M obile Cranes in

Constr uction Sites


OSD / ENG CIR / LE / 4/01

By Occupation Safety and Health Division


Ministry of Manpower Causes of Crane Accidents

The main causes of accidents that had


Introduction been identified can be traced to the
There are approximately 10,000 mobile following:
cranes being used in Singapore. The
majority of these cranes are used in the a) Lack of planning and supervision;
construction industry to increase the b) Incorrect siting or setup of cranes;
productivity of the building construction. c) Failure to correctly calculate or
However the misuse, failure to follow estimate the load;
safe practices and procedures or d) Failure of personnel to carry out the
complacency often led to accidents. correct procedures;
Such accidents could have a e) Careless & Complacent;
catastrophic impact to the safety of f) Use of wrong lifting gears;
workers and members of public. g) Faulty devices or machines;
h) Lack of proper maintenance.
This safety circular is meant to provide
Accident Case 1: August 2000
guidelines for the safe use of mobile
cranes in construction sites.

Accident Statistics
In year 2000, there were a total of 32
incidents involving mobile cranes, of
which 2 cases resulted in fatalities and
16 cases resulted in varying degrees of
injury. Another 14 cases involved
damages to properties.
The boom of a crawler crane flipped
backwards when the steel casing (for
No. of accidents involving
bore piling operation) it was lifting broke
mobile cranes in year 2000 at the tip where it was shackled. The
16 boom and the hook block landed on the
expressway and hit a vehicle.
12

Selecting the crane


8 Cranes should always be selected to
handle the maximum anticipated load
4 with capacity to spare. Other
consideration for the selection of the
0 cranes are the nature of lift, ground
Resulted in Resulted in Resulted in condition, site constraints, etc.
death of Injury to damages to
worker workers properties
only
Safe Use of Mobile Cranes in Construction Sites 1
The crane operator timber mats should be placed under the
The crane shall only be operated by a outriggers to evenly distribute the
trained and competent operator. The weight.
operator must also be registered with
the Chief Inspector of Factories. The crane should also be positioned so
that:
Documents for the crane
When the crane arrives on site, the a) The operator has a clear view of
the operation as far as practicable;
following documents should come along
with the crane for inspection and review b) There is sufficient operating space;
when requested: c) It is well away from edges of
excavation and fixed structures
a) A valid Certificate of Test / Thorough which people may be trapped by
Visual Examination of Lifting the moving parts such as
Equipment for the mobile crane (LM counterweights, etc
Certificate);
Planning and Supervision
b) Valid Certificates of Test / Thorough
Visual Examination of Lifting
All lifting operation should be properly
Equipment for all lifting gears that planned by a competent person before
comes with the crane; the actual execution and not left solely
to the crane operator.
c) The log-book or log sheet for the
recording of the operational tests
carried out by the operator before the Investigation into crane accidents
start of every workshift; revealed that one of the root causes of
these accidents was due to lack of
If the operator is unable to produce the proper planning and supervision. This is
above documents, the crane supplier particularly so for simple routine lifts.
should be contacted and the documents Hence, all contractors are advised not to
obtained before the machine is put into be complacent during any lifting
use. It is advisable to state that the operation, and to plan and supervise the
production of these documents will be operation carefully.
required when the crane is hired.
Site constraints that would have an
Siting of Crane impact on the safe operation of the
The stability of the crane depends lifting should be considered before the
heavily on the proper siting and setting execution of the lift. Examples of such
of the crane. Unless stated by the constraints are:
manufacturer, the crane should have its
outriggers fully extended with the a) Lifting next to or over an
wheels off the ground. The ground excavation pit;
should be level and b) Materials or machines placed
capable of supporting along the access way thereby
the full weight of the reducing the available space to
crane and its load. In extend the outriggers;
addition, sufficient and c) Site is located nearby busy traffic,
suitable packing in the or existing building or structures.
form of steel plates or

Safe Use of Mobile Cranes in Construction Sites 2


Careful planning is especially critical fpr All contractors are advised to familiarise
difficult lifts such as pick and carry themselves with the duties of these
operations, tandem lifting and tilt-up appointees as spelt out in the regulation
operation. and ensure that the only trained and
competent personnel are appointed.
“The change in radius caused by
booming down and/or telescoping out In the case where the lifting operation is
shall be considered when determining out of the view of the operator (such as
the lifting capacity of the crane. The
lifting a load from the rooftop of a
reduction in the boom angle, caused by
building), the occupier is obligated to
the load when just lifted off the ground,
and the consequential increase in the appoint sufficient number of signalman
radius shall also be considered in for the operation.
determining the safety of a lift.”
– SS CP 37: Safe Use of Mobile Cranes The Load
The weight of the load should always be
Special consideration should be given known from specifications or through
when the load is required to be placed calculations. It is important to note that
at a distant further away from the crane the safe working loads (SWL) indicated
than when it is being picked up, i.e. an in most load capacity charts are gross
increase in the crane’s working radius. SWL. This means that the weight of the
hook block, and all lifting gears used
Personnel must be deducted from this gross SWL
The Factories (Operation of Cranes) to obtain the net SWL that the crane is
Regulations 1998 requires the able to lift at that configuration.
appointment of the following personnel
for all mobile crane operation: Load Radius Indicator
• Trained lifting supervisor; The mandatory load radius indicator
• Trained riggers; and gives the safe working load at the
• Trained signalman. configuration that the crane has been
set, and gives a warning signal when
Fatal Accident Case 2: August 2000 the radius is unsafe. The indicator:
• must be calibrated regularly;
• must be configured for both main and
auxiliary hooks (when both hooks are
used)
• The operator must be trained to use /
The deceased set the indicator correctly to tally with
and the the actual configuration adopted;
platform fell
from the 5 th
storey to the It is important to note that the load
ground. radius indicator served primarily as an
operational aid. Although the indicator
The crane operator lifted and placed a can warn the operator of an impending
pallet of bricks onto a work platform on
th
the 5 storey without being instructed or overload, it should not be used as the
signaled to do so. The platform only tool to test the stability limit of the
collapsed together with a worker. The crane during operations.
worker died subsequently

Safe Use of Mobile Cranes in Construction Sites 3


Supervisors and foreman are advised Accident Case 3: June 2000
not to rely on the operator to use the
indicator to determine the weight of the The crane operator had lowered his hook
block from an opening into the basement
load. They should instead have prior infrastructure. The workers at the
knowledge of the weight of the load. basement then pulled the hook block
This is especially critical when the lifting away from the opening and rigged up a
operation involves the dismantling of truss structure. They then gave the
machinery or structure from heights. signal to the operator to lift. The boom of
the crane snapped when the load was
dragged out.
Singapore Standards Code of

û
Practice 37: Safe Use of Mobile
Cranes: 2000
The Factories (Singapore Standards
and Code of Practice) Order 2001 has
gazetted the SS CP 37 as a mandatory
code for compliance by any user. The Dragging is expressively forbidden
code provides comprehensive
requirements on the application, safe
operation, maintenance and testing of Checks and Maintenance
mobile cranes. The crane should be in good working
condition when it arrives on site and
The guidelines and requirement laid out before the start of the workshift. In
in this circular are extracted from the addition to the statutory annual
code. inspection, the manufacturer’s
The crane's safe working load is always
recommendation on the inspection and
indicated for freely suspended loads. It is maintenance regime should also be
expressly forbidden to use the crane to drag followed closely.
any load, or any operation that may cause the
hoist line to be out of plumb. Types Checks
Slewing should be done slowly to maintain • Check limit switches e.g.
control of the load. over-derricking; over
hoisting
Functional
Tag lines should be used where applicable to • Slewing
Checks
minimise swing • Telescoping
• Travelling
The operator should stay at the controls at all
• Safety devices
time when the loads are suspended.
• Wire ropes
Interpolation of the safe working load in the • Rope terminations
load capacity is disallowed unless specifically Integrity • Hook block
allowed by the manufacturer. Extrapolation is Checks • Boom section
strictly disallowed. • Rope pulleys
• Rope guards
No additional counterweight shall be added to The checks listed in this table are not exhaustive.
the crane unless specifically allowed by the
manufacturer.
All contractors are advised to familiarise Issued by
themselves with the requirement THE CHIEF INSPECTOR OF FACTORIES
stipulated in the code. MINISTRY OF MANPOWER

Safe Use of Mobile Cranes in Construction Sites 4

You might also like