RISK MANAGEMENT PLAN FOR ORIENTATION

What can hinder the smooth implementation of the Orientation Module? How will you prevent them or mitigate its possible
adverse effect(s) on the plan? Answer these questions using the table below and discuss them with your colleagues in LAC or
with your assigned Coach.

DESCRIPTION OF LIKELIHOOD TO SEVERITY OF PREVENTIVE ACTION MITIGATION ACTION


RISK HAPPEN (Very Likely, EFFECT ON THE (What to do to prevent (If or when a risk
Likely, Unlikely) PROJECT the risk from occurring) happens, what do you
(High, Medium, Low) need to do to mitigate
its effect on the project)

100% Attendance Likely Medium Inform them on the Ask a companion to


importance of this mentor the absent
orientation in advance member

Lack of Gadgets like Likely Medium Let them use the e- Gadget sharing
laptop classroom

Punctuality Likely Medium Encourage them to Companion tutorial


come early

Power Interruption Likely High Charge fully all gadgets Use Generator

Note: Add more rows as needed.