COMMENTS ON AIR CONDITIONING PACKAGE OF 2 X 150 MW.

1) For Main control room BC BAY 11.5mtr:- 63105mm X 10000mm.


2) AHP PLC + Control room :- 5000mm X 7000mm.
3) ESP Control room (Boiler-1&2) :- 6000mm X 8000mm.
4) ESP Control room (Boiler-3&4) :- 6000mm X 8000mm.
5) DM Plant :- 6000mm X 8000mm
6) CW SWGR (Cooling water RIO) :- 5000mm X 10000mm.

Forced Ventilation.

1) ESP Control room (Boiler-1&2) :- 26500mm X 8000mm.


2) ESP Control room (Boiler-3&4) :- 26500mm X 8000mm.
3) Main control room LT MCC (Unit-1) :- 21000mm X 10000mm.
4) Main control room LT MCC (Unit-2) :- 24000mm X 10000mm.
5) Compressor House SWGR :- 23000mm X 7000mm.
6) BC BAY 0.5mtr :- 135000mm X 10000mm.
7) BC BAY 8.5mtr :- 135000mm X 10000mm.

AGENDA FOR MEETING WITH SIEMENS