Professional Documents
Culture Documents
HINDUSTAN PETROLEUM
CORPORATION LTD ..... Petitioner
Versus
AND
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
Introduction
Factual Context
10. Whilst DSM claims that HPCL was negligent in supplying Form
– Cs, even though in some cases, HPCL had received the same from the
State Tax Department; HPCL claims that the delay was on account of
reconciliation and/or on the delay on the part of the State Sales Tax
Department in issuing the necessary Form-Cs.
14. DSM took steps to assail the said demands and also preferred a
Writ Petition (being W.P. No. 1453 (MB) of 2009 in the High Court of
Allahabad) impugning the sales tax/penalty demand. DSM also pursued
with HPCL for an indemnity against any liability and to pay the amount
due.
15. Since DSM had suspended the supplies pending resolution of the
issue regarding submission of the Form-Cs by HPCL, HPCL considered
the same as a breach of the ‘Take or Pay/Supply or Pay’ Clause and, by
a letter dated 18.05.2009, put DSM to notice that it would be liable to
pay penalty of a sum of ₹28,85,945/-. Similarly, by a letter dated
17.09.2009, HPCL put DSM to notice regarding levy of penalty of
₹55,45,710/- under the ‘Take or Pay/Supply or Pay’ Clause. By a
subsequent communication dated 20.08.2010, HPCL also claimed an
additional amount quantified at ₹3,34,755.
21. The Arbitral Tribunal entered upon reference and by the first
procedural order, fixed a schedule for completion of the pleadings.
DSM filed its Statement of Claims on 10.10.2011. DSM claimed a sum
of ₹56,86,050, which according to it was deducted from the invoices
raised by it, along with interest at the rate of 24% compounded annually.
DSM also claimed a sum of ₹1,40,21,870/- along with interest at the
rate of 24% per annum at annually compounded rates, in terms of
HPCL’s obligation under the ‘Take or Pay/Supply or Pay’ Clause under
the agreements in question, as according to DSM, HPCL was
responsible for suspension of the supply of ethanol. DSM also claimed
25. The concerned Trade Tax Authorities passed the final assessment
orders on 28.06.2012 and 01.08.2013 setting aside the Sales Tax
demands raised, at the maximum rate on DSM.
26. Both the parties have assailed the impugned award. HPCL
contends that the award of a sum of ₹35,30,363/- awarded in favour of
DSM is patently erroneous as no such sales tax liability had crystallized
on DSM. DSM was contesting the demands raised by the Uttar Pradesh
Sales Tax Authorities and the Arbitral Tribunal had found that HPCL
had provided the necessary Form-C to DSM. Albeit after some delay.
27. HPCL also assails the decision of the Arbitral Tribunal to award
further sums to DSM, which included a sum of ₹ 8,45,034/- on account
of obligations under the ‘Take or Pay/Supply or Pay’ Clause of the Fifth
Agreement.
29. DSM also assails the impugned award on, essentially, two
grounds. It contends that the levy of damages under the ‘Take or
Pay/Supply or Pay’ Clause [Clause-3 under the Initial Agreements] is
patently erroneous for two reasons. First, that DSM had not breached
any of its obligations under the Initial Agreements. It had suspended the
supply of ethanol solely because HPCL had breached its obligations to
pay the sales tax or to provide Form-Cs in a timely manner. Resultantly,
32. He submitted that HPCL could either establish that it has suffered
a loss or establish that the penalty as provided under the ‘Take or
Pay/Supply or Pay’ Clause was a genuine pre-estimate of the loss,
which could not be quantified. But HPCL had done neither. It had not
pleaded that it was not possible to establish the loss suffered by it on
account of short supply of ethanol. It had also not produced any
evidence to establish the loss suffered by it.
41. Undisputedly, DSM would not be liable to pay any amount under
the aforesaid clause if it was entitled to suspend the supplies on account
of non-supply/delay in providing the Form-Cs. It is also not disputed
that DSM had called upon HPCL to indemnify it for any loss that it may
incur on account of delay or deficiency in providing the Form-Cs but
HPCL had failed to provide any such indemnity.
46. Insofar as issue no. (ii) is concerned, the Arbitral Tribunal held
as under:-
48. DSM had submitted that the delay in providing the Form-Cs was
about three years in some cases. The Arbitral Tribunal’s conclusion that
there was delay in furnishing of the Form-C’s did indicate that the
Arbitral Tribunal had accepted that HPCL has breached its obligations.
The Arbitral Tribunal’s reasoning that even though there were a number
of instances of delay in furnishing the Form-Cs by HPCL, but since no
Form-C was pending, the claimant was not justified in withholding the
supplies to some extent, fails to address the question. This is because
DSM had suspended the supplies at a time when the Form-Cs was
pending, and that issue was not resolved. It remained unresolved for a
considerable time. Therefore, it is difficult to follow as to how
furnishing the Form-Cs at a later date would absolve HPCL of its failure
to provide the Form C’s at the material time.
54. In the given circumstances, this Court is of the view that the
award of ₹88,14,785/- in favour of HPCL, is not sustainable.
55. It is also material to note that DSM had also made a similar claim
under Clause 3 of the Initial Agreements and Clause 5 of the Fifth
Agreement. DSM’s claim in respect of the Initial Agreements was
rejected as the Arbitral Tribunal had found that DSM had failed to
supply ethanol and there was no failure on the part of HPCL to
indent/accept the same. However, DSM’s claim under Clause 5 of the
Fifth Agreement was allowed. As conceded, the award of ₹8,45,034/-
in favour of DSM is also liable to be set aside, as DSM had also failed
to establish the loss suffered by it.
57. The contention that HPCL was entitled to amend the counter-
claim and the Arbitral Tribunal had erred in not permitting the same, is
clearly unmerited.
58. Section 23(3) of the A&C Act, which was relied on behalf of
HPCL, reads as under:-
59. It is clear from the plain language of Section 23(3) of the A&C
Act that a party is entitled to amend or supplement its claim unless the
Arbitral Tribunal considers it inappropriate having regard to the delay
in making any such amendment. In the present case, there was an
inordinate delay on the part of HPCL in filing its counter claim in the
first place.
60. The learned Arbitrator entered upon reference and by the first
procedural order dated 09.09.2011, fixed a schedule for completion of
the pleadings. DSM was directed to file a Statement of Claims along
with the relevant documents on or before 29.09.2011 and HPCL was
directed to file its reply to the Statement of Claims on or before
20.10.2011. The first hearing was scheduled on 29.10.2011. DSM
sought extension of ten days’ time for filing its Statement of Claim and
did so on 10.10.2011.
61. HPCL did not file its reply within the stipulated time. It was also
not represented before the Arbitral Tribunal at the first hearing, that is,
on 29.10.2011. The Arbitral Tribunal directed HPCL to immediately
file its reply and DSM was directed to file its rejoinder within a period
of fifteen days from receipt of HPCL’s reply.
63. HPCL filed its reply on 02.01.2012 disputing the claims made by
DSM. DSM filed its rejoinder to the said reply on 22.02.2012.
Thereafter, on 20.03.2012, HPCL filed its sur-rejoinder and also
included a counter claim, which comprised of a tabular statement
indicating calculation of penalty aggregating to ₹88,14,785/- under the
‘Take or Pay/Supply or Pay’ Clause. DSM filed its reply to the counter-
claim on 10.04.2012.
64. The Arbitral Tribunal listed the matter for hearing on 04.05.2012
and on that date, struck the issues to be decided. After the issues were
framed, both the parties also agreed not to lead any further evidence.
67. It is apparent from the above, that HPCL had delayed in filing its
counter claim, which was filed along with its sur-rejoinder after the
pleadings were complete. The application to make an amendment was
moved at the stage of final hearing of the claims. Undeniably, the same
was at a much belated stage. Thus, the decision of the Arbitral Tribunal
to deny HPCL’s request to amend the claim cannot be faulted.
69. The petitions are disposed of in the aforesaid terms. The pending
application is also disposed of.
VIBHU BAKHRU, J
JANUARY 06, 2022
pkv/v
Click here to check corrigendum, if any