1. Madayaw Residences - AFP/PNP Project Davao Brgy. Talomo, Davao City, Davao del Sur
a. Provide copy of TE 3
2. Freedom Residences (Stonerise Homes AFP/PNP Housing Project) Brgy. Cuambogan, Tagum City
a. Provide copy of Certificate of Project Completion.
b. Indicate % actual accomplishment
c. For reported fully completed units, is there a temporary water and power?
3. Bansalan Resettlement Project Brgy. Sto. Niño, Bansalan, Davao del Sur
a. Bakit last report date started is December 26, 2019 and completion date is May 24,
2020. As of January report, date started is January 3, 2020 and completion date is June
1, 2020. Bakit po kaya?
b. Yung target po na 75.17% based on the approved TE4 na po ba yun or TE5?