Professional Documents
Culture Documents
Safety Status:
Onsite Personnel:
Date: 4 Sept 5 Sept 6 Sept 7Sept 8Sept 9Sept 10Sept TOTAL Comments
ABSG 11 12 11 16 14 2 66
LSEF 42 42 48 43 45 26 246
PEMSA 5 5 4 4 4 22
Sun Packing 9 7 6 6 10 38
Hansa Meyers 9 8 3 3 23
Maxim 1 5 6 12
Hurricane Harvey may impact schedule and an updated version of the schedule will be issued.
Executive Summary:
Page 1
Weekly Summary Report
Monday September 4:
Tuesday September 5:
Safety meeting JSA for Hansa Meyers Crane Operations and Lonestar Crane Operations.
Material Disposition log is being updated daily.
Lift Report is updated daily as new equipment and modules are being rig down.
Continue disconnecting and rolling back power cables on both sides of module 0030B (drag
chain)
Compile work packs for the rig down activity files.
Prep documents for further rig down sign offs.
Continue conversion of the marked up drawings, photographs, work instructions, etc. for Rig Up
manual for use on site.
Lonestar crew spend most of day taking out pins on module 9010B
Identified walkway pieces that were not labeled.
Working on module work packs for items completed at site.
Rig down the following: Module 4210 and 9010 West crane base
Dave Ellis visit GDS location where the top drive is being assessed/examined.
Wednesday September 6:
Safety meeting JSA for Hansa Meyers Crane Operations and Lonestar Crane Operations.
Material Disposition log is being updated daily.
Lift Report is updated daily as new equipment and modules are being rig down.
Resumed disconnecting cables from M3320 Gen # 3 module to M4320 module. 100% completed
Continued disconnecting cables from module M8010 stairway tower. 100% completed. Module
M8010 Ready for lift.
Continued disconnecting 600V high voltage cables from north end of M0030B drag chain. Pulled
cables back to cable tray on M4120 module. 50% completed
Compile work packs for the rig down activity files.
Prep documents for further rig down sign offs.
Continue conversion of the marked up drawings, photographs, work instructions, etc. for Rig Up
manual for use on site.
Mechanical- at LSEF
9020B East lower crane base stair way removed. 09:08hrs.
Lonestar crew removing pins from upper DES modules and brackets.
Walk through and signoff by Wavecrest, ABS, and Lonestar of modules
Working on module work packs for items completed at site.
Work on sign off documentation for prior removals
Working on Rig Up manual.
Page 2
Weekly Summary Report
Thursday September 7:
Safety meeting JSA for Hansa Meyers Crane Operations and Lonestar Crane Operations.
Material Disposition log is being updated daily.
Lift Report is updated daily as new equipment and modules are being rig down.
Electrical- At LSEF
Continued disconnecting cables on module 0030B drag chain to cable tray in module 4120.
Cables were rolled back and secured on both ends. (100% Completed).
Witnessed completion of lifts on mud pumps 1-3. Mud pumps were staged on west end of rig.
Continued to update electrical work packs
Compile work packs for the rig down activity files.
Assist in development of the Module Installation Sequence.
Continue conversion of the marked up drawings, photographs, work instructions, etc. for Rig Up
manual for use on site.
Lonestar removing pins and prepping Mud pumps #3, #2, #1 and modules M3110 and 3120 for
removal.
Working on module work packs for items completed at site.
Working on Rig Up manual.
Rig down the following: Mud Pump inside Ladder 1, Mud Pump inside Ladder 2, Mud Pump
inside Ladder 3, Mud Pump #3, Mud Pump #2, Mud Pump #1, Module 4110 West Mud Tank
Shipped out following Walkway’s and Ladder’s: DES 5230-D-2 Walkway, DES 5320-G Walkway,
DES 5330-H Walkway, Bell Nipple Piping 3, Bell Nipple Piping 2, Bell Nipple Piping 1, DES 5410-
Z, DES 5310-S-3, DES 5310-T, DES 5310-W, DES 5310-P-1, DES 5310-S-1, A Frame Spreader
Bar
Maxim Crane (Hansa Meyer’s Sub Contractor) went off Charter at 1550, 7 Sep, 2017.
Page 3
Weekly Summary Report
Cage Repairs
Cage is repaired and ready for paint.
Friday September 8:
Saturday September 9
Page 4
Weekly Summary Report
Page 5
Weekly Summary Report
Photos:
Page 6
Weekly Summary Report
Page 7