Qualities of good tender
• Should be based upon DEFINITE and DETAILED
information
• Drawings to be supplied wherever details are
involved
• Factory made products should be supplied with
their trade names
• Avoid the phrase “As Approved by the Architect”
• Mention “BASIC PRICE OF THE MATERIAL” when
trade name cant be given
• All tenderers shall be given equal and same
information
Types of Tender
ITEM RATE
TENDER
LUMPSUM
TENDER
COST + PERCENTAGE
TENDER
LABOUR TENDER
TENDER FOR
DEMOLITION WORK
ITEM RATE TENDER
╬ Work based on the rates of various items of work.
╬ Contractor is required to fill in the rates of each and every item both in
╬ The measurements of the work done are recorded and contractors bill
╬ It is suitable for all types of civil works like buildings, roads, bridges etc
LUMPSUM TENDER
╬ Work based on the rates of various items of work.
╬ Contractor is required to fill in the rates of each and every item both in
╬ The measurements of the work done are recorded and contractors bill
╬ It is suitable for all types of civil works like buildings, roads, bridges etc
Methods of Inviting Tenders
BILL OF QUANTITIES
DRAWINGS
ARTICLES OF
AGREEMENT &
GENERAL CONDITIONS
OF CONTRACT
Earnest Money Deposit [EMD]
╬ Initial Deposit enclosed with Tender
╬ Payment shows contractor’s interest in work.
╬ Amount of EMD - 1% of Estimate Amount.
╬ Main intension/purpose – to see fair competition takes place.
╬ Paid by Demand Draft payable at the place of Employing Agency/
Owner. Also accepted in cash.
╬ Remains with Employer/Owner till contractor is selected, sometimes
this period is extended till work is awarded.
╬ EMD of selected contractor is converted into Security Deposit or
adjusted towards Security Deposit.
╬ EMD of contractor’s whose offer/Tender is not accepted should be
returned.
╬ Does not bear any interest
Security Deposit
╬ PURPOSE
a) Contractor fulfills all terms and conditions of contract.
b) Carries work to entire satisfaction
c) Maintain expected progress of work.
╬ 5% (Five Percent) of estimated amount
╬ Asked and to be Paid by Successful contractor
╬ Paid by Cash, Fixed Deposit Receipts. Also divided into instalments.
First installment - before entering into contract
Further installments - deducted from every Running Bill.
Security Deposit
╬ Forfeited - If contractor fails to comply all the conditions
╬ Does not bear any interest
╬ To be returned to the contractor after defects liability period is over.
╬ If contractor does not attend and cures defects, then work is done
through any other suitable agency and amount incurred is deducted
from contractor’s Security Deposit and balance amount is returned.
2. Work is commenced after Work cannot be started all Work can be commenced
completing formalities, formalities like finalisation immediately without waiting for
invitation and acceptance of of cost, acceptance of all formalities
Tender Tender and agreement
3. All plans, specifications, All details, plans, elevations, All details, elevations, sections
schedule of items are sections, specifications need not be ready prior to
prepared before inviting schedule of items are commencement of work.
Tender. Elevations and details prepared before inviting
can be issued during the tenders.
progress of work.
Comparative statement of Types of Tenders/
Difference/Characteristics
ITEM RATE LUMP SUM COST PLUS PERCENTAGE
4. Quality of materials and good Quality of materials and Standard quality of materials
workmanship assured good workmanship cannot and good workmanship at the
be assured cost of Owner/ economy
6. Final cost of work is not known Final cost of work is known Final/Total cost of work is not
before completion of work before commencement of known in advance
work
9. Time limit for completion of Time limit for No time limit for the completion
work is strictly adhered completion of work of work
strictly enforced
10. Scope for selection of Scope for selection of Scope for selection of contractor
contractor is wide contractor is less is wide
11. Cost of completed project is Cost of project is Cost of completed project is not
guaranteed if variations are guaranteed if proper guaranteed
limited control over variations
Comparative statement of Types of Tenders/
Difference/Characteristics
15. More work load for Work load of Architect and Architect’s and engineers work
architect and engineer. engineer is reduced load is reduced. However
Measurements of all items considerably since owner’s work is increased.
are required to be measurements are not to Owner has to bear loss and
recorded. Contractor is be recorded. Contractor is wastage of materials from site
responsible for loss and responsible for loss and
wastage of materials from wastage of materials from
site site