Professional Documents
Culture Documents
4. Architecture has been defined as a art or science of design, construction, style, appearance of any structure
with aesthetic character.
a) True b) False
5. The period of notice to be given to rescind the contract will be _____ days.
a) 60 b) 30 c) 15 d) 45
6. The architect shall be compensated actual expenses incurred during extended period of contract, if
construction period runs beyond ______months of the completion period as per construction contract.
a) 3 months b) 6 months c) 12 months d) 18 months
7. If the creator architect seeks protection under the Copyright Act, 1957, he has to prove that is work is :-
a) Having artistic character b) Having artistic design c) Option (a) & (b) d) None of the above
8. contractor‟s cannot be compelled to complete the work earlier than the agreed date unless :-
a) There is an express term authorizing architect to require acceleration
b) The parties have agreed by consent to acceleration against some consideration to be paid to the contractor
(a new contract)
c) It can be proved that there is an implied instruction from the owner to that effect
d) All of the above
9. The Architect‟s first duty on being commissioned for a job is to inspect the site to find out the physical
condition of the plot.
a) True b) False
10. Minimum fees of architect for all projects other than housing is :-
a) 2.5 percent on the cost of works assigned b) 5 percent on the cost of works assigned
c) 7.5 percent on the cost of works assigned d) 10 percent on the cost of works assigned
UNIT 2
1) Site evaluation, analysis and impact of existing and proposed development on its immediate environs are?
A) Duty of Engineer B) Service of Supervisor
C) Services of Architect D) None of the above
3) How much fees payable on submitting the conceptual designs and rough estimate of cost?
A) Only 15 % of total fees B) Not such mentioned
C) 10% of total fees payable D) Rs 20M or 5% of fees
4) A part from the professional fee, the client shall pay to architect documentation and communication @
______ % of the Professional fees payable to the architect.
A) 15% B) 10% C) 5% D) None of the Above
6) Agreement between the architect and client may be terminated by either one giving the other a written
notice of not less than
a) 45 days b) 30 days c) 60 days
8) Architect is required to maintain all records related to project for a minimum project of ____ years after the
Issuance of certificate of virtual completion.
a) 2 years b) 4 years c) 6 years d) 8 years
9) The architect‟s liability shall be limited of maximum period of _____ years after the building is handed over
to/occupied by the owner, whichever is earlier.
a) 3 years b) 4 years c) 5 years d) 6 years)
10) How many sets of drawing the architect shall supply to the clients free of costs?
a) 2 sets b) 4 sets c) 6 sets d) 8 sets
11) Failure to take reasonable degree of care in the course of his engagement for rendering professional
services is called as...?
a) Negligence b) Duties c) Both a and b d) none of these
12) Upon client‟s / statutory approval necessary for commencement of construction payable fees is ?
a. 25% of the total fees b. 30% of the total fees
c. 20% of the total fees d. 35% of the total fees
13) On submitting working drawings and details required for commencement of work at site payable cost is ?
a. 60% of the total payable cost at stage 2 to 5 b. 65% of the total payable cost at stage 1 to 5
c. 55% of the total payable cost at stage 2 to 5 d. None of these.
14) Percentage of the total cost of the project does an architect can charge for the single block housing having
site area up to 0.5hectare..?
a. 5% of the total cost of the project b. 50% of the total cost of the project
c. 6.2% of the total cost of the project d. None of these
15) Percentage of the total cost of the project does an architect can charge for the individual house?
a. 0.5% of the total cost of the project b. 0.8% of the total cost of the project
c. 7.5% of the total cost of the project d. 0.6% of the total cost of the project
17) Apart from the professional fee, the client shall pay to the architect documentation and communication
charges, @ 10% of the professional fee payable to the architect at all stages are known as..?
a. Documentation and communication charges b. site visit charges
c. Architectural charges d. None of these
18) Which section is imposed on the architect, when an architect found guilty of professional misconduct?
a. Section 30 b. Section 40 c. Section 50 d. Section 6
22) Which Act defined deficiency means any fault, imperfection, shortcoming, or inadequacy in the quality?
a) Architect Act 1989
b) Indian Act 1872
c) No such Act
d) Consumer protection act,1986
23) What are the circumstances involved in Exception if the damaged to the building has occasioned?
a) Use of building for the purpose other than for which it has been designed.
b) Any changes or modification to the building carried by the owner.
c) Any changes or modification to the building carried out by consulting another architect.
d) All of the above
24) What is the minimum fee for fees an architect can charge for repetition of units in same campus?
a) 2.5% on the cost of work assigned b) 10% on the cost of work assigned
c) 5% on the cost of work assigned d) 4% on the cost of work assigned
25) In case of architect closing his business or client has terminated the agreement; the client does not have
the right to appoint another architect to complete his work.
True
False
UNIT 3
1. The architect does not need to provide any agreement with them defining their scope of work,
responsibilities, functions, fees and mode of payment.
True
False
2. A restriction on the architect to take another architect as a partner is the latter stands disqualified for
registration by the reason of the fact that‟s his name has been removed from register under section________
of architect‟s acts 1972.
a) Section 29 b) Section 30 c) Section 29 and section 30 both d) None
4. Quantum meruit - a reasonable sum of money to be paid for architects or work done when the amount due
is not stipulated in a legally enforceable contract.
True
False
6. the overall cost of the employment of the clerk of works shall not exceed_______% of overall cost of project
a) o.5% b) 1% c) 0.2% d) 2%
9) After completion of project, the architect has to prepare __ number of drawing sets?
a) 2 b) 5 c) 3 d) 1
11) The architect be paid for plans and preliminary work on percentage basis set out in R.I.B.A.
a) R.I.B.A.SCALE b) ARCHITECTS ACT 1972 c) Architects regulation 1989 d) none of the above
1) Tender is an invitation of offer for execution of Construction work under certain terms & conditions.
True
False
6) Earnest Money id Totally refundable to all the unsuccessful bidders with an interest deducted.
True
False
7) E.M. of Successful Bidder remains with the owner & once he________ shall be added to S.D.
a) Signs the contract
b) Completes the construction
c) Completes The defect liability Period
d) Signs Contract for Negotiation
8) In Case of this , if Contractor dose not come forward to take responsibility, The S.D can be utilized to
overcome damage.
a) Substandard Construction
b) Nonpayment of bills to pity contractors
c) Accidents
d) All above
10) Contractor can ask for deducting certain amount from his running bills in order to submit ______ this
amount is called as :
a) Security Deposit, Retention amount
b) Minimum amount of Interim certificates & Security deposit
c) Security deposite & 10%
d) None of above.
UNIT 5
Q.1.Which act India contract does set a guide line and the standard from of contract prepared by I.I.A..?
a. ACT 1972 b. ACT 1985 c. ACT 156 d. both a and b
Q.2. The contract is an agreement enforceable at law between which parties made by free consent of parties
competent to contract for lawful consideration and lawful object…?
a. Two or more parties b. Two or three parties c. four or five parties d. none of these
Q.3.which definition says a building or engineering contract may be defined as an agreement under which a
person undertakes for reward to carry out for another person works of a building or civil engineering nature..?
a. Hudson‟s definition says b. IIA definition says c. Both a and b d. none of these
Q.6. He is an engineer employed for the supervision of big work or works by the architect where he makes less
visits..?
a. Resident engineer b. Consultant c. Quantity surveyor d. All of these
Q.7. One who enters into contract undertaking to construct or supervise the work for a consideration..?
a. contractor b. builder c. consultant d. none of these
Q.8. How many types of contracts are there adopted for execution of work under government or private owners
depending on nature of work?
a. 5 b. 4 c. 3 d. 2
Q.10. A voluntary arrangement between two or more parties that is enforceable by law as a building legal
agreement is known as-
a. Contract b. job c. loan d. mutual fund
Q.11. which is type of mistake which occurs when only one party to a contract is mistaken as to the terms or
subject – matters
a. Mutual mistaken b. Bilateral mistaken c. Unilateral mistaken d. Individual mistaken
Q.13. In which type of contract measurement of executed items are not required to keep
a. Lump- sum contract b. Items rate contract
c. % rate contract d. Cost plus contract
Q.17. When owner of the project only performs duty of promoter and delegates duty of design and construction
of project to large consortium or firm then such contract is called as ---
a. Items rate contract b. All in contract c. Cost plus contract d. Lump – sum contract
Q.18. When owner is supplying material and bidder needs to complete all items through supplying labour then
such contracts are known as
a. Labour contract b. Material supply contract c. Entire contract d. Bot contract
Q.19.The contract is executed on stamp paper of the value as prescribed under the Indian Stamp Act 1899.
State whether true or false?
a. True b. False c. Maybe d. None of the above
Q.20. What does the condition no.4 of I.I.A form of contract says?
a. Owner reserves the right to increase any of the quantities
b. Owner reserves the right to decrease any of the quantities
c. Owner reserves the right to totally omit any item of work
d. All of the above
Q.22. How many sections do you have for dealt with following sections in the topic of contracts?
a. Section A - Section B b. Section C - Section D c. Section E - Section F d. Section A - Section M
Q.23. All contract bill is to be prepared in accordance with the principal of the standard method of
measurement of building works last before issue by the________.
a. Indian Standard Institution (I.S.I.) b. I.I.A c. COA d. AICTE
Q.24. In which clause of the I.I.A make a form of contract (1979Ed.) reference to the mode of measurements to
be adopted for preparation of the contract bills?
a. Clause 7 (1) b. Clause 8 c. Clause9 d. Clause 5
Q.25. Which present form of contract document being used by the Architect and Engineering for building
works?
a. Form 1979 (Approved by I.I.A, Mumbai) b. Form 1001
c. Form 2000 d. Form 2500
Q.27. In which type of contract owner acts as a promoter and deligates a large firm to perform both design and
construction?
a. Turn key contract b. Design build contract c. Item rate contract d. Cost plus contract
Q.28. When owner of the project only performs duty of the promoter and delegates duty of design and
construction of project to large consortium or firm then such contract is called as________________
a. Item rate contract b. All in contract c. Cost plus contract d. Lumpsum contract
Q.29. Which of these is not an advantage of lumpsum contract?
a. Owner does not require funds to start project b. Detailed measurement not required
c. Project cost is already known d. Speed in construction
Q.31. In lumpsum contract ,if contractor abondones work he or she is liable to ______________
a. To 10% penalty of total amount
b. To a 0.1% penalty per day of total amount
c. To get their terminated and receive work done amount
d. To be not eligible to get any amount of work done
Q.32. In which types of contract measurement of executed items are not required keeping?
a. Item rate contract b. Lumpsum contract c. Percentage rate contract d. Cost plus contract
Q.33. In percentage rate contract, bidders can bid their rate at _________rate indicates in bill of quantities.
a. At par with b. %above c. %below d. All of the above
Q.36. What are the instruction that Architects are allowed to change?
a. Corrective nature. b. Deductions from the work. c. Additions to the work. d. All of the above.
Q.37. The Indian Contract Act 1872 does not provide any special mode of acceptance.
a) True b) False
Q.41 A ________ is a contract to be executed on stamp paper and it provides for payment of specified sum
of money.
a) Bond b) Article c) Section d) None of the above
Q.42. What are the various duties and liabilities of Architect under the contract?
a) As agent of the owner b) To interpret the contract c) As Quasi- Arbitrator d) All of the above
Q.43. _____ is an agreement creating an obligation on the contractor to complete the work as shown in the
drawings on a unit rate per sq. mt. of plinth area.
a) Lump-Sum Contract b) Item rate Contract
c) Rates with percentage d) Cost plus fee Contract
Q.44. Some new architect will take the position of prime mover but he will not
be entitled to rule over any____?
a) Certificate b) Opinion c) Approval d) All of the above
Q.46. ________ is an agreement enforceable at law between two or more parties made by free consent.
a) Contract b) Register c) Chapter d) None of the above
Q.48. The Indian Contact Act provide some special mode of acceptance.
a) True b) False
Q.49. Under which act the value of stamp paper is prescribed for the
contract which is to be executed?
a) Indian Stamp Act 1885 b) Indian Stamp Act 1890 c) Indian Stamp Act 1899 d) Indian Stamp Act 1872
Q.52. Contractor should supply the owner priced copy of bill called quantities called contract bill.
a) True b) False
Q.53. How many clauses are there in agreement for contractual obligations?
a) 4 b) 5 c) 3 d) 2
2) Architects act follows objectives mentioned in the preamble is “to regulate the profession of architect by
evolving “code of ethics” and by laying down minimum standards of architectural education in India.”
True
False
3) Under which section of Architects act a person is prohibited from using the title „Architect‟ unless he is a
person registered in the register of architects?
A) Section 47 B) Section 29 C) Section 37 D) None of the above
4) A statutory body Constituted by Ministry of Human Resource Development, Govt. of India, under the
Architects act 1972 is?
A) Architects Registration council. B) Indian Institute of architect.
C) Council of Architecture. D) None of the Above.
5) Which is in charge for responsibility to regulate the education and practice of profession throughout India
besides maintaining the register of architects.
A) IIA B) Architects registration council.
C) Government department. D) Council of Architecture
6) Which is in charge for responsibility to regulate the education and practice of profession throughout India
besides maintaining the register of architects.
A) IIA B) Architects‟ registration council. C) Government department. D) Council of Architecture
7) _____ has framed Rules and _____ has framed regulations as provided for in the Architects act with the
approval of GOI.
A) GOI & COA. B) COA & IIA. C) IIA & GOI D) None of the above
8) It‟s in Power of the Council of architecture to enter into a contract and sue or be sued.
False
True
9) Who prescribe standards of professional conduct and etiquette and code of ethics for architects?
A) Architects‟ association B) GOI C) IIA D) COA
10) IIA is an organization and association of Architects.
True.
False.
11) In which year the Architect (Professional Conduct) Regulation was passed?
a) 1989 b) 1972 c) 1984 d) 1970
12) The lettering height for advertising the architect‟s name in front of his building should not exceed_______.
a) 5cm b) 10cm c) 15cm d) 20cm
13) According to Architect (Professional Conduct) Regulation an Architect can give gifts and discounts to the
client for gaining the work.
True
False
14) In which year the Indian Institute of Architects established?
a) 1919 b) 1979 c) 1980 d) 1917
15) In which year did the Bombay Architectural got associated with Royal Institute of British Architects?
a) 1920 b) 1979 c) 1925 d) 1952
18) Any person desirous of carrying on the profession of Architect must have registered himself with COA
True
False
26) A student who is also a member of IIA has right to vote for the president of IIA.
True
False
28) According to Architect (Professional Conduct) Regulation, an Architect cannot advertise his name but with
some exceptions.
True
False
32) COA allowed an architect to appoint registrar and other officers necessary to carry out its function ,
True
False
35) Why is register of architects kept who are registered under the act, on payment of prescribed fees?
a) To keep the list of architects and to renew their registration
b) To keep the attendance during the college
c) To know the whereabouts of the architects
d) None of the above
38) Which form is being use practically by all the architects and engineers subject to certain changes if any?
a) IIA form b) COA form c) None of the above
39) In which clause of the I.I.A make a form of contract (1979Ed.) reference to the mode of measurements to
be adopted for preparation of the contract bills?
a) Clause7(1) b) Clause7(2) c) Clause6(1) d) Clause6(2)
42) Use of title Architect Contravention will lead to fine on first conviction and on subsequent conviction with
imprisonment or fine or both.
True
False
43) The registration with COA entities a person?
a) To practice the profession of landscape architecture
b) To practice the profession of architecture, holds a Certificate of registration with an update renewals.
c) To practice business
d) None of the above
48) Advisor
a) Using best of his knowledge and experiences and is involved in interests of client.
b) Financial undertaking c) Both a and b d) None of the above
49) Role of architect is advisor, general manager, auditor, supervision, umpire, educator
True
False
51) Principal architect attends to contract, cost planning and time limit for completion of work
True
False
55) Identify the statement. Proper distribution of work among the staff members is assigned by principal
architect.
True
False
56) How does Architects get the works?
a) By friends and relatives b) By Advertisement
c) Through chartered accountants and other professionals d) All of the above
57) Which students can become a student member in IIA?
a) Any student from college of architecture
b) Graduate from IIA recognised college of architecture
c) An associate member with 36 years and old
d) Anyone can become the student member
58) The architect act provides for the establishment of council of architecture, a body corporate consisting of
members from institutions, council, central and state government nominees…?
True
False
59) What is the full form of (R.I.B.A)?
a) Royal Institute of Britannia Architects b) Royal Institute of British Architects
c) Royal Institute of Beloved architects d) None of the above
65) Which statements are true with respect to architect & his fellow brothers
i An architect should supplant other architects
ii Should not under cut fees merely to secure the project
iii Should not undertake the project where the architect has been assigned earlier without prior NOC from
retiring architect
a) i b) ii c) ii & iii d) i & iii
70) Which among the following statement is true ( duties and responsibilities of a principal )
a) To take active part in the social activities b) Less productivity
c) Long period of experience required to handle big project d) High salary
71) IIA was formed as an association made by the past student of architecture of -
a) Sir JJ school of art b) St Paul school and Jr college
c) Harvard of art school d) Delft university of technology