You are on page 1of 10

12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.

com

  Home Study tools


 My courses
 My books My folder Career Life 

Find solutions for your homework Search

home / study / business / accounting / accounting questions and answers / mini case: theassume you have just been hired as a financial analyst by tro…

Post a question
Question: MINI CASE:
TheAssume you have just been hired as a financial
… Answers from our experts for your tough
homework questions
(1 bookmark)

MINI CASE: Enter question


TheAssume you have just been hired as a financial
analyst by Tropical Sweets Inc., a mid-sized California
company
that specializes in creating exotic candies from tropical fruits
such as mangoes, papayas, and
dates. firm's CEO, George Yamaguchi,
recently returned from an industry corporate executive conference
in San Francisco, and one of the sessions he attended addressed
real options. Because no one at Tropical
Continue to post
Sweets is familiar with
the basics of real options, Yamaguchi has asked you to prepare a
brief report that
the firm's executives can use to gain at least a
cursory understanding of the topic. 20 questions remaining

To begin, you gathered some outside materials on the


subject and used these materials to draft a list of
pertinent
questions that need to be answered. Now that the questions have
been drafted, you must
develop the answers.
Answer just these five questions Only! Complete and
accurate as possible!! ASP! My Textbook Solutions
f. Use a financial option pricing model to estimate the value of
the investment timing option.
g. Now suppose that the cost of the project is $75 million and
the project cannot be delayed. However, if
Tropical Sweets
implements the project then the firm will have a growth option: the
opportunity to
replicate the original project at the end of its
life. What is the total expected NPV of the two projects if both
are implemented?
h. Tropical Sweets will replicate the original project only if
demand is high. Using decision-tree analysis, Macroecon… Principles of... Algorithms
estimate the value of
the project with the growth option. 8th Edition 1st Edition
7th Edition
i. Use a financial option model to estimate the value of the
project with the growth option.
View all solutions
j. What happens to the value of the growth option if the
variance of the project's return is 14.2%? What if it
is 50%? How
might this explain the high valuations of many start-up high-tech
companies that have yet to
show positive earnings?
Required is Only this five questions Please! Correct and
as accurate as possible! ASP!

Expert Answer

Anonymous answered this


Was this answer helpful? 0 0
71 answers

Ans;
https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 1/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com
f.               
Use a financial option pricing model to estimate the value of the
investment timing option.
  Answer:
Home Study tools
My courses
My books My folder
 Career Life
 
The option
to wait resembles a financial call option-- we get to “buy” the
project for $70 million in
one year if value of project in one year
is greater than $70 million. This is like a call option with an
exercise
price of $70 million and an expiration date of one
year.

X = Exercise Price = Cost Of


Implement Project = $70 Million.

RRF = Risk-Free Rate =


6%.

T = Time To Maturity = 1 year.

P = Current Price Of Stock = Current


Value Of The Project’s Future Cash Flows.

σ 2 = Variance Of Stock
Return = Variance Of Project’s Rate Of Return.

We explain how to calculate P and


σ2 below.

Just as the price of a stock is the


present value of all the stock’s future cash flows, the “price” of
the real
option is the present value of all the project’s cash
flows that occur beyond the exercise date. Notice that
the exercise
cost of an option does not affect the stock price. Similarly, the
cost to implement the real
option does not affect the current value
of the underlying asset (which is the PV of the project’s cash
flows). It will be helpful in later steps if we break the
calculation into two parts. First, we find the value of all
cash
flows beyond the exercise date discounted back to the exercise
date. Then we find the expected
present value of those values.

Step 1: Find the value of all cash


flows beyond the exercise date discounted back to the exercise
date. Here
is the time line. The exercise date is year 1, so we
discount all future cash flows back to year 1.

                                                
0           
1           
2         
3           
4

     
High                                             
$45     
$45        $45

     
Average                                        
$30     
$30        $30

     
Low                                      
       
$15     
$15        $15

   High: PV1 = $45/1.10 +


$45/1.102 + $45/1.103 = $111.91

      Average: PV1 =


$30/1.10 + $30/1.102 + $30/1.103 = $74.61

      Low: PV1 = $15/1.10 +


$15/1.102 + $15/1.103 = $37.30

The current expected present value,


P, is:

P = 0.3[$111.91/1.1] +
0.4[$74.61/1.1] + 0.3[$37.30/1.1] = $67.82.

For a stock option, σ2 is


the variance of the stock return, not the variance of the stock
price. Therefore, for a
real option we need the variance of the
project’s rate of return. There are three ways to estimate this
variance. First, we can use subjective judgment. Second, we can
calculate the project’s return in each
scenario and then calculate
the return’s variance. This is the direct approach. Third, we know
the projects
value at each scenario at the expiration date, and we
know the current value of the project. Thus, we can

https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 2/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com
find a variance
of project return that gives the range of project values that can
occur at expiration. This is
  the indirect
Homeapproach.
Study tools
 My courses
 My books My folder Career Life 

Following is an explanation of each


approach.

Subjective estimate:

The typical stock has σ2


of about 12%. Most projects will be somewhat riskier than the firm,
since the risk of
the firm reflects the diversification that comes
from having many projects. Subjectively scale the variance
of the
company’s stock return up or down to reflect the risk of the
project. The company in our example
has a stock with a variance of
10%, so we might expect the project to have a variance in the range
of 12%
to 19%.

Direct approach:

From our previous analysis, we know


the current value of the project and the value for each scenario at
the
time the option expires (year 1). Here is the time line:

                                             
Current
Value                   
Value At Expiration

                                                     
Year
0                                    
Year 1

     
High                           
$67.82                                  
$111.91

     
Average                     
$67.82                                    
$74.61

     
Low                           
$67.82                                    
$37.30

The annual rate of return is:

High: Return = ($111.91/$67.82) – 1 =


65%.

High: Average = ($74.61/$67.82) – 1 =


10%.

High: Return = ($37.30/$67.82) – 1 =


-45%.

Expected Return = 0.3(0.65) +


0.4(0.10) + 0.3(-0.45)

= 10%.

s2   =
0.3(0.65-0.10)2 + 0.4(0.10-0.10)2 +
0.3(-0.45-0.10)2

      =
0.182 = 18.2%.

The direct approach gives an estimate


of 18.2% for the variance of the project’s return.

The indirect approach:

Given a current stock price and an


anticipated range of possible stock prices at some point in the
future,
we can use our knowledge of the distribution of stock
returns (which is lognormal) to relate the variance of
the stock’s
rate of return to the range of possible outcomes for stock price.
To use this formula, we need
the coefficient of variation of stock
price at the time the option expires. To calculate the coefficient
of
variation, we need the expected stock price and the standard
deviation of the stock price (both of these
are measured at the
time the option expires). For the real option, we need the expected
value of the
https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 3/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com
project’s cash flows at the date the real option
expires, and the standard deviation of the project’s value at
  the
date
Home the real optiontools

Study expires.
 My courses
 My books My folder Career Life 

We previously calculated the value of


the project at the time the option expires, and we can use this to
calculate the expected value and the standard deviation.

                   
Value At Expiration

                                                     
Year 1

     
High                         
$111.91

     
Average                     
$74.61

     
Low                           
$37.30

Expected Value   
=.3($111.91)+.4($74.61)+.3($37.3)

= $74.61.

svalue    
= [.3($111.91-$74.61)2 +
.4($74.61-$74.61)2

+
.3($37.30-$74.61)2]1/2

           
= $28.90.

Coefficient Of Variation = CV =
Expected Value / svalue

CV           
= $74.61 / $28.90 = 0.39.

Here is a formula for the variance of


a stock’s return, if you know the coefficient of variation of the
expected stock price at some point in the future. The CV should be
for the entire project, including all
scenarios:

σ2 = LN[CV2 +
1]/T = LN[0.392 + 1]/1 = 14.2%.

Now, we proceed to use the OPM:

      V =
$67.83[N(d1)] -
$70e-(0.06)(1)[N(d2)].

           
d1 =

           
   = 0.2641.

           
d2 = d1 -
(0.142)0.5(1)0.5 = 0.2641 - 0.3768

           
   = -0.1127.

           
N(d1) = N(0.2641) = 0.6041.

           
N(d2) = N(-0.1127) = 0.4551.

therefore,

https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 4/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com
                 
  V = $67.83(0.6041)
Home Study tools
My courses
  My books My folder Career Life 
-
$70e-0.06(0.4551)

= $10.98.

g.              
Now suppose the cost of the project is $75 million and the project
cannot be delayed. But if
Tropical Sweets implements the project,
then Tropical Sweets will have a growth option. It will have the
opportunity to replicate the original project at the end of its
life. What is the total expected NPV of the two
projects if both
are implemented?

Answer:    Suppose the cost of the


project is $75 million instead of $70 million, and there is no
option to
wait.

         NPV = PV of future


cash flows - cost

                 
    = $74.61 - $75 = -$0.39 million.

                 
The project now looks like a loser. Using NPV analysis:

                 
NPV = NPV Of Original Project + NPV Of Replication Project

                       
= -$0.39 + -$0.39/(1+0.10)3

                       
= -$0.39 + -$0.30 = -$0.69.

                 
Still looks like a loser, but you will only implement project 2 if
demand is high. We might have
chosen to discount the cost of the
replication project at the risk-free rate, and this would have made
the
NPV even lower.

h.              
Tropical Sweets will replicate the original project only if demand
is high. Using decision tree
analysis, estimate the value of the
project with the growth option.

Answer:    The future cash flows of


the optimal decisions are shown below. The cash flow in year 3 for
the
high demand scenario is the cash flow from the original project
and the cost of the replication project.

                        
0           
1           
2                       
3           
4              
5               
6

     
High                 
-$75       
$45       
$45           $45
-$70       
$45          
$45           
$45

     
Average           
-$75       
$30       
$30                   
$30         
$0            
$0             
$0

     
Low                 
-$75       
$15       
$15                   
$15         
$0            
$0             
$0

To find the NPV, we discount the


risky cash flows at the 10 percent cost of capital, and the
non-risky cost to
replicate (i.e., the $75 million) at the
risk-free rate.

NPV high = -$75 + $45/1.10 +


$45/1.102 + $45/1.103 +
$45/1.104

                 
+ $45/1.105 + $45/1.106 -
$75/1.063

                 
= $58.02

NPV average = -$75 + $30/1.10 +


$30/1.102 + $30/1.103 = -$0.39
https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 5/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com

NPV average = -$75 + $15/1.10 +


$15/1.102 + $15/1.103 = -$37.70
  Expected
Home Study tools
My courses
My books   My folder Career Life 
NPV = 0.3($58.02) +
0.4(-$0.39) + 0.3(-$37.70) = $5.94.

Thus, the option to replicate adds


enough value that the project now has a positive NPV.

i.               
Use a financial option model to estimate the value of the growth
option.

Answer:    X = Exercise Price =


Cost Of Implement Project = $75 million.

rRF = Risk-Free Rate =


6%.

t = Time To Maturity = 3 years.

      P =
Current Price Of Stock = Current Value Of The Project’s Future Cash
Flows.

σ2 = Variance Of Stock
Return = Variance Of Project’s Rate Of Return.

We explain how to calculate P and


σ2 below.

Step 1: Find the value of all cash


flows beyond the exercise date discounted back to the exercise
date. Here
is the time line. The exercise date is year 1, so we
discount all future cash flows back to year 3.

                                                
0           
1           
2         
3           
4           
5              
6

     
High                                                                       
$45       
$45          
$45

     
Average                                                                 
$30       
$30          
$30

     
Low                         
                                              
$15       
$15          
$15

      High: PV3 = $45/1.10 +


$45/1.102 + $45/1.103 = $111.91

      Average: PV3 =


$30/1.10 + $30/1.102 + $30/1.103 = $74.61

   Low: PV3 = $15/1.10 +


$15/1.102 + $15/1.103 = $37.30

The current expected present value,


P, is:

P = 0.3[$111.91/1.13] +
0.4[$74.61/1.13] + 0.3[$37.30/1.13] =
$56.05.

Direct approach for estimating


σ2:

From our previous analysis, we know


the current value of the project and the value for each scenario at
the
time the option expires (year 3). Here is the time line:

                      
Current
Value                   
Value At Expiration

                                                     
Year
0                                    
Year 3

  
High                           
$56.02                                  
$111.91

     
Average                     
$56.02                                    
$74.61

https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 6/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com
     
Low                           
$56.02                                    
$37.30
  The annual
Home Study tools
 My courses
 My books My folder Career Life 
rate of return is:

High: Return =
($111.91/$56.02)(1/3) – 1 = 25.9%.

High: Average =
($74.61/$56.02)(1/3) – 1 = 10%.

High: Return =
($37.30/$56.02)(1/3) – 1 = -12.7%.

Expected Return = 0.3(0.259) +


0.4(0.10) + 0.3(-0.127)

= 8.0%.

s2   =
0.3(0..259-0.08)2 + 0.4(0.10-0.08)2 +
0.3(-0.127-0.08)2

      =
0.182 = 2.3%.

This is lower than the variance found


for the previous option because the dispersion of cash flows for
the
replication project is the same as for the original, even
though the replication occurs much later. Therefore,
the rate of
return for the replication is less volatile. We do sensitivity
analysis later.

The indirect approach:

First, find the coefficient of


variation for the value of the project at the time the option
expires (year 3).

We previously calculated the value of


the project at the time the option expires, and we can use this to
calculate the expected value and the standard deviation.

                   
Value At Expiration

                                                     
Year 3

     
High                         
$111.91

     
Average                     
$74.61

     
Low                           
$37.30

Expected Value   
=.3($111.91)+.4($74.61)+.3($37.3)

= $74.61.

svalue    
= [.3($111.91-$74.61)2 +
.4($74.61-$74.61)2

+
.3($37.30-$74.61)2]1/2

           
= $28.90.

Coefficient Of Variation = CV =
Expected Value / svalue

CV           
= $74.61 / $28.90 = 0.39.

To find the variance of the project’s


rate or return, we use the formula below:

https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 7/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com

σ2 = LN[CV2 +
1]/T = LN[0.392 + 1]/3 = 4.7%.
  Now, we proceed to use the OPM: My courses

Home Study tools


  My books My folder Career Life 

                             
V = $56.06[N(d1)] -
$75e-(0.06)(3)[N(d2)].

                             
d1 =

                             
   = -0.1085.

                             
d2 = d1 -
(0.047)0.5(3)0.5 = -.1085 - 0.3755

                             
   = -0.4840.

                             
N(d1) = N(-0.1080) = 0.4568.

                             
N(d2) = N(-0.4835) = 0.3142.

Therefore,

V = $56.06(0.4568) - $75e-(0.06)(3)(0.3142)

               
  = $5.92.

Total Value = NPV Of Project 1 +


Value Of Growth Option

           
=-$0.39 + $5.92

           
= $5.5 million

j.               
What happens to the value of the growth option if the variance of
the project’s return is 14.2
percent? What if it is 50 percent? How
might this explain the high valuations of many dot.com
companies?

Answer: If risk,
defined by σ2, goes up, then value of growth option goes
up (see the file ch 12 mini
case.xls for
calculations):

σ2 = 4.7%, option value =


$5.92

σ2 = 14.2%, option value =


$12.10

σ2 = 50%, option value =


$24.09

If the future profitability of dot.com companies is very


volatile (i.e., there is the potential for very high
profits), then
a company with a real option on those profits might have a very
high value for its growth
option

Comment


https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 8/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com

Practice with similar questions


  Home Study tools
 My courses
 My books My folder Career Life 

Q: Assume you have just been hired as a financial analyst by


Tropical Sweets Inc., a mid-sized California company that
specializes in creating exotic candies from tropical fruits such as
mangoes, papayas, and dates. The firm’s CEO, George
Yamaguchi,
recently returned from an in- dustry corporate executive conference
in San Francisco, and one of the
sessions he attended addressed
real...

A: See answer 100% (1 rating)

Questions viewed by other students

Q: Complete the Chapter 14 Mini Case (page 568).


MINI CASE:
TheAssume you have just been hired as a financial
analyst
by Tropical Sweets Inc., a mid-sized California company
that specializes in creating exotic candies from tropical fruits
such as mangoes, papayas, and dates. firm's CEO, George Yamaguchi,
recently returned from an industry corporate
executive conference
in San Francisco...

A: See answer

Q: Assume that you have just been hired as a financial analyst by Tropical Sweets Inc., a mid-sized California company that
specializes in creating exotic candies from tropical fruits. The firm's CEO has asked you to prepare a brief on possible
outcomes of the project the company is planning. Tropical Sweets is considering a project that will cost $90 million. This
project will run for...

A: See answer

Show more 

COMPANY

LEGAL & POLICIES

CHEGG PRODUCTS AND SERVICES

CHEGG NETWORK

https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 9/10
12/26/21, 5:13 PM MINI CASE: TheAssume You Have Just Been Hired As A... | Chegg.com

CUSTOMER SERVICE
  Home Study tools
 My courses
 My books My folder Career Life 

© 2003-2021 Chegg Inc. All rights reserved.

https://www.chegg.com/homework-help/questions-and-answers/mini-case-theassume-hired-financial-analyst-tropical-sweets-inc-mid-sized-california-compa-q13365807 10/10

You might also like