Professional Documents
Culture Documents
A New Technique To Detect Faults in De-Energized Distribution Feeders 2011
A New Technique To Detect Faults in De-Energized Distribution Feeders 2011
Abstract—Re-energizing an overhead distribution feeder safely diodes to create a high voltage charging circuit. If there is a
is a major consideration for a utility’s safe work practice. One way short circuit, the charging circuit will not be able to reach a
to improve the safety is to determine whether the feeder still expe- very high voltage. In [11], a portable tester utilizes a capacitor
riences short circuits before it is energized. In this paper, a novel
fault detection technique is proposed to detect if a de-energized dis- to discharge a high-voltage pulse into the de-energized line and
tribution system still experiences short-circuit faults. The proposed estimates the voltage and current response. These devices are
method involves injecting a thyristor-generated-controllable signal portable but they require maintenance of power source such as
into the de-energized feeder. The feeder voltage and current re- batteries. Moreover, the energy of the injected pulse is usually
sponses are analyzed to determine if a fault still exists. A thyristor
gating control strategy and fault detection algorithm are also de-
fixed and limited, which means these devices cannot be adapted
veloped in this paper to detect all possible types of faults that can for a system with different voltage ratings or used for a high
occur in a system. The effectiveness of the proposed method has impedance fault.
been verified through theoretical analysis, computer simulations, Another way to generate the detection signal is to “borrow”
and lab tests. energy from the upstream power system and, therefore, an extra
Index Terms—De-energized distribution line, fault classification, power supply is not required. The fault detector in [12] pro-
fault detection, power electronics, safe recloser. duces the detection signal by closing the recloser for one cycle.
If the current is too high, indicating the existent of a down-
stream short circuit, a series impedance will be inserted to re-
I. INTRODUCTION
duce the inrush current. Similar to autoreclosers, this method
still injects significant inrush current into the downstream before
R E-ENERGIZING or reclosing to a de-energized overhead
distribution feeder safely is a major consideration for a
utility’s safe work practice [1]–[5]. After a feeder is de-ener-
the insertion of the series impedance. In [13], a short-duration
voltage from an electronic switch is applied to test if the down-
gized for an extended period due to events, such as repair, main- stream circuit is shorted. However, the device may not have
tenance, or storms, there is always the possibility that humans or enough rating for working in MV system, and the strength of
animals may be in contact with feeder conductors unknowingly the pulse is not adjustable (different types of faults require dif-
[6], [7]. A reclosing action in such a situation can easily lead ferent signal strength (e.g., a strong signal is needed to detect a
to fatalities [8], [9]. Utility companies are therefore very inter- high impedance fault). Furthermore, another drawback for the
ested in techniques that can determine whether a de-energized aforementioned methods is that they cannot identify different
feeder is clear of short circuits so that operators can re-energize types of faults in a single device.
the feeder with confidence. Recently, a pulse-recloser technique has been developed for
Compared to detecting faults in an energized system, to de- the purpose of reducing the inrush current caused by reclosing
tect faults in a de-energized system is more challenging, since to a faulted feeder [14]. This technique uses specialized recloser
it requires the generation and application of a voltage signal to and is intended for fuse-saving-oriented feeder reclosing oper-
the de-energized feeder. Furthermore, the signal must be high ations. In theory, the technique can be applied to the problem
enough to mimic the normal medium-voltage stress (e.g., 25 of concern in this paper (i.e., detecting feeder faults after the
kV) to be experienced by the feeder. One way to generate the feeder has been de-energized for an extended period). However,
signal is through charging or discharging a capacitor in the cir- its application requires replacing the existing feeder breaker or
cuit. For example, in [10], a cable tester uses a capacitor and recloser. This can be costly to utility companies if implemented
on a large scale.
Manuscript received October 03, 2010; revised January 07, 2011; accepted In view of the limitations of existing techniques, a new detec-
February 08, 2011. Date of publication April 07, 2011; date of current version tion technique is proposed in this paper. A thyristor-based de-
June 24, 2011. This work was supported by iCORE. Paper no. TPWRD-00758- vice is used to inject a controllable signal into the de-energized
2010.
The aurthors are with the Department of Electrical and Computer Engi- downstream to stimulate the electrical response. A significant
neering, University of Alberta, Edmonton, AB T6G 2V4, Canada (e-mail: feature of this technique is that the signal strength is adjustable
xlong@ualberta.ca; wxu@ualberta.ca; yunwei.li@ece.ualberta.ca). by changing the thyristor firing angle. Therefore, a low-voltage
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. pulse can be created to satisfy the safety requirement, and a
Digital Object Identifier 10.1109/TPWRD.2011.2118237 high-voltage pulse can be produced to break down an insulted
0885-8977/$26.00 © 2011 IEEE
1894 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 26, NO. 3, JULY 2011
Fig. 4. Gating control logic in two fault detection modes.: (a) Phase-to-ground
fault. (b) Phase-to-phase fault.
TABLE I
OVERALL CONTROL LOGIC AND DETECTED FAULT TYPES
Fig. 6. Current waveforms under (a) no fault with balanced three-phase cur-
rents and (b) a single-line-to-ground fault with unbalanced three-phase currents.
(6)
(1)
where is the rated phase-to-neutral voltage of the distribution However, if a single phase-to-ground fault exists, the fault
line, and are the zero impedance of resistance will be parallel to the circuit as shown in Fig. 7. In this
1896 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 26, NO. 3, JULY 2011
Fig. 8. Voltage and current pulses generated with different thyristor firing an-
case, the equivalent impedance in the faulted phase is smaller gles. (a) Voltage pulses. (b) Current pulses.
than the healthy phases as
(7)
Fig. 10. Voltage and current pulses when a phase A-to-phase B fault exists. (a)
Voltage pulses. (b) Current pulses.
Fig. 14. Three-phase currents in three steps under a phase C-to-ground fault.
Fig. 16. Current difference between phases under the phase C-to-ground fault.
A. Phase-to-Ground Fault
If a single-phase-to-ground fault exists in phase C and
ground, the current in Step I will change. As shown in Fig. 14,
the current of phase C increases significantly due to the fault. Fig. 17. Three-phase currents in three steps under a phase A-to-phase B fault.
As discussed earlier, under the same firing angle, the magni-
tude of the current depends on the fault resistance in the existing
system. When the firing angle is 150 , the current waveforms have almost the same values. As discussed, reducing
with different fault resistance are shown in Fig. 15. It is apparent the firing angle can make the difference of current between
that the magnitude of the fault current decrease with the increase phases more significant.
of fault resistance. Therefore, if is small, the thyristor firing
angle should be large enough to decrease the current to a safe B. Phase-to-Phase Fault
value. On the other hand, If is large, the current of faulted If there is a phase-to-phase fault between phase A and B,
phase is comparable to the currents of unfaulted phase, which the three-phase current waveforms in three steps are shown in
increase the difficulty of detection. Thus, the firing angle should Fig. 17. In Step I, all three-phase currents are identical, but in
be reduced to obtain an obvious difference between faulted and Step II, a reverse signal shows up in phase B when a pulse is in-
healthy phases. jected from phase A. It indicates a fault existing between phase
According to the criterion of identifying an unbalanced A and phase B. The waveforms in Step III verify the existent of
phase-to-ground fault, the current difference between two a fault since a reverse signal shows up in phase A when a pulse
phases is calculated. The single phase C-to-ground fault does is injected from phase B.
not affect phase A and phase B; thus, the currents of phase The current of phase B in Step II not only depends on the in-
A and B are identical when a zero-sequence voltage pulse is jected current from phase A, but it is also affected by other three
applied to the downstream in Step I. As shown in Fig. 16, parameters of power system as shown in (9): the fault location
is almost zero regardless of firing angles and fault (the length from the fault detection point, which determines the
resistance. Since the current of phase C is larger, and line impedance of interest), the load, and fault impedance.
LONG et al.: NEW TECHNIQUE TO DETECT FAULTS IN DE-ENERGIZED DISTRIBUTION FEEDERS—PART I 1899
Fig. 18 shows the ratio of with the different values of voltage measurement channels and three current measurement
the three parameters in Step II. Apparently, the fault resistance channels—have been utilized (note that regular current/voltage
has a significant impact on the current division. If the phase-to- probes or transducers are sufficient for the proposed device).
phase fault has high impedance, the current of phase B through Due to the limitation of lab equipment, all of the transmission
the fault will be largely reduced. Another significant impact is lines and transformers have been replaced by equivalent induc-
from the load. A large load will lead more current flow through tors in the single-phase system. The loads have been replaced
the load on phase B rather than from the grounded conductor by an equivalent R-L model as well. All parameters have been
of phase B where the measurement point X is located as shown scaled down based on the computer simulation model:
in Fig. 9(b). The impact of the Line1 length is very limited as •. power source: 120 V;
shown in Fig. 18, which confirms the analysis in (9). •. transformers: 0.03 p.u.,
Moreover, the situation of multiple faults is also tested, which 0.76 mH;
includes: 1) a phase C-to-ground fault; 2) a phase A-to-phase •. signal generator: a thyristor. Firing angle is adjustable from
B fault; and 3) a phase A-to-phase C fault. The test results are 170 to 150 ;
shown in Fig. 19. In Step I, phase C current is much larger than •. feeders: 0.4 mH;
that of phase A and phase B, which indicates a phase C-to- •. load: 10 mH;
ground fault. In Step II, a pulse is injected from phase A and •. faults: resistance .
reverses pulses show up on both phases B and C, meaning that The equivalent circuit of the lab test prototype is shown in
the A-B fault and A-C fault exist. Step III verifies that a fault be- Fig. 20. The fault resistance and the load size are
tween A-B exists. If necessary, a pulse can also be injected from adjustable.
phase C to verify if a fault between A-C or B-C exists. There- Fig. 21 shows that the typical voltage waveforms in the test.
fore, all three different faults can be successfully identified with represent the 120 V, 60 Hz single-phase voltage source and
the proposed scheme. is the voltage across the thyristor. When the thyristor is
fired at a certain degree before the source voltage crosses zero,
IV. EXPERIMENT VERIFICATIONS becomes zero instantaneously. At this moment, the
An experiment based on a 120-V single phase system has de-energized part of the circuit is connected to voltage source.
been carried out in the laboratory, and the prototype consists is the voltage pulse created by the thyristor. When the thyristor
of: 1) a thyristor-based signal generator; 2) a NI-DAQ-based current becomes zero, the thyristor turns off naturally and the
data-acquisition system; and 3) a lumped model-based equiva- passive circuit returns to its de-energized state.
lent circuit. The firing angle of the thyristor can be adjusted from The corresponding currents, including the load current ,
170 to 150 and the firing interval can be either 2 or 4 funda- the fault current , and the total current , are shown in
mental cycles. In the DAQ device, six channels—including three Fig. 22. The currents are highly related to the characteristics
1900 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 26, NO. 3, JULY 2011
TABLE II
CONTROL LOGIC OF THE CASCADED STRUCTURE
Fig. 22. Measured current waveforms in the lab experiment.
not only from phase B but also phase A since the first thyristor [4] J. F. Witte, S. R. Mendis, M. T. Bishop, and J. A. Kischefsky,
must be turned on in order to connect phase B to the energized “Computer-aided recloser applications for distribution systems,” IEEE
Comput. Appl. Power, vol. 5, no. 3, pp. 27–32, Jul. 1992.
side. So faults between A-C or B-C will be detected in Step III. [5] A. T. Johns, R. K. Aggarwal, and Y. H. Song, “Improved techniques
Despite the different control logic of gating signals of the for modeling fault arcs on faulted EHV transmission systems,” in Proc.
Inst. Elect. Eng., Gen., Transm. . Distrib., 1994, pp. 148–154.
cascaded thyristor topology, the criteria for fault detection are [6] V. L. Buchholz, M. Nagpal, and J. B. Neilson, “High impedance fault
the same as those in the bridge-based topology, as the signal detection device tester,” IEEE Trans. Power Del., vol. 11, no. 1, pp.
responses under different types of faults are still the same. 184–190, Jan. 1996.
[7] S. P. Ahn, C. H. Kim, R. K. Aggarwal, and A. T. Aggarwal, “An alter-
native approach to adaptive single pole auto-reclosing in high voltage
transmission systems based on variable dead time control,” IEEE Trans.
VI. CONCLUSION Power Del., vol. 16, no. 4, pp. 676–686, Oct. 2001.
[8] M. M. Eissa and O. P. Malik, “A novel approach for auto-reclosing
In this paper, a thyristor-based fault detection scheme is EHV/UHV transmission lines,” IEEE Trans. Power Del., vol. 15, no.
proposed to detect the existence of a fault in the de-energized 3, pp. 908–912, Jul. 2000.
downstream system, which can ensure a smooth and safe [9] C. G. Wester, “High impedance fault detection on distribution systems,”
in Proc. Rural Elect. Power Conf., St. Louis, MO, 1998, pp. C5 1–5.
reclosing without causing a hazard to the downstream devices [10] A. T. Trihus, “Cable tester,” U.S. Patent 4 254 374, Mar. 3, 1981.
and personnel. The proposed technique functions by generating [11] D. A. Rhein and L. R. Beard, “Fault detection system including a ca-
pacitor for generating a pulse and a processor for determine admittance
a controllable detection signal through the thyristor- based versus frequency of a reflected pulse,” U.S. Patent 5 650 728, July 22,
device connected in parallel with a recloser, and using the 1997.
stimulated voltage and current signals to detect whether a fault [12] D. D. Wilson and Hedman, “Fault isolator for electrical utility distri-
bution systems,” U.S. Patent 4 370 609, Jan. 25, 1983.
still exists in the downstream. The device can be run manually [13] R. Maier and W. Roethlingshoefer, “Method and arrangement for de-
or automatically whenever reclosing is needed. For auto opera- tecting short-circuit in circuit branches of electrical power system net-
works,” US Patent 5 345 180, Sept. 6, 1994.
tion, communication is not an issue since the recloser is linked [14] “S&C, “S&C IntelliRupter PulseCloser: Outdoor distribution 15.5 kV
with communication means if it can be reclosed remotely. To and 27 kV,” in S&C Descriptive Bull. 766-30 Mar. 22, 2010.
identify different types of faults, the characteristics of injected [15] W. Xu, G. Zhang, C. Li, W. Wang, G. Wang, and J. Kliber, “A
power line signaling based technique for anti-islanding protection of
signals under phase-to-ground faults and phase-to-phase faults distributed generators—Part I: Scheme and analysis,” IEEE Trans.
are studied and the criteria for identifying a faulted line from Power Del., vol. 22, no. 3, pp. 1758–1766, Jul. 2007.
[16] W. Wang, K. Zhu, P. Zhang, and W. Xu, “Identification of the faulted
healthy lines are developed accordingly. The three-step fault de- distribution line using thyristor-controlled grounding,” IEEE Trans.
tection algorithm is then developed, where all phase-to-ground Power Del., vol. 24, no. 1, pp. 52–60, Jan. 2009.
faults (including asymmetrical and symmetrical faults) will be [17] M. T. Aung, J. V. Milanovic, and C. P. Gupta, “Propagation of asym-
metrical sags and the influence of boundary crossing lines on voltage
detected in Step I, and the phase-to-phase faults are detected sag prediction,” IEEE Trans. Power Del., vol. 19, no. 4, pp. 1819–1827,
in Steps II and III. The whole three-step testing procedure will Oct. 2004.
[18] D. C. Yu and S. H. Khan, “An adaptive high and low impedance
take between one to a few seconds, which is sufficiently fast fault detection method,” IEEE Trans. Power Del., vol. 9, no. 4, pp.
for the fault detection in a de-energized system. Both computer 1812–1821, Oct. 1994.
simulation and lab experiment results are obtained to verify the
effectiveness of the proposed technique. An alternative struc-
ture with fewer thyristors is also proposed to reduce the size and Xun Long (S’08) received the B.E. and M.Sc. degrees in electrical engineering
cost of the power-electronics device. The proposed technique from Tsinghua University, Beijing, China, in 2004 and 2007, respectively, and
is currently pursuing the Ph.D. degree in electrical and computer engineering
is used for reclosing after the feeder has been de-energized for from the University of Alberta, Edmonton, AB, Canada.
an extended period; however, it also can be improved for the His main research interests include power-line signaling, distributed genera-
fuse-saving oriented reclosing operations. tion, and fault detection.
This paper mainly focuses on the introduction of the proposed
power–electronics-aided fault detection technique, such as the
faulty line electrical signal characteristics, gating signal genera- Wilsun Xu (F’05) received the Ph.D. degree from the University of British Co-
lumbia, Vancouver, BC, Canada, in 1989.
tion algorithm, and fault detection steps. More practical imple- From 1989 to 1996, he was an Electrical Engineer with BC Hydro, Vancouver,
mentation issues, including the detection of three-phase sym- and Surrey, BC, respectively.
metrical faults and distinguishing a fault from stalled motors or Currently, he is with the Department of Electrical and Computer Engineering,
University of Alberta, where he has been since 1996. His research interests are
downstream shunt capacitors, are presented separately in a com- power quality and distributed generation.
panion paper.
REFERENCES Yun Wei Li (S’04–M’05) received the B.Sc. degree in engineering from Tianjin
[1] IEEE Guide for Automatic Reclosing of Line Circuit Breakers for AC University, Tianjin, China, in 2002, and the Ph.D. degree from Nanyang Tech-
Distribution and Transmission Lines, IEEE Std C37.104-2002, Apr. nological University, Singapore, in 2006.
2003. In 2005, he was a Visiting Scholar with the Institute of Energy Technology,
[2] G. D. Rockefeller, C. L. Rockefeller, J. L. Linders, K. L. Hicks, and D. Aalborg University, Denmark. From 2006 to 2007, he was a Postdoctoral Re-
T. Rizy, “Adaptive transmission relaying concepts for improved per- search Fellow in the Department of Electrical and Computer Engineering, Ry-
formance,” IEEE Trans. Power Del., vol. 3, no. 4, pp. 1446–1458, Oct. erson University, Toronto, ON, Canada. After working with Rockwell Automa-
1988. tion Canada in 2007, he joined the Department of Electrical and Computer En-
[3] M. M. Eissa and O. P. Malik, “A new digital directional transverse gineering, University of Alberta, Edmonton, AB, Canada, as an Assistant Pro-
differential current protection technique,” IEEE Trans. Power Del., vol. fessor. His research interests include distributed generation, microgrid, power
11, no. 3, pp. 1285–1291, Jul. 1996. converters, and electric motor drives.