Sr No Project Level SP RFD TL

Number

1 287 1st FRS Pending Pending Pending


2 480 GF Pending Pending Pending
3 525 2nd to 4th Revision Revision Revision
4 552 4th Floor Pending Pending Pending
5 559 5th FRS -B Pending Pending Pending
6 629 6th Floor Pending Pending Pending
7 637 2nd FRS Finished Finished Finished
8 655 GF Part C Finished Pending Pending
9 655 Podium Part B Finished Pending Pending
10 532 9th FRS Pending Pending Pending
11 754 4th FRS Finished Finished Finished
12 756 2nd FRS Pending Pending Pending
13 731 Parking slab Pending Pending Pending
14 673 3rd FRS Pending Pending Pending
15 795 2nd Floor Pending Pending Pending
16 806 GFRS Pending Pending Pending
17 - All blocks Finished In progress -
18 - - - - -