Start Finish
2/18/2020 2/24/2020
AREA SUNDAY MONDAY TUESDAY WEDNESDAY THURSDAY FRIDAY SATURDAY
IV curve testing (BLOCK 04,05,09) IV curve testing (BLOCK 01,02,03) IV curve testing (BLOCK 01,02,03) IV curve testing (BLOCK 10,11,12) IV curve testing (BLOCK 10,11,12) IV curve testing (BLOCK 13,14,15)
VOC Test VOC Test VOC Test VOC Test VOC Test VOC Test
(BLOCK 68,69,70,71,72) (BLOCK 68,69,70,71,72) (BLOCK 73,74,75,76,77) (BLOCK 73,74,75,76,77) (BLOCK 78,79,80,81) (BLOCK 78,79,80,81)
ELECTRICAL
Visual inspection of PV modules (BLOCK Visual inspection of PV modules Visual inspection of PV modules Visual inspection of PV modules Visual inspection of PV modules Visual inspection of PV modules
6,7,8,9) (BLOCK 11,12,13,14) (BLOCK 11,12,13,14) (BLOCK 15,16,17,18) (BLOCK 15,16,17,18) (BLOCK 20,21,22,23)
Mechanical
Test of RMU Test of RMU Test of RMU Test of RMU Test of RMU Test of RMU
MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU
Comm Procedure Comm Procedure Comm Procedure Comm Procedure Comm Procedure Comm Procedure
Test of the Transformer Test of the Transformer Test of the Transformer Test of the Transformer Test of the Transformer Test of the Transformer
MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC-
0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure
Schneider
Internal testing Internal testing Internal testing Internal testing Internal testing Internal testing
MP0092-C-TC-PR-EPC-0070 MP0092-C-TC-PR-EPC-0077 MP0092-C-TC-PR-EPC-0078 MP0092-C-TC-PR-EPC-0080 MP0092-C-TC-PR-EPC-0010 MP0092-C-TC-PR-EPC-0019
Scada
Tracker testing Tracker testing Tracker testing Tracker testing Tracker testing Tracker testing
MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017
PVH Tracker
SUBESTATION
Start Finish
IV curve testing (BLOCK 06,07,08) IV curve testing (BLOCK 06,07,08) IV curve testing (BLOCK 04,05,09)
ELECTRICAL VOC Test VOC Test VOC Test VOC Test VOC Test VOC Test
(BLOCK 51,52,53,54,55,56,57) (BLOCK 51,52,53,54,55,56,57) (BLOCK 58,59,60,61,62) (BLOCK 58,59,60,61,62) (BLOCK 63,64,65,66,67) (BLOCK 63,64,65,66,67)
Mechanical
Test of RMU Test of RMU Test of RMU Test of RMU Test of RMU Test of RMU
MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU MP0092-C-TC-PR-EPC-0022_RMU
Comm Procedure Comm Procedure Comm Procedure Comm Procedure Comm Procedure Comm Procedure
Test of the Transformer Test of the Transformer Test of the Transformer Test of the Transformer Test of the Transformer Test of the Transformer
MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC- MP0092-C-TC-PR-EPC-
0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure 0021_Transformer Comm Procedure
Schneider
Internal testing Internal testing Internal testing Internal testing Internal testing Internal testing
MP0092-C-TC-PR-EPC-0018 MP0092-C-TC-PR-EPC-0018 MP0092-C-TC-PR-EPC-0018 MP0092-C-TC-PR-EPC-0018 MP0092-C-TC-PR-EPC-0018 MP0092-C-TC-PR-EPC-0018
Scada
Tracker testing Tracker testing Tracker testing Tracker testing Tracker testing Tracker testing
MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017 MP0092-C-TC-PR-EPC-0017
PVH Tracker
Substation
MP0092-C-TC-PR-EPC-0013-HV01 MP0092-C-TC-PR-EPC-0013-HV01 MP0092-C-TC-PR-EPC-0013-HV01
Commissioning Firefighting system Commissioning Firefighting system Commissioning Firefighting system