superohtLED
; ‘uperior Court of California
‘ounty of Los Angelos
a JAN 1.3 2022
Shen cculve Otc Clerk
"—a4 fea Scig — O°PUY
GONZALEZ V. COUNTY OF LOS ANGELES
20STCW35594
January 13, 2022
ORDER DENYING MOTION TO STRIKE COSTS
Plaintiff filed this case on September 17, 2020. His later filed Second Amended
Complaint (SAC) alleged six causes of action. On April 15, 2021, the Court issued an order
sustaining County's demurrer except as to causes of action three (FEHA retaliation), four (FEHA
failure to prevent retaliation) and five (retaliation pursuant to Labor Code 1102.5). Further, these
causes of action were limited to “plaintiff's claim that he reported [a] fight between two deputies
and was thereafter subject to retaliation.”
‘The FEHA “protected activities” alleged by plaintiff in the SAC were that plantiff: (1)
participated as a witness in a discrimination or harassment complaint; (2) reported or resisted
discrimination or harassment and (3) requested or used leave under the California Family Rights
Act or FMLA.' |
On July 29, 2021, County filed a Motion for Summary Judgment/Adjudication (“MSJ").
Among other things, County argued that plaintiff did not engage in FEHA protected activities.
Plaintiff's Opposition to the MSJ completely failed to respond to this argument and instead only
addressed plaintiff's alleged protected activity under the Labor Code. Similarly, plaintiff's
Opposing Separate Statement (which included over 100 so-called “Additional Material Facts”)
failed to raise any issue regarding protected activities under plaintiff's FEHA claims.”
In its Order of November 4, 2021 granting the MSJ, the Court held that plaintiff had
conceded that the protected activities element of his FEHA retaliation claims could not be met.
See also Schuler v. City of Los Angeles, 62 Cal. App. 5S" 793, 800 (2021) (a party who fails to
present argument and authority for his causes of action abandons them).
"The Labor Code retaliation claim vaguely referenced “protected activities,” by citation to
a laundry list of federal and state laws as well as Los Angeles County policies and guidelines.
? Itis also worth noting that the request for continuance in plaintiff's Oppesition to the
MSJ did not claim that more time was needed to conduct discovery regarding FEHA protected
activities,As prevailing party, County then submitted a Memorandum of Costs, seeking $13,943.
Plaintiff has now filed his Motion to Strike Costs. He first concedes that “prevailing
parties are usually entitled to costs.” He then argues that, because the Court allowed his FEHA
claims to proceed at the demurrer stage, his action was not “frivolous, unreasonable or
groundless when brought.” Plaintiff cites Williams v. Valley Indep. Fire Dist., 61 Cal. 4° 97
(2015), as providing guidance to trial courts in awarding costs in a FEHA case. Finally, plaintiff
does not contend that County's costs were unreasonable.
In opposition, County argues that the Motion to Strike should be denied because plaintiff
pursued claims that were either legally flawed or factually unsupported and that plaintiff tried to
change his theories to stave off summary judgment.
Plaintiff's Reply first makes the strained argument that County'is trying to “punish” him
by seeking costs. ‘The Reply then acknowledges that a FEHA plaintiff who continues to litigate a
case withott an objective basis for believing it has merit can be subject to costs, but claims that,
there is no basis for such an award here. And, once again, no argument is made that the costs are
unreasonable.
Upen due consideration, County has the better of the argument and the Motion to Strike
Costs will be denied. While itis true that plaintiff's FEHA claims withstood demurrer, that was
based only upon a reading of the SAC, the facts of which the Court had to accept as true. Since
that time, plaintiff had the opportunity to find evidence showing that he was involved in the
protected activities alleged in the third and fourth causes of action, but apparently he was unable
to do so. Nevertheless, plaintiff chose not to dismiss these claims, requiring defendant to engage
in highly contentious litigation and requiring the filing of a MSJ seeking to have these claims
dismissed.
In other words, plaintiff continued litigating his FEHA retaliation claims without any
objective basis for believing he could establish a necessary element of these claims. He should
have dismissed these claims when he realized this or, at the latest, when the MSI was filed, He
did not do so and this is a sufficient reason by itself for allowing County to recover costs under
Williams. See also Ramon v. BRE Properties, Inc., 237 Cal. App. 4" 1040, 1057 (2015).
Further, and despite the arguments in his opposition to the MSJ, plaintiff ultimately had
no evidence that he suffered from an adverse employment action or had damages. This complete
lack of evidence was fatal to both his FEHA claims as well as his claim under the Labor Code.In sum, the Court concludes that this was one of those thankfully very rare cases which
‘was brought for reasons other than to remedy personal harm to the plaintiff. Apparently, plaintiff
and his attomeys believe that there are personnel problems in the Sheriff's Department and itis,
their mission to “curtail” them. This is evidenced by the frequent comments made by plaintiff's
counsel in the media.’
Plaintiff and his attorneys then came up with a series of unproven allegations, including
claims about being unable to take family leave, “unusual misdemeanor arrests,” “illegal quota
programs” and actions involving other deputies. Plaintiff sought vastly overbroad discovery in
part to assist his attorneys with other cases against the County. All of this resulted in the County
having to expend enormous time and resources to defend what tured out to be a frivolous,
unreasonable and groundless case when brought and/or which plaintiff continued to litigate after
it clearly became so. Gov't Code 12965(b); Roman, supra at 1057
Accordingly, good cause having been shown,
IT IS ORDERED that plaintiff's Motion to Strike Costs is Denied.
Notice by defendant
Y Ay
: JAN 13 2022 Mi a
> See, e.g., Exhibits attached to November 24, 2021 Declaration of Mira Hashmall.
3