You are on page 1of 32

SPDC

Basic Gas
Lift
CONTINUOUS FLOW BASICS

– Flowing/Unloading Hydraulics

– Multiphase flow

– Continuous flow unloading

– Precautions during unloading

– Well Instability

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 1


SPDC
Basic Gas
Lift
IPO UNLOADING

How do we inject gas into a well in the first place?

This process of replacing the completion brine with injection gas is


called unloading and it is done only once after the initial
completion and after any well servicing where the casing to tubing
annulus is filled with liquid.
Pressure
Depth

SBHP
Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 2
SPDC
Basic Gas
Lift
IPO UNLOADING

Gas is injected into the casing - tubing annulus and the pressure
pushes the brine through each of the gas lift valves which are wide
open. This is a particularly dangerous time for the valves. If the
differential is too high the liquid velocity can be enough to cut the
valve seat. Then, the valve will not be able to close and the design
will not work.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 3


SPDC
Basic Gas
Lift
IPO UNLOADING

Operators must allow sufficient time for unloading. The rule from
API RP 11V5 is to take 10 minutes for each 50 psi increase in casing
pressure up to 400 psi. After that point a 100 psi increase every 10
minutes is acceptable until gas injects into the tubing. To get up to
1000 psi should require at least 2 hr, 20 min. A good practice is to
assign an operator to the well for the duration of this operation.

Pressure
Depth

Brine may go out the


tubing or into the
reservoir.
SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 4


SPDC
Basic Gas
Lift
IPO UNLOADING

Once the brine level is below the top valve, gas will
enter the tubing and begin lifting the well. If the tubing
pressure is less than the SBHP the reservoir will
begin to contribute. The first production from the
reservoir is normally recovered completion brine.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 5


SPDC
Basic Gas
Lift
IPO UNLOADING

When the second valve is uncovered, gas


will begin to enter the tubing at the second
valve.
Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 6


SPDC
Basic Gas
Lift
IPO UNLOADING

In the case of IPO valves, the injection gas rate into the well at
the surface must be regulated to control the gas entry to
approximately the design rate of one valve. Since two valves
are passing injection gas, the pressure in the casing annulus
will fall.

Gas to
casing
+500 500 mcfd

Gas from
-500 casing
500 mcfd

-500 Gas from


casing
500 mcfd
With more gas leaving casing than entering, the injection
pressure must fall.

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 7


SPDC
Basic Gas
Lift
IPO UNLOADING

When the casing pressure falls enough, the top


valve wWill close based on valve mechanics in a
good design.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 8


SPDC
Basic Gas
Lift
IPO UNLOADING

Since there is still more casing pressure than tubing


pressure at the bottom valve and the bottom valve is
still open, the injection gas will continue to displace
the brine in the annulus until the third valve is
uncovered.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 9


SPDC
Basic Gas
Lift
IPO UNLOADING

Once again with more gas leaving the casing through


two valves, the casing pressure will fall until the
second valve closes. Obviously if there were more
valves deeper the unloading process would continue.
Pressure
Depth

What would happen if


the third valve injected
too much gas? SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 10


SPDC
Basic Gas
Lift
IPO UNLOADING

Valve 4 (orifice)
injecting, 3 closes
Time

Valve 3 injecting, 2
closes

Valve 2 injecting, 1
closes

Valve 1
injecting

Start gas to
well

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 11


SPDC
Basic Gas
Lift
UNLOADING

Although we have been talking about unloading, the


same is true for kickoff, which is the same lift and
transfer progression, except starting with an empty
casing. This occurs every time the well is shut-in wheras
unloading occurs only the first time the well is put on lift.
Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 12


SPDC
Basic Gas
Lift
PPO UNLOADING

Lets look at the process of unloading with PPO valves.


This process of replacing the completion brine with
injection gas is called unloading and it is done only
once after the initial completion and after any well
servicing where the casing to tubing annulus is filled
with liquid. Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 13


SPDC
Basic Gas
Lift
PPO UNLOADING

Gas is injected into the casing - tubing annulus and the pressure
pushes the brine through each of the gas lift valves which are wide
open. This is a particularly dangerous time for the valves. If the
differential is too high the liquid velocity can be enough to cut the
valve seat. Then, the valve will not be able to close and the design
will not work.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 14


SPDC
Basic Gas
Lift
PPO UNLOADING

Operators must allow sufficient time for unloading. The rule from API RP
11V5 is to take 10 minutes for each 50 psi increase in casing pressure up to 400
psi. After that point a 100 psi increase is acceptable until gas injects into the
tubing. To get up to 1000 psi should require at least 2 hr, 20 min. A good
practice is to assign an operator to the well for the duration of this
operation.

Pressure
Depth

Brine may go out the tubing


or into the reservoir. SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 15


SPDC
Basic Gas
Lift
PPO UNLOADING

Once the brine level is below the top valve, gas will enter the tubing and
begin lifting the well. If the tubing pressure is less than the SBHP the
reservoir will begin to contribute. The first production from the reservoir is
normally recovered completion brine. In PPO valve unloading, the valve
will tend to inject gas, close, re-open and repeat the cycle at each valve
while the brine is being unloaded.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 16


SPDC
Basic Gas
Lift
PPO UNLOADING

When the second valve is uncovered, gas will begin


to enter the tubing and the tubing pressure at the top
valve will fall and the top valve will close. The second
valve will tend to open and close.
Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 17


SPDC
Basic Gas
Lift
PPO UNLOADING

Since there is still more casing pressure than tubing


pressure at the bottom valve and the bottom valve is
still open, the injection gas will continue to displace
the brine in the annulus until the third valve is
uncovered.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 18


SPDC
Basic Gas
Lift
PPO UNLOADING

When the third valve is uncovered, gas will be


injected and the pressure at the second valve will fall,
closing the second valve. What will happen at the
third valve?

Pressure
Depth

Never operate from


a PPO valve. SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 19


SPDC
Basic Gas
Lift
PPO UNLOADING

Use an IPO or an orifice valve at the


operating depth.

Pressure
Depth

SBHP

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 20


SPDC
Basic Gas
Lift
PPO UNLOADING

Time

Gas into valve


4

Gas into valve


3

Gas into valve Gas into valve


2 1

Start gas to
well

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 21


SPDC
Basic Gas
Lift
UNLOADING PRECAUTIONS

• Don’t Cut Out the Valves!

• Buildup Injection Pressure


Slowly

• 5 psi/min. to 400 psi

• 10 psi/min. Until Gas


Production

• Then increase Gas


Injection Rate to the
Desired Value
Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 22
SPDC
Basic Gas
Lift
OPERATING PARAMETERS

• Data Variable Impacts


on Downhole Operation

• Well Instability, Causes,


Remedies & Impacts

• Dual Gas-Lift
Completions

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 23


SPDC
Basic Gas
Lift
OPERATING PARAMETERS

Higher backpressure requires more lift gas

FTP=205,
LG=550

FTP=100,
LG=280

Which case would produce more?

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 24


SPDC
Basic Gas
Lift
OPERATING PARAMETERS

We can see the effect of lifting from various depths.

No gas lift = lift at zero


depth.

Assumed lift
depths

If the SBHP is 1500 psi, will the well produce


with no lift gas?

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 25


SPDC
Basic Gas
Lift
OPERATING PARAMETERS

A useful analysis is to change the amount of gas injected


into a well and see the difference.
In this illustration the injection gas is changed by a fixed
increment, starting at zero injection. There is a tremendous
increase in drawdown as the first increment of gas is
injected into the well. Thereafter, the benefit diminishes.
Finally the well reaches the minimum gradient.

Zero injection
(natural flow)

100 mcfd
increments

Minimum
gradient

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 26


SPDC
Basic Gas
Gas lift Injection
Lift
Performance Curve

1. Unlimited Gas or
maximum
flowrate is
900 desired
800 2. Limited Gas or
the most
700
economical rate
Net Production(BPD)

600 is desired

500 3. Production is
fixed
400 3 2 1 • Water /gas
coning
300
• Sand
200 production
• Government
100 regulations
0
50 1002003004005006007008009001000

Gas lift Injection (Mscfd)

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 27


SPDC Gas lift Injection Performance
Basic Gas
Lift Curve

• Relatively more gas is required for a small


incremental production as we approach
maximum point

dQinj
900

800 Optimum Injection Point dQliq

700
Net Production(BPD)

600

500
Sub-optimum injecting points
400

300

200

100

0
50 1002003004005006007008009001000

Gas lift Injection (Mscfd)

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 28


SPDC
Basic Gas
Lift
WELL INSTABILITY

• Causes
– Valve Interference
– Low injection gas, liquid production
– Incorrect size valve ports
– Poor lift gas supply control
– Variations in production system pressure

• Impacts
– Propogate instability in other wells
– Excessive G/L & control valve wear
– Production system upsets

• Remedies
– Design installations with good data
– Use effective control systems
– Operate within the envelope

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 29


SPDC
Basic Gas
Lift

BACKUP SLIDE

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 30


FLOW REGIMES
SPDC
Basic Gas
Lift

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 31


Pressure Drops in Oil Production
SPDC
Basic Gas
Lift

Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 32

You might also like