Professional Documents
Culture Documents
Basic Gas
Lift
CONTINUOUS FLOW BASICS
– Flowing/Unloading Hydraulics
– Multiphase flow
– Well Instability
SBHP
Copyright 1998 SIEP EPT-OM Portions Copyright SEPTCo, Burney Waring 2
SPDC
Basic Gas
Lift
IPO UNLOADING
Gas is injected into the casing - tubing annulus and the pressure
pushes the brine through each of the gas lift valves which are wide
open. This is a particularly dangerous time for the valves. If the
differential is too high the liquid velocity can be enough to cut the
valve seat. Then, the valve will not be able to close and the design
will not work.
Pressure
Depth
SBHP
Operators must allow sufficient time for unloading. The rule from
API RP 11V5 is to take 10 minutes for each 50 psi increase in casing
pressure up to 400 psi. After that point a 100 psi increase every 10
minutes is acceptable until gas injects into the tubing. To get up to
1000 psi should require at least 2 hr, 20 min. A good practice is to
assign an operator to the well for the duration of this operation.
Pressure
Depth
Once the brine level is below the top valve, gas will
enter the tubing and begin lifting the well. If the tubing
pressure is less than the SBHP the reservoir will
begin to contribute. The first production from the
reservoir is normally recovered completion brine.
Pressure
Depth
SBHP
SBHP
In the case of IPO valves, the injection gas rate into the well at
the surface must be regulated to control the gas entry to
approximately the design rate of one valve. Since two valves
are passing injection gas, the pressure in the casing annulus
will fall.
Gas to
casing
+500 500 mcfd
Gas from
-500 casing
500 mcfd
Pressure
Depth
SBHP
Pressure
Depth
SBHP
Valve 4 (orifice)
injecting, 3 closes
Time
Valve 3 injecting, 2
closes
Valve 2 injecting, 1
closes
Valve 1
injecting
Start gas to
well
SBHP
SBHP
Gas is injected into the casing - tubing annulus and the pressure
pushes the brine through each of the gas lift valves which are wide
open. This is a particularly dangerous time for the valves. If the
differential is too high the liquid velocity can be enough to cut the
valve seat. Then, the valve will not be able to close and the design
will not work.
Pressure
Depth
SBHP
Operators must allow sufficient time for unloading. The rule from API RP
11V5 is to take 10 minutes for each 50 psi increase in casing pressure up to 400
psi. After that point a 100 psi increase is acceptable until gas injects into the
tubing. To get up to 1000 psi should require at least 2 hr, 20 min. A good
practice is to assign an operator to the well for the duration of this
operation.
Pressure
Depth
Once the brine level is below the top valve, gas will enter the tubing and
begin lifting the well. If the tubing pressure is less than the SBHP the
reservoir will begin to contribute. The first production from the reservoir is
normally recovered completion brine. In PPO valve unloading, the valve
will tend to inject gas, close, re-open and repeat the cycle at each valve
while the brine is being unloaded.
Pressure
Depth
SBHP
SBHP
Pressure
Depth
SBHP
Pressure
Depth
Pressure
Depth
SBHP
Time
Start gas to
well
• Dual Gas-Lift
Completions
FTP=205,
LG=550
FTP=100,
LG=280
Assumed lift
depths
Zero injection
(natural flow)
100 mcfd
increments
Minimum
gradient
1. Unlimited Gas or
maximum
flowrate is
900 desired
800 2. Limited Gas or
the most
700
economical rate
Net Production(BPD)
600 is desired
500 3. Production is
fixed
400 3 2 1 • Water /gas
coning
300
• Sand
200 production
• Government
100 regulations
0
50 1002003004005006007008009001000
dQinj
900
700
Net Production(BPD)
600
500
Sub-optimum injecting points
400
300
200
100
0
50 1002003004005006007008009001000
• Causes
– Valve Interference
– Low injection gas, liquid production
– Incorrect size valve ports
– Poor lift gas supply control
– Variations in production system pressure
• Impacts
– Propogate instability in other wells
– Excessive G/L & control valve wear
– Production system upsets
• Remedies
– Design installations with good data
– Use effective control systems
– Operate within the envelope
BACKUP SLIDE