Professional Documents
Culture Documents
___________
Q.1 (a) What are the different types of contracts? Explain any one. 05
(b) Draft a tender for repair of windows and doors of military hospital having a 05
cost of 100 lakhs fees of tender is 10,000. Last date of tender is 15th January
2020.
Q.2 (a) Define the term: 1. Tender fees 2. Ernest money deposit 3. Surface 04
excavation, 4. Security deposit
(b) What is the significance of market survey? How the rate of an item is derived 06
by method of rate analysis?
OR
(b) Define rate analysis and write purpose of rate analysis. 06
Q.3 Find the quantity and rate analysis for 150 m2 area and 10 mm thick plaster. 10
OR
Q.3 (a) Explain the term specification. State the importance of it. 05
(b) Write short note on (i) Typical Bay method, (ii) prime cost. 05
Q.5 (a) Find the rate of Plain cement concrete (1:1.5:3) per cu.m. by rate analysis. 05
Assume suitable rates of material and labour.
(b) Give accuracy criteria for length, area and volume. 05
OR
(b) Which IS code is referred for the various measurements? Write the deduction 05
rules for plastering.
*******************