Technical project management in WASH emergencies

Your Project Gantt Chart (2)

Activities
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Negotiations with key


stakeholders
X X
Recruitment of project staff
- construction of water X X X
points

Boreholes sited with


community inputs X X X X X X
Identification of a drilling
rig and drilling team (which
included the tendering
X X X X X X
process)

Procurement of borehole
consumables, construction X X X X
materials and handpumps

Market analysis for spare


parts and consumables
X X X X X X
Provide health & safety
training
X X
Borehole drilling, pump and
water quality testing
X X X X X X X X X X X X X X
Installation of Asia Mk II
hand pumps
X X X X X X X X X X X X X X
Community consultation of
water point design
X X X X X X X X X X X X
Construction of the aprons
and drainage
X X X X X X X X X X X X X X
Water quality testing at
Asia Mk II handpumps
X X X X X X X