PENGAJUAN HARGA UPAH KERJA

PROYEK : PT. AVIAN AVIAN INDUSTRI PIPA (AAIP) - CIREBON

Pengajuan Mandor
No Pekerjaan Volume Sat
Satuan Harga Total
1 Pas Geotextile 1,488.25 M² 50,000 74,412,500
2 Strous dia.25cm Pembesian dan Cor By AB 744.00 M 40,000 29,760,000
3 Lantai Kerja 5 cm 21.46 M³ 40,000 858,400
4 Pas Batu Kali Include urugan pasir, pipa suling, ijuk setrikan 551.46 M³ 55,000 30,330,300
5 Sloof 20/30 Include bekisting, pembesian dan cor 459.10 M 70,000 32,137,000
6 Kolom 25/25 (Pondasi Pagar) Include bekisting, pembesian dan cor 314.72 M 70,000 22,030,400
7 Pagar Panel 6 Sap (t=2.4m) Include cor kolom pagar pricase 185.60 M 275,000 51,040,000
8 Pas Kawat duri 4 baris Include pasang siku 185.60 M 200,000 37,120,000
9 Pas U1000 x 1000 + Cover Include lantai kerja 5 cm, pas udit, nat dan cover 600.30 M 89,000 53,426,700
10 Pas U400 x 400 + Cover Include lantai kerja 5 cm, pas udit, nat dan cover 147.50 M 89,000 13,127,500
11 Pas U800 x 800 + Cover Include lantai kerja 5 cm, pas udit, nat dan cover 144.30 M 89,000 12,842,700
12 Pasangan Paving Include abu batu dan stemper 72.00 M² 140,000 10,080,000
13 Pasang Kansteen Include urugan pasir dan nat 24.00 M 140,000 3,360,000
14 RCP 80 Include lantai kerja 5 cm, pas udit, nat dan cover 140.00 M 89,000 12,460,000
JUMLAH 382,985,500
Harga sudah termasuk Andang dan APD