Handover :

1) Changeover for bilge ballast stripping valve :


Engine room bottom platform :
2 Valves ( One green color and one blue color )
Green one open for ballast stripping ( normally in open position only )
Blue one to be open when bilge stripping to be done.

When bilge stripping to be done :


Close green color valve ( ballast stripping valve )
Then open blue color valve ( bilge stripping valve )

After stripping done .


Close blue color valve . And open green color valve.

2) Sounding:
Total tanks : 22
SWT : 14
DB: 6
1 AFT
1FPT

Location :
SWT 1,2,3,4,5 ( P, S ) in Tunnel
SWT 7P 7S ( Cross deck hold no. 10 and no.9 )
SWT 6P 6S ( Cross deck hold no. 8 and 9 )
Db 6 ( bottom platform )
DB 1,2,3,4,5 ( Cross decks )

Fresh water corr :


Port Side – Add 0.10 to the sounding
Stbd side – Add 0.15 to the sounding

Temp . Check :
Dry wet entries to be made in white color book . Daily temp log book

Bilges sounding to be updated in red color book .


Other soundings to be updated in back pages of red color book.

Aft peak line setting :