Professional Documents
Culture Documents
αdLT = 30 units
c)
Safety stock with 2% stock out risk is less than that of 1% stock out risk.
a)
Z(99%)= 2.33
ROP = Expected demand during lead time + zαdLT = 300 + 2.33 x 30 = 370 unit
Z (98%) = 2.06
Therefore safety stock amount with 2% acceptable stock out risk is less than that for 1% risk.
2. A home appliances manufacturer usage 48,000 motors per year for its blender series.
The firm makes its own motors, which it can produce at a rate of 600 per day. The blenders
are assembled uniformly over the entire year and it operates 240 days per year. Monthly
carrying cost is $0.6 per motor. It takes a full day to setup the system for a production run
at a cost of $288. -
a) If the motors are periodically produced in batches of 3000 units, what penalties is the
firm incurring at this production level? What is your recommended run size? (4 points)
- b) Compute the
maximum inventory level at your recommended run size. What will be the inventory level
after 6 days from the start of a run? (2 points)
- c) The same process
that is used to make the motor could also be used to make a component for another firm.
That job would require nine days, including setup time. Is there enough time to do this job
between production of batches of motors? Explain (2 point) -
d) Suppose the manager decides to increase the run size of the new product. How many
additional units would be needed to just accommodate the other job? How much will that
increase the total annual cost? (2 point)
Soltion
a)
D = 48000 units/year
S = $288/run
H = $0.6 x12 = $7.2/unit-year
P = 600 units/day
u =48000/240 = 200 units/day
EPQ = SQRT(2DSp/H(p-u)) = SQRT( 2 x 48000 x 288 x 600/(7.2 x (600-200)) = 2400 units/run
Cost (Q = 2400) = DS/Q + HQ(p-u)/2p = 48000 x 288/2400 + 7.2 x 2400 x (600-200)/(2x600)
= $11520
Cost (Q = 3000) = 48000 x 288/3000 + 7.2 x 3000 x (600-200)/(2x600) = $11808
So penalty incurring = 11808 -11520 = $288
Recommended run size = 2400 units/run
b) Imax = (p-u) x Q/p = (600 -200) x 2400/600 = 1600 units
Run time = Q/p = 2400/600 = 4 days
Cycle time = Q/u = 2400/200 = 12 days
Inventory level after 6 days = ( 4 x 600 – 6 x 200) = 1200 units
c) Idle time = 12 -4 = 8 days
Required time = 9 + 1 = 10 days
Since required time is more than available time so there is not enough time to do the other
job
d) Required time to accommodate the other job is 10 days
So production time per run would be = 12 – 10 = 2days
Production size = 2400 units
Rate of production = 2400/2 = 1200 units/day
Cost = 48000 x 288/2400 + 7.2 x 2400 x (2400 – 200)/2 x 2400 = $13680
Increase in cost = 13680 – 11520 = $2160.
a)
ROP = Expected demand during lead time + Safety stock
ROP = Expected demand during lead time + zαdLT
Expected demand during lead time = 300 units
Std. dev. of lead time demand, αdLT = 30 units
Risk of stock-out = 1%
Service level = 100 – 1 = 99%
No. of std. dev. Z (99%) = 2.33
ROP = Expected demand during lead time + zαdLT = 300 + 2.33 x 30
= 370 units
b) Safety stock = zαdLT= 2.33 x 30 = 70 units
c) risk of stock out = 2%
Service level = 100 – 2 = 98%
Z (98%) = 2.06
Safety stock = zαdLT= 2.06 x 30 = 62 units
A risk of stock out of 2% require less safety stock than 1% stock out risk.
Solution:
a)
d = 21 g/week, αd = SDd = 3.5 g/week, Lead time, LT = 2 days = 2/7 weeks
αlt =Sdlt = 0
Service level = 90%, z(90%) = 1.28
b)
d = 21 g/week = 3 g/day
OI = Order interval = 10 days
LT = lead time = 2 days
αd = 3.5 g/week = 0.5 g/day
Service level = 90%, Z(90%) =1.28
Amount on hand at the time of order, A = 8 gallons
Amount to order = 3 x (10 +2) + 1.28 x 0.5 x SQRT(10+2) – 8 = 30.22 gallons
ROP = 8 gallons
8 = 21 x 2/7 + z x SQRT(2/7 x 3.5 x 3.5 + 3 x 3 x 0 x0)
8 = 6 + 1.87 x Z
Z = 2/1.87 = 1.07
Service level = 0.8577 = 85.77%
Risk of stock out = 100 – 85.77 = 14.23%
c)
S = $1/order
H = $0.40/roll
d = 10 rolls/day,
αd =SDd = 2 rolls/day
LT = 3 days
αlt = 0
d)
E(z) = Standardized short = 0.016 ( for 96% service level) from table 13.3
a)
ROP = 21x2/7 + 1.28 x SQRT(2/7 x 3.5 x3.5 + 21 x 21 x 0x0) = 6 + 2.39 = 8.39 gallons
b)
Amount to be ordered = 21 x (10/7 + 2/7) + 1.28 x 3.5 x SQRT(10/7 + 2/7) – 8 =36 + 5.87 – 8 = 33.87 gallons
ROP = 8 gallons
8 = 6 + z x 1.87
Z = (8-6)/1.87 = 1.07
c)
6.39 = 6 + z x 1.87
S = $1/order
H = $0.40/roll-year
b)
d)
a)
b)
Order Qty = 21 x (10/7 + 2/7) + 1.28 x 3.5 x SQRT(10/7 + 2/7) – 8 = 36 + 5.87 – 8 = 33.87 gallons
ROP = 8
8 = 6 + 1.87 x Z
Z = (8-6)/1.87 = 1.07
c)
6.39 = 6 + z x 1.87
(ROP = 5.5
5.5 = 6 + z X 1.87
Solution
{ROP = d x LT + zσd√ ¿
(If lead time is fixed, that is no variation in lead time so zero std. dev.)}
c)
D = 3600 rolls
d)
Q = 134 rolls