You are on page 1of 12

i An update to this article is included at the end

Desalination 261 (2010) 321–330

Contents lists available at ScienceDirect

Desalination
j o u r n a l h o m e p a g e : w w w. e l s ev i e r. c o m / l o c a t e / d e s a l

Pilot studies on high recovery BWRO-EDR for near zero liquid discharge approach
Y. Oren a,⁎, E. Korngold a, N. Daltrophe a, R. Messalem a, Y. Volkman a, L. Aronov a, M. Weismann a,
N. Bouriakov a, P. Glueckstern b, J. Gilron a
a
Department for Desalination and Water Treatment, Zuckerberg Institute for Water Research, Ben-Gurion University of the Negev, P.O. Box 653, Beer-Sheva 84105, Israel
b
Mekorot Development & Enterprise LTD, Israel

a r t i c l e i n f o a b s t r a c t

Article history: A hybrid process combining reverse osmosis and electrodialysis has been shown to be effective in recovering
Received 24 May 2010 97–98% of brackish water as product water with chloride levels of 200 mg/L or less. Potential for scaling on
Received in revised form 1 June 2010 the brine side of the electrodialysis unit was prevented by acidification, operating the electrodialysis in a
Accepted 2 June 2010
reversal mode (EDR), and a side loop crystallizer which prevented buildup of scaling components. Settlers,
Available online 29 June 2010
inline microfiltration, and side-loop ultrafiltration kept suspended solids from returning to the EDR unit. This
process was demonstrated in a series of more than eighty batch experiments of 1.5 to 1.8 m3 of RO
Keywords:
BWRO
concentrate of raw brackish groundwater from the Negev Highland, Israel. Each batch could be processed
EDR within a single day. The feed-water was concentrated from 0.3% to over 10% TDS super-concentrate while
Near ZLD producing the water that could be recycled to the RO permeate. This super-concentrate from the EDR unit
Inland desalination was further concentrated in a wind powered WAIV unit that brought final brine TDS to N 30%, and showed
promise as a method to recover mineral byproducts such as magnesium salt. Initial economic estimates show
that this hybrid process is competitive with conventional RO and other enhanced recovery processes for
inland desalination requiring use of evaporation ponds.
© 2010 Elsevier B.V. All rights reserved.

1. Introduction will put out treated effluent with a higher salt load than may be
permitted for downstream use. While deep well injection is used in
Inland brackish water desalination is becoming an important some regions, such as Florida, the geological conditions are not always
source for water in particular in areas that are remote from the sea. appropriate for this solution. Land disposal can lead to salinization of
According to Zhoua and Tolb [1], 23% of the installed world soil and must usually be diluted with secondary wastewater effluent
desalination capacity comes from deep and shallow brackish water. before application. Mechanical/thermal evaporation is economically
As desalination is applied in increasingly larger scale and varied prohibitive in many cases.
locations, the issue of concentrate disposal is becoming an increasing The philosophy behind the zero liquid discharge (ZLD) approach is
challenge [2–4]. Estimates show that it can be in the order of 15% of to further concentrate the brine towards near or, if possible to
the costs of desalination in the case of inland sites [5]. This is especially complete dryness in cost effective methods. The removed water can
so at many inland installations which are located more than 80 km be recycled to the process for increasing its recovery ratio. The
from the sea coast where disposal of concentrate to the sea becomes remaining, reduced volume waste is a dry or semidry solid that should
economically prohibitive. Mickley [4] has surveyed the various be disposed off in special sites.
methods for dealing with concentrate. These include: discharge to The various kinds of brine volume minimization schemes using
surface waters and wastewater treatment plants, deep well injection, thermal, membrane and other techniques have been reviewed by van
land disposal (spray irrigation), evaporation ponds, mechanical/ der Bruggen et al. [6]. Mechanical/thermal evaporation is usually
thermal evaporation (zero discharge). The use of the first three applied to reach zero discharge because of the highly concentrated
options depends on the geographical location and the nature of the solutions that must be evaporated. This has been most intensively
brine. Sometimes in inland locations, surface waters that would not be used in the power industry where waste heat is abundant and
significantly polluted by the brine are not available. If they receive regulations severely limit the discharge of effluent [7,8]. A major
concentrate from large-scale desalination installations, sewage works problem with evaporation of such concentrated brines is the
formation of scale on the heat exchange surfaces. Various special
evaporators have been constructed and seeded precipitation techni-
ques have been proposed to overcome this problem [9,10].
⁎ Corresponding author. Where thermal techniques are required, the high-energy cost of
E-mail address: yoramo@bgu.ac.il (Y. Oren). thermal evaporation, even with highly efficient evaporators, creates a

0011-9164/$ – see front matter © 2010 Elsevier B.V. All rights reserved.
doi:10.1016/j.desal.2010.06.010
322 Y. Oren et al. / Desalination 261 (2010) 321–330

premium on pre-concentrating the brine by other techniques MF or UF can guarantee that micro-crystallites are eliminated by
beforehand so that only the smallest volumes will be fed to the removing crystal nuclei above the critical size.
evaporators. RO is often proposed for this purpose [11,12], but A pilot unit, capable of treating BWRO concentrate at a maximum
recoveries are limited by sparingly soluble salts. ED has also been used rate of 500 L/h was constructed at the BGU Desalination Pilot
for this purpose and has been combined with RO to reduce the overall Facilities. In this article we present the results obtained from long-
volume sent to brine concentrators [12]. However the overall recovery term operation experiments with raw brackish water taken from the
of the combined ED/RO step was still only 64% of the feed derived brackish water well field at the Negev Highlands, Israel. This article
from ion exchange regeneration and RO brine from the pre-ion will be mainly focused on the RO-EDR-Crystallizer/settler-UF chain.
exchange desalination step [12]. This is in part also due to The WAIV piloting results were discussed in a separate publication
precipitation of sparingly soluble salts in either the RO or ED stages. [18].
Rautenbach and coworkers [13,14] have proposed a way to overcome
this in ED by using seeded precipitation from the ED brine stream with 2. Experimental
a settler to remove the precipitated solids. It has been found [16] that
this is problematic because of hydraulic limitations in settlers 2.1. The pilot concept
requiring impractically large tank volumes when dealing with the
flow rates to be expected in actual BWRO processes for drinking water In this study a combined process is investigated to increase water
production. recovery and approach zero liquid discharge from RO brackish water
ZLD has been regarded for many years as an uneconomic solution desalination brines. The processes integrated as a treatment chain are:
and, therefore was employed in limited cases. However, the a) Electrodialysis reversal (EDR) operating on the RO concentrate; b)
increasing rate of population growth, scarcity of water in many places Crystallizer/settler with microfiltration or ultrafiltration (MF/UF) to
around the globe, and the growing awareness about the need for relieve supersaturation of sparingly soluble salts in the brine recycle
environment protection has brought this issue back to focus. stream of the EDR process; and c) Wind Aided Intensified Evaporation
Accordingly, new ZLD technologies are today developed and new, (WAIV) [15] to turn the bleed from the ED brine recycle stream into a
more cost-effective options are now available. Furthermore, there is a solid or semisolid.
long-term practical experience available for designing new industrial The scheme illustrating the concept of the studied processes is
plants and for optimizing the functions of existing plants. In particular shown in Fig. 1. A brine stream (1) from an RO desalination process is
this experience includes innovative solutions in handling industrial fed to an ED unit where it is desalted. The desalted stream (2 + 3) is
streams and municipal wastewater. In other words, the ZLD approach returned as a feed to a second RO stage or can be added to the main RO
is becoming an important strategy in managing water resources permeate stream (4), depending on the quality of stream (2). The
towards maximizing water savings, reducing desalination and water brine stream (7) of the EDR unit, more than 10% in TDS, is fed into a
treatment costs and protecting water resources and the environment. crystallizer, pumped through a submerged UF membrane module and
In this investigation a series of processes involving EDR and WAIV circulates (7′) through the EDR brine compartments. Sparingly
[15] are operated in a fully synchronized fashion to achieve the soluble salts are precipitated within the seeded crystallizer and
following goals: a) Increasing the overall recovery of the desalination collected at its' bottom. Since the antiscalant used in the BWRO is left
process and the cost of brine handling by minimizing its volume and in the EDR diluate stream (2) and do not reach the brine stream (7),
by recycling the water that is removed from the brine; b) Prevention the crystal growth in the latter to relieve supersaturation can occur in
of scaling and fouling in the EDR and WAIV units which could an unimpeded fashion.
otherwise lead to water production loss or increased energy To prevent the return of the suspended crystal solids to the EDR
consumption; c) Reduced energy consumption due to exploitation stack, a settling tank is installed after the seeded crystallizer from
of wind energy and synergetic combination of the processes, and d) which the clear non-turbid supernatant is pumped through a dead
Preservation of the vapor pressure driving force in the WAIV unit by end submerged ultrafiltration unit. This is done to remove the
prior removal of ions such as calcium and magnesium that otherwise suspended solids so that a crystal-free stream (7′) is returned to the
would lead to concentrated solutions with low vapor pressure. If brine recycle stream containing much lower content of sparingly
greater volume reductions were required, magnesium could be soluble salts, thus approaching their saturation concentration. It is
precipitated in the crystallizer by adding base and carbonate. clear that the settler is limited by the rate at which crystallites could
While electrodialysis has been proposed in the past for recovering settle by gravity and small crystallites could be entrained in the up-
water from RO concentrates, it has not been operated with high levels flow, thus limiting the crystallizer's capacity. Similarly it has been
of brine concentration (N10% TDS) in the brine recycled stream, and found that filters with pore size above 1 μm will not adequately retain
also it has not previously been tested on RO concentrates from the crystallites and in such case precipitation will occur in the recycle
brackish waters. In previous work by Korngold et al [16,17]), it was stream (7′).
shown that these concentration levels could be achieved with EDR, A bleed stream (6) containing a high content of dissolved and
provided that CaSO4 scaling is avoided by a constant removal through suspended solids is led away from the crystallizer. Bleeding rate from
precipitating in a seeding/settling device. By operating at such high the crystallizer tank is governed by the rate of osmosis and
EDR brine concentrations and reducing the diluate concentration to electroosmosis through the ion exchange membranes in the EDR
that of an inter-stage RO feed, the overall voltage drops could be kept unit. This bleed stream is fed to the WAIV unit where wind evaporates
at the lowest possible. Subsequently, energy consumption in this EDR the remaining liquid and the deposit drops off the evaporation
step is minimized. surfaces onto collection troughs underneath the WAIV unit. The WAIV
While seeded precipitation has been proposed in the past to unit itself could in some circumstances be used for precipitation of the
reduce supersaturation in the electrodialysis brine [13,14], the sparingly soluble salts in place of the crystallizer, and the liquid that
method involved sludge contactors and settlers. These place a runs off the bottom of the WAIV evaporation surfaces will be returned
hydrodynamic restraint on the process since linear flow rates up to the brine recycle stream (7′) of the EDR.
through the settler cannot exceed the settling velocities of the
smallest crystals. As a result, when large volumetric rates must be 2.2. Equipment and operational conditions
treated by such precipitation, huge tank volumes may be required. By
introducing a barrier of MF or UF, it is expected to limit the tank RO concentrate of raw brackish groundwater from the Negev
volume to that needed for contact time to cause precipitation. Also, Highlands, Israel was prepared in a 1 m3/h unit with four 4 in. × 40 in.
Y. Oren et al. / Desalination 261 (2010) 321–330 323

Fig. 1. Schematic presentation of the proposed ZLD process.

Filmtec BW-30 RO membrane modules (two pressure vessels, system was operated for 6–12 h per day with polarity reversal every
connected in parallel, each containing two modules). The system 1 h. Before shutting the unit down after each operation period, it was
was operated in an open loop concentration mode, namely the 250 L operated for half hour with unsaturated solution at short circuit and
feed tank of the unit was filled with raw brackish water which was fed bypassing the crystallizer and the settler to wash out the over-
to the membrane modules by a high pressure pump. The concentrate saturated solution in the brine container and brine EDR cells.
was recycled to the tank, while permeate was withdrawn and The typical ionic compositions of the raw brackish water feed to
discarded. During the initial experiments, raw water was added the RO unit and the BWRO concentrate are given in Table 1.
periodically to the tank to replenish the amount of permeate until the Sulfuric acid was added to the EDR diluate feed to reach a pH 4 at
planned VCF (volume concentration factor) ranging from 4.0 to 8 was the beginning of each batch, and periodically to the electrode rinsing
achieved. In the following experiments the raw water was continu- solutions to maintain a pH 1.5 to 2 so that the EDR brine pH was stable
ously added to the feed tank while withdrawing the concentrate at a in the range of 2.0 to 2.2. Blow down of the EDR brine was controlled
constant concentration or VCF. The requested salt level in the by the conductivity that was kept constant (80 mmho/cm at the initial
concentrate was obtained by adjusting precisely the recycling flow experiments and 140 mmho/cm in the later ones). The make up for
rate. the EDR brine was done automatically with tap water at about 10 l/
The raw water was pre-treated by acidification with HCl to h and by electroosmosis through the membranes of the diluate
pH = 6.5 and by addition of sodium hexametaphosphate (Calgon) or compartments.
PC191(PermaTreat) as antiscalants. The recycle flow rate was kept Seeded crystallization and settling tanks were made of polypro-
constant at 1160 L/h. Permeation rate changed gradually from 320 L/ pylene with volumes of 680 L and 830 L respectively. In typical
h at VCF = 1 to 130–150 L/h at VCF = 4. Feed pressure to the experiments they contained 600 L and 633 L of EDR brine solution
membrane modules was set at 14.9 bars. The rejection (based on respectively.The UF crystallizer was equipped with two 1 m2 Zee-
conductivity measurements) was continuously monitored and kept at Weed-500 (by GE-Zenon, Canada) module, composed of reinforced
96–97%. hollow fibers with pore-size of 0.04 μm and made of PVDF. Each
An EDR stack by PCCell GmbH (Germany), Model EDR ED 1000H module was installed within a 30 L tank containing 18 L solution. The
with the following characteristics was used: 50 cell pairs fed in parallel, two containers are connected in parallel with a self sustained flow
total active area, 5 m2 with Asahi AMV and CMV membranes and control system that allows well controlled and timed backwash. The
spacer thickness 0.5 mm. Membrane area for electrical current flow is vacuum range applied by a peristaltic pump to the inner side of the
1000 cm2. The EDR rack system with piping, controls and power hollow fibers is 17 to 24 kPa with filtration rate of 200 to 160 l/
supply was constructed by Nirosoft, Israel. An artist view of the EDR h which is just a fraction of the total 550 l/h circulated through the
unit with its controls and the accompanying tanks is shown in Fig. 2. EDR brine tank. Backwash with UF product water was employed for
In each experiment 1500 to 1800 L of BWRO concentrate was 30 s every 5 min and chemical cleanings with citric acid 2% and with
circulated through the EDR diluate compartments from a 2000 L tank. deionized water was used occasionally.
The volume of the EDR brine container was 100 L. Brine and diluate
flow rate through the EDR stack were 500 to 700 l/h, corresponding to 3. Results and discussion
an average linear velocity of 2.5 cm/s. The maximum calcium sulfate
oversaturation in the stack reached 35%. Cell-pair voltage was 0.5–1 V, The EDR diluate composition for a typical experiment as a function
and current density was in the range 10 to 22 mA/cm2. The EDR of the experiment time and the EDR brine composition as a function of
324 Y. Oren et al. / Desalination 261 (2010) 321–330

Fig. 2. An artist view of the EDR with tanks.

the experiment number are presented in Figs. 3 and 4 respectively. It emerging from the EDR may be limited unless some measures are
is clear from Fig. 3 that the concentrations of all the ionic components taken to reduce silica concentration. This can be done for instance, by
in the diluate decrease steadily during each single batch experiment. combining the EDR diluate stream with the BWRO product where an
A clear exception in this case is silica as its concentration remains estimated dilution by a factor of 4.5 could be achieved.
almost unchanged. It should be noted that the rate of decrease of An analysis of the buildup of the EDR brine composition during the
chloride ions with CMV and AMV membranes used in these first 43 batch experiments shown in Fig. 4 reveal that the concentra-
experiments was comparable to that of the sulfate ions, in contrary tions of ions such as Cl− and Mg2+ of soluble salts increased steadily,
to the case with AMT CMT membranes used in the previous small while those of SO2− 4 and Ca2+ increased more slowly due to CaSO4
scale experiments where chloride ions were removed faster than precipitation. As the equivalent concentration of sulfate in the EDR
sulfate[5]. However, the rate of silica removal through these feed solution was higher than that of Ca2+, its concentration in the
membranes was significantly lower compared to that with AMT/ EDR brine slowly increased and Ca2+ concentrations changed in
CMT. This phenomenon may be attributed to the differences in water response to solution composition. As can be seen in Fig. 4, SiO2
splitting rate at the membrane/solution interface between the two concentration in the EDR brine remains almost constant, at ∼30 ppm.
types of anion exchange membranes being lower with the CMV/AMV A total salt concentration of 1.5–1.8 N was reached implying 97.5 to
membrane pair. This important point is now under thorough 98% recovery ratio. The time averaged coulombic efficiency for
investigation. Transport rate of silica may be of a crucial importance achieving that is 70 to 80%.
in the current process since on one hand, upon crossing the Turbidity and the percent of CaSO4 oversaturation in the EDR brine
membrane to the EDR brine compartments it may cause precipitation stream immediately at the outlet of the brine compartments are
of silica and silicates (such as talcum — Mg3Si4O10(OH)2) on the shown in Figs. 5 and 6, respectively. The turbidity shown in Fig. 5 was
membrane surface or within the brine compartment. Once this monitored for 25 h on a constantly stirred sample taken from the EDR
happen the hydrodynamic resistance of the brine compartments as brine vessel, indicating a continuing increase due to CaSO4 precipi-
well as the electrical resistivity of the anion exchange membranes tation in the highly oversaturated solution. After the brine stream had
may significantly increase. These phenomena were clearly observed in passed through the precipitator, gypsum oversaturation was in the
the previous, small scale experiments [5]. On the other hand, if silica range of 2 to 5%, as in the previous study [17], and turbidity after 1 μm
remains intact in the diluate, further use of the product water filtration was at the range of 0–0.1 NTU. The percent of CaSO4

Table 1
Composition of raw brackish water feed and BWRO concentrate (VCF = 3.5–4).

Ions Conductivity. Cl− Ca2+ Mg2+ SO2−


4 F− Sr2+ Ba2+ K+ Na+ SiO2 P Al3+ Cu2+
−1
Units mmho cm ppm
Solution

RO feed 4.44 1115 196 415.5 1.38 5.60 0.04 18.4 651 24.07 0.00 0.06 0.02
RO concentrate 15.54 4817 959.4 378.5 2560.3 6.22 23.3 0.18 70.4 2024 87.33 0.98 0.08 0.03
Y. Oren et al. / Desalination 261 (2010) 321–330 325

Fig. 3. EDR diluate concentrations of several ions vs. time during a single experiment Fig. 5. Turbidity of an oversaturated EDR brine solution vs. time at the exit of the stack
with 5 m2 stack. (experiment 36). In this case, after sampling the turbidity in the sample was monitored
as a function of time while stirring.

oversaturation in the brine stream and in the precipitator was


measured during all the EDR experiments. Examples of these is determined at different times during the experiment as a function
measurements are given in Figure 11 in [17]. Fig. 6 shows that at of the logarithmic mean γ D ̅ of the specific resistances of the inlet and
the beginning of each experiment, when Ca2+ electro-transport flux is outlet solutions in the diluate compartments. In most of the cases, a
high, the extent of oversaturation increased but becomes low at the fairly good linear regression could be obtained.
end of the experiment due to reduced Ca2+ ions transport rates. The This behavior can be interpreted as follows: At each time domain
total precipitation rate was 300 to 400 g gypsum per hour. during an experiment, the total stack resistance is an algebraic
Water composition was examined continuously in the EDR diluate summation of the single resistances of the different components in
and brine solutions. Salt content in the BWRO concentrate was the stack according to,
reduced to a level of 18–20 mN, which is suitable for mixing with the
BWRO permeate as illustrated in Fig. 1. The change of cell-pair   Ncp lξ
C A
Rstack = Relectrodes + Ncp RM + RM + ðγD + γB Þ ð2Þ
resistance of the EDR stack with brine compartment concentration is A
shown in Fig. 7 for some different experiments. As expected, the
resistance of the stack decreases as the brine conductivity increases. where, Relectrodes, RCM, RAM, Ncp, A, γ̅D, and γ̂ B are the resistance of the
There are also no significant differences in that respect between the electrode compartments, the resistance of the cation and anion
different experiments. However, as discussed below, a closer look at exchange membranes, the number of cell pairs (50 for the present
the results reveals a different, unexpected behavior. case), the membrane area available for the flowing current (in the
The total current, Itotal flowing through the stack, the applied present case, 1000 cm2), the specific resistances of the diluate and the
voltage Vtotal and the specific resistance of the inlet and outlet solution brine compartments (logarithmic averaged between the inflow and
in the diluate compartments were constantly monitored as a function outflow solutions), respectively; l is the geometric gap between each
of time during each experiment, from these measurements the total two membranes in the diluate and brine compartments and ξ is a
stack resistance Rstack expressed as parameter convoluting the shielding effect of the spacer forming the
gap between each two membranes and the effect of membrane and
Vtotal spacer fouling and scaling due to precipitation of organics and
Rstack = ð1Þ
Itotal sparingly soluble components. Taking this into account, ξ is always
larger than 1. The effective inter-membrane gap leff., is defined as,

leff : = lξ ð3Þ

Fig. 6. Gypsum oversaturation in brine at the exit of the EDR stack as a function of the
Fig. 4. Changes of brine concentration vs. the experiment number with 5 m2 stack. experiment duration, during experiment number 37.
326 Y. Oren et al. / Desalination 261 (2010) 321–330

practically unaffected by the experimental conditions while leff


increased by at least 60% in the course of experiments 60 to 65
indicating an increase in the stack internal resistance.The actual
reason for that is yet unclear but it is suspected that precipitation of
sparingly soluble salts happened within the stack during experiments
60 to 65 when a changed was made in the VCF of the BWRO
concentrate from 4 (75% recovery) to 8.3 (88% recovery) in order to
tests the limits of the process with respect to the brackish water used
in these experiments. It was also assumed that the low silica transport
through Asahi AMV membranes composing the EDR stack will allow
an increase in the silica concentration in the BWRO concentrate/EDR
feed that eventually will not precipitate in the EDR brine circulation
lines. However, the BWRO concentrate, becoming oversaturated with
silica and gypsum due to the high VCF, probably resulted in these
precipitating in the EDR diluate lines, causing an increase in stack
electrical resistance as reflected in leff. In the experiments following
Fig. 7. Electrical resistance per cell pair vs. ERD brine conductivity with RO brine and
65, VCF = 4 was used again. Nevertheless, the original leff values could
NaCl solution (5289 ppm Cl− in tap water) as feeds.
not be restored even after a thorough cleaning procedure including
NaOH at pH 11, sodium metabisulfite 1% and deionized water.
Assuming that the resistance of the electrode compartments and the The above conclusion is supported by a mass imbalance of some
membranes remains practically constant throughout an experiment, ions and silica between the inlet and the outlet streams in the BWRO
and γ ̅B bb γ ̅D, Eq. (2) is reduced to, concentrate, indicating a possible precipitation even at this early stage
in the treatment chain. In the BWRO concentrate, we used 1 ppm
0 Ncp leff : Calgon, or PC 191 as antiscalants which prevent scaling only for a few
Rstack = Rstack + γD ð4Þ
A hours. However, for the EDR step, the BWRO concentrate was stored
for up to one day in the EDR feed tank so that at the conditions of 88%
where, R0stack = Relectrodes + Ncp(RCM + RAM), is the stack resistance when recovery (VCF = 8.3) scaling could occur both in the EDR diluate feed
solution with high concentrations are flowing through the diluate and tank and in the diluate compartments. Therefore, in the experiments
brine compartments where practically their ohmic resistance is that followed 65, the BWRO recovery was maintained at 75%
negligible. Since, as assumed above no change of electrode and (VCF = 4) to avoid further precipitation due to high oversaturation.
membrane resistance occur during an experiment as well as at the In fact, when using a “once through” flow mode in the diluate
different experiments, this parameter should remain practically compartments, higher recoveries of the BWRO concentrate / EDR feed
constant. can be considered only if it appears that there is no risk of silica
From the slopes of the regression lines of Rstack vs. γ ̅D, leff. can be precipitation within the EDR stack.
calculated according to, Energy requirement for EDR as a function of brine concentration
shows that 5–6 kWh/m3 are required for desalinating the BWRO
A concentrate from 200 mN to 20 mN. Fig. 9 shows a typical trend of the
leff : = ðslopeÞ ð5Þ
Ncp total energy consumption as well as of each one of its components
during a batch experiment while reducing the salt content in the EDR
Fig. 8 shows the trends of both leff and R0stack during the experiments diluate stream. In these calculations the mixing energy demand in the
ranging from 42 to 81. The BWRO concentrate in the various crystallization/precipitation tank as well as that for the total pumping
experiments was prepared according to the following conditions: in in the system, were taken into account in addition to the energy
experiments 42 through 59 and 66 through 81, the VCF was 4 and demand for the desalination process. Since the three components are
Calgon (sodium hexametaphosphate) was used as an antiscalant; in dependent on the desalination time, they increase upon reducing the
experiments 60 through 65, the VCF was 8.3 while the antiscalant is salt content in the diluate stream. As long as the diluate concentration
PC 191. It is clear from the Figure that, as expected, R0stack remains is high enough a linear relationship between the different energy

Fig. 8. Effective inter-membrane gap and the EDR stack resistance at high solution
concentrations in the diluate and brine compartments as a function of experiment
number. The BWRO concentrate feed conditions at the different experiments are noted
on the abscissa: Calgon and PC 191 are commercial formulas added as antiscalants to Fig. 9. Cumulative energy requirement for BWRO concentrate desalination by EDR.
the BWRO feed. Starting and final concentration are 198 mN and 18 mN respectively (experiment 44).
Y. Oren et al. / Desalination 261 (2010) 321–330 327

components and the diluate concentration is observed. This tendency where for the base case YRO,base is taken as 88%, and UP is the value of
is changed towards the lower concentrations as longer time periods the additional product water (taken as 3.5 NIS/m3 = 0.73 €/m3 after
are required to desalinate each unit volume of the diluate stream. Jan 2010 based on average Israel water tariff cited in [22]). Using the
The experiments conducted with the UF setup were aimed at relation in Eq.(10) we generate the upper bound for the unit process
learning about the water quality that can be obtained and the integrity costs of the EDR step as a function of recovery in the RO step and the
of the membranes under long operation. In these sense, the results are value of the total recovery.
quite promising as turbidity b0. 1 NTU were obtained in all the To calculate the present energy and capital costs for the ED step we
experiments and the membrane integrity was preserved. However, in took the actual energy usage and pressure drops from the above pilot
order to maintain a smooth operation and to avoid high TMP's, a study. Future developments and system understanding may allow
backwash practice was applied as mentioned in the Experimental improved economics. The actual values for calculating energy
section. It should be stressed that in this phase of the study just part of consumptions and pressure drops are provided in Table 3-A and
the settler outflow was treated by the UF unit. These conditions are far were discussed in the previous section.
from satisfactory and in future studies this unit will have to be more The extent of salt removal required in EDR is related to the extent
challenged. of chloride removal since this is the ion that is most challenging for
both drinking and agricultural purposes. To calculate the total amount
4. Economic analysis of chloride removal required we set up a mass balance for the chloride
ion in the feed, concentrate and total product streams:
The economic analysis for the RO/EDR/UF crystallizer–settler/
Brine disposal treatment chain was carried out on the basis of a Vtot Ctarget + Vdsp Cdsp = VFeed CFeed VFeed CFeed
comparison of relative energy, chemical and capital costs based on  
Ctarget
costs in Israel. The operating and capital costs used as a basis for Vdsp Cdsp = VFeed CFeed ⋅ 1−Ytot ⋅
CFeed
comparison are given in Table 1-A. Energy, capital charge and brine    
removal costs are provided in Table 2-A. = VD;out CR;RO −CD;out + VR;RO −VD;out ⋅CR;RO
To simplify the calculations, we have only used the feed
ð11Þ
abstraction/pretreatment, power and capital costs for the RO section
since these are the main contributors to the costs of this section as a
The second equality in this equation shows that the total amount of
function of recovery with other cost centers being relatively
chloride to be removed in the EDR step depends on the total recovery,
insensitive. Chemical costs for acid in the EDR section are also
but does not depend on how the total volume recovery is achieved
included, based on 105 €/metric ton of sulfuric acid. The overall costs
between the RO and ED steps. However the amount removed in the EDR
for the desalination and brine recovery can be divided into three cost
step will be divided between the part removed by the current and the
centers, that is, RO, EDR-UF-settler and brine disposal.
part removed by direct volumetric transfer from the RO concentrate to
The overall costs/m3 of product water is given by the following
the EDR brine. In addition, the energy requirements of the EDR step is a
equations:
function of the recovery in the RO step, because higher recovery in the
WCtot = UCRO ⋅VRO + UCEDR ⋅VEDR + UCBrine ⋅VBrine ð6Þ RO step allows higher average diluate concentrations in the EDR, leading
to lower resistance and power consumption. This is shown by the
where V is the volume (m3) concerned, WCTOT is the total water cost, following equation for the specific EDR power consumption:
UC are unit water costs (€/m3) and subscripts refer to the process step. !2
The overall unit cost for product water is therefore given by: Ncp Q D ΔCD
EEDR = 2⋅ΔPst RR = ηpump + F Rcp : ð12Þ
QD ηEDR
WCtot Y Y 1−Ytot
UCtot = = UCRO ⋅ RO + UCEDR ⋅ EDR + UCBrine ⋅ ð7Þ
VRO + VEDR Ytot Ytot Ytot
The subscript CP refers to cell pairs and RCP is the cell pair
where Y refers to the product water volume relative the feed volume. resistance, Q DΔCD is the rate of total anions (or cations) removed.RR in
To gauge the economic viability of EDR for enhanced recovery the expression (12) is the recycle rate referring to how many times the
case of Negev Highlands well water is considered with the diluate must be recycled through the stack per rate of diluate
composition given in Table 1.With the present generation of production. While the actual value in the pilot experiments was 3.5,
antiscalants, it is possible to treat Negev Highlands water to 88% for economic calculations we used RR = 1, i.e. a once through
recovery (Glueckstern, [19]). If no further recovery is used (namely, arrangement but with more than one stack in series for achieving a
YRO = YTOT) this gives the following total water cost per unit volume: similar product composition. The number 2 comes from the require-
ment to recycle the concentrate stream of the stack at the same rate.
1−YRO;base 3 For EDR operation on the RO brines studied in the lab pilot unit, it
UCTOT = 0:301 + 1:4⋅ = 0:491 € = m ð8Þ
YRO;base was shown that most of the current was used to remove chloride as long
as the ratio of chloride to sulfate did not drop below 0.8. On the other
This sets an upper bound on the costs of the EDR treatment step. hand, in the larger scale pilot plant (5 m2 of cell pairs) using different
Setting EDR process costs and brine disposal costs of EDR concentrate membranes, a smaller fraction of the current was carried by chloride
equal to the base case RO brine disposal costs and lost product water ions in the anion exchange membranes. The overall review of existing
from RO brine gives: pilot data confirms that for a final chloride concentration of 200 mg/L in
the RO permeate — EDR diluate blend, the ratio of equivalents of
UCBrine ð1−Ytot ÞVFeed + UCEDR YEDR VFeed b chloride removed to total equivalents of anions removed in the EDR step
    ð9Þ
bUCBrine 1−YRO;base VFeed + UP Ytot −YRO;base VFeed was about 0.67 and this was used throughout the rest of the calculations.
At the same time the pilot unit stack current efficiency was somewhat
higher than that for the lab unit (0.81 in pilot vs. 0.65 in the lab).
This can be rearranged to give:
Because of sizing the number of cell pairs by fixing the linear flow rate
  through each cell pair (5.8 cm/s), this will be dictated primarily by the
YTOT −YRO;base ⋅ðUCbrine + UP Þ
UCED ≤ ð10Þ total amount of volume to be treated, so it will be sensitive to the RO
YED recovery. Also, the RO concentrate flow rate will directly affect the size of
328 Y. Oren et al. / Desalination 261 (2010) 321–330

the settler and UF unit as these will be proportional to a fraction of the aiming at increasing the process recovery toN 98% and decreasing the
diluate flow rate. For sizing the crystallizer and UF sections, it is assumed, disposed concentrate volume to minimum that is, to near complete
based on the findings in the pilot experiments, that two complete units dryness. For achieving that, further concentration of the BWRO brine with
(one for each of the first two EDR stacks in series) are needed, each sized EDR and WAIV is proposed. In order to protect the EDR from precipitation
for the concentrate flow rate (equal to diluate flow rate) in order to of sparingly soluble components such as CaSO4 and BaSO4 , a chain of
remove excess scaling ions that will only significantly transfer in the first treatments including a seeding crystallizer and settler were investigated.
two stages of the EDR. In addition UF filtration aimed at replacing the settler was studied as well.
Given these assumptions, we obtain the sizing and overall It is clear that possible silica deposition within the BWRO and the EDR
operating conditions for the EDR section as a function of RO recovery systems may pose a serious drawback upon increasing the BWRO
for a unit treating the concentrate from an original well water feed of recovery to more than 75%. However, cost analysis taking into account all
100 m3/h and overall process recovery of 98% (See Table 4-A). Note the components in the process clearly show that increasing the BWRO
that total chloride (and total anions) must be removed from the recovery ratio from 75 to 88% is not necessarily associated with a
highest RO recovery brine because the volume fraction of diluate significant reduction of the final product cost. Accordingly, it is to be
blended with RO permeate is the smallest. concluded that for keeping a smooth operation, the BWRO recovery ratio
When these options are cost out according to the cost assumptions should be limited when the EDR residence time of BWRO concentrate is
of Tables 1-A and 2-A and the design parameters of Table 4-A, we can not kept to a suitably short period of time. This will come at the price of
calculate the annualized costs for treating the RO brine by ED with an requiring a higher extent of salt removal in the EDR step.
attached crystallizer and UF separation unit (see Table 5-A). We can In this work part of the flow from the crystallizer/settler was fed to
see that there is a slight advantage to operating the EDR on the RO the UF crystallizer. In this sense, the latter was just partially
concentrate after 88% recovery in the RO step over the other cases. The challenged as a means of relieving EDR brine supersaturation and
88% recovery case is $40,000/year less expensive than the 75% RO keeping it free of crystallites that could otherwise precipitate within
recovery case. In addition to the smaller amount of anion that must be the EDR and the piping. However, results from this work show that it
removed at 88% recovery, the cost of acidifying the RO brine fed to the is worthwhile to go along with this part of the study and to further test
EDR stack is smaller because of the smaller volumes involved and the the UF crystallizer as an optional replacement for the settler.
overall lower amount of bicarbonate that must be neutralized to Finally, it is to be emphasized that even though the present study was
prevent calcium carbonate precipitation in the EDR stack. done on a specific brackish water source, its implications are general in
Table 2 presents the unit treatment costs for the RO/EDR hybrid the sense that it brings forward the various problems that have to be
process with 98% total RO recovery for a plant with a feed of 100 m3/h. encountered in achieving near ZLD with inland brackish installations.
By calculating unit costs for total product produced by the RO/EDR Moreover, this works provides some important quantitative methods
hybrid process we can see that the overall product water costs are for assessing problems, such as precipitation within the EDR stack once
clearly less than the base case (0.491 €/m3) for all BWRO recoveries. they occur. In addition, the cost calculations conducted in this work
These unit costs are also significantly less than the costs for seawater provide the sensitivity analysis of the final product cost to some
desalination in the most advanced plants presently in operation. In important system variables and can be apply to brackish water from
addition all the costs are significantly less than the present water tariff different locations provided that the necessary information is available.
for fresh water in Israel — 3.5 NIS/m3 (0.73 €/m3)[22]. Note that this
does not include the costs of transporting the water to the user. The Nomenclature
difference between the present water tariff and the product water A Membrane area for current flow in EDR [m2]
costs is the amount that can be allocated for transporting from the site ΔCD Concentration change in the EDR diluate compartments
of the high recovery desalination unit to the user. [eq/m3)
Cdsp Chloride concentration in brine sent for disposal (e.g. via
evaporation ponds or WAIV) [eq/m3]
5. Conclusions
Ctarget Target level of chloride ion concentration in final product
(set at 200 mg/L for the present calculations)
This work summarizes the long term studies made on BWRO ̅ Specific EDR power consumption [kW-h/m3]
E EDR
desalination of raw brackish water from the Negev Highlands, Israel
F Faraday number [coulombs/eq]
Itotal Total current [Ampere]
Table 2
Unit Treatment costs for RO/EDR hybrid with 98% total recovery for a 100 m3/h plant
l Geometric gap between each two membranes in the diluate
(feed flow rate). and brine compartments [m]
leff Effective gap between membranes [m]
RO step recovery RO Processing Costs 75% 83% 88% Unit
Ncp Number of cell pairs in EDR stack
Feed and pretreatment 124,484 124,484 124,484 € QD EDR diluate flow rate [m sec−1]
(at 0.16 €/m3 feed at 100 m3/h
Rstack Resistance of EDR stack [Ω]
for all cases)@
RO Power and capital 76,869 85,068 90,193 € R0stack Stack resistance at high concentrations.[Ω]
(0.13 €/m3 product) Relectrodes Resistance of electrode compartments [Ω]
RO permeate 591,300 654,372 693,792 m3/y RCM Resistance of cation exchange membranes [Ω]
Annual RO cost 201,353 209,553 214,677 €/yr RAM Resistance of anion exchange membranes [Ω]
Total EDR costs* 140,418 115,763 99,689 €/yr
RR Recycle rate (Diluate recycle pumping rate through stack/
Total RO/EDR Costs 319,999 308,441 298,857 €/yr
Brine disposal# 16,556 16,556 16,556 €/yr Diluate production rate)
Total Costs 336,555 324,998 315,413 €/yr Rcp Cell pair resistance (Ω)
Sp. RO costs 0.341 0.320 0.309 €/m3 ΔPst Pressure drop along EDR stack [bar]
(feed, power, capital)
Vtotal Total voltage applied to EDR [Volt]
Total product costs 0.436 0.421 0.408 €/m3
Base Case costs 0.491 0.491 0.491 €/m3 V Volume [m3]
Israel Water Tariff 0.730 0.730 0.730 €/m3 Vdsp Volume of brine sent for disposal (e.g. via evaporation
*) From Table 5-A.
ponds or WAIV) [m3]
#) Taken from Table 4 in [18]. UC Unit water costs [€/m3]
@) From Table 1-A. UP Value of the additional product water
Y. Oren et al. / Desalination 261 (2010) 321–330 329

WCTOT Total water cost [€/m3] Table 3-A


Y Product water volume relative the feed volume Performance assumptions based on EDR piloting at BGU.

ED Section
Greek Performance assumptions Figures
γ ̅B Specific resistances of the brine compartments (logarithmic −
Δ [Cl ]/Δ [Total anions] (%) 66.7
average) [Ω cm] Diluate Resistance of cell pair (Ω-cm2) 0.188 × 103/(1.6 + [Cl−]lm)
γ ̅D Specific resistances of the diluate compartments (logarith- Balance of stack resistance per cell pair (Ω-cm2) 9.2
mic average) [Ω cm] Current efficiency (%) 81.0
Current density (A/m2 cell pair) ∼ 200
ξ Shielding factor
P drop in ED stack/pass (bar/pass at 25 L/min) 0.8
ηEDR Coulombic efficiency of EDR stack Recycle ratio of diluate (Qrecycle/Qdil) 1
ηpump Pump efficiency (pump energy / motor energy) Electrode voltage drop (Volts) 8
Δ Difference Recovery of Diluate (Qdil/QRO conc) (%) 92.5

Abbreviations
cp Cell pair Table 4-A
dsp disposal Sizing of EDR unit to treat RO brine to reach 98% overall recovery with blended product
target Target chloride concentration in EDR diluate of 200 mg/L of chloride (Full-scale ED with 0.5 m2 cells).

tot Total RO step recovery Item 75% 83% 88%


EDR Electrodialysis reversal Total anion removal rate = Qd × Δ 4079 3832 3658
TMP Trans membrane pressure (Total anion conc.) (eq/h)
RO/BWRO Reverse Osmosis / Brackish water Reverse Osmosis Qd, (m3/h) 25 17 12
VCF Volume concentration factor (Rd)cp ave, (Ω-cm2) 22.4 16.8 12.6
(Rst)cp ave, (Ω-cm2) 9.2 9.2 9.2
UF Ultrafiltration i, (A/m2) 193 181 202
WAIV Wind Aided Intensified eVaporation cell pairs/stack 350 350 300
ZLD Zero liquid discharge Vstack,( V) 221 173 140
stacks in series 4 4 4
Total cell pair area (m2) 756 756 648
I, (A) 96 91 101
Acknowledgments Power consumption (kW) 85.4 62.6 56.4
Power consumption per unit product volume 3.71 4.17 5.64
This research was conducted under the framework of a BMBF-MOS (kWh/m3)
project grant WT 0504, “Near-ZLD Strategy for Optimal Management of
Inland Brackish Water Desalination”. The authors are indebted to the Fella
and David Shapell and the Blaustein Foundations for supporting this work. Table 5-A
Total capital and operational expenditures for treatment of RO brine with ED/
Crystallizer/UF. Assumes 90% plant availability and 100 m3/h feed to RO section.

RO step recovery Item 75% 83% 88%


Appendix A. Cost assessments
Capital costs (in €)
EDR (total membrane area × 842)* 636,552 636,552 545,616
Crystallizer* 165,600 108,000 72,000
UF* 44,160 28,800 19,200
Table 1-A TOTAL CAPITAL COSTS 846,312 773,352 636,816
Specific capital costs assumed in calculating cost of desalinating brackish water with
EDR combination. Annual costs (in €/yr)
3 2
EDR + Cryst. + UF Annual capital cost# 67,705 61,868 50,945
Step €/m stream/d €/m Basis for costs
Annual stack power 48,460 35,532 32,043
Pretreatment 100 [19] Pump power costs 2481 1489 1191
RO * 321 192 [20] Acid costs 21,772 16,874 15,510
ED 842 Quotations for Asahi stacks Total EDR + Cryst. + UF Annual Costs 140,418 115,763 99,689
UF 40 [21]
*) Based on data from Table 1-A.
Crystallizer/ 150 Quoted costs of pilot unit, with scaleup
#) Based on 8% annual capital recovery factor.
settler exponent of 0.7

* assuming 25 L/m2-h average flux.

References
[1] Yuan Zhoua, S.J. Richard, Tolb, “Evaluating the costs of desalination and water
Table 2-A transport” Working Paper FNU-41, Research Unit Sustainability and Global
Economic assumptions assumed in calculating the cost of treating water. Change Centre for Marine and Climate Research, Hamburg University, Hamburg,
2004.
Economic assumptions Value Unit [2] M. Mickley, Environmental Considerations for the Disposal of Desalination
Concentrates, Proceedings, 1995 International Desalination Association Confer-
Electricity costs 0.072 (€/kWh) ence, Nov. 1995, Abu Dhabi.
Annual capital charge rate 8.00 % [3] M. Mickley, R. Hamilton, Survey of membrane drinking water plant disposal
RO feed pumping and pretreat 0.14 €/m3 feed methods, Desalination 102 (1995) 93.
RO production costs (power and capital) 0.131 €/m3 product [4] M. Mickley, Membrane Concentrate Disposal: Practices and Regulations, USBR
Brine removal costs (by evaporation ponds) 1.40 €/m3 brine report #69, September, 2001.
Brine removal costs (by WAIV) 1.05 €/m3 brine [5] P. Glueckstern, M. Priel, Desalination 108 (1996) 19.
Online factor* 0.9 [6] B. Van der Bruggen, L. Lejon, C. Vandecasteele, Reuse, Treatment and discharge of
the concentrate of pressure-driven membrane processes, Env. Sci. Technol.
⁎) An online factor is the percentage of calendar year that the plant is actually operating. (2003) 3733.
This is always less than 1 because of downtime for maintenance, holidays, etc. The [7] David Bowlin, Case studies: zero liquid discharge systems at three gas-fired power
values usually run between 0.9 and 0.95 for most plants. plants, Am. Soc. Mech. Eng., IGTI v 7 (1992) 443–447.
330 Y. Oren et al. / Desalination 261 (2010) 321–330

[8] Brian E. Heimbigner, Zero liquid discharge control in United States coalfired steam [16] E. Korngold, L. Aronov, N. Belayev, K. Kock, Electrodialysis with brine solutions
electric stations, Water Science and Technology v 15 (1982) 101–118. oversaturated with calcium sulfate, Desalination 172 (1) (2005) 63–75.
[9] R.E. Dascher, R. Lopper, Meeting water-recycle requirements at a western zero- [17] E. Korngold, L. Aronov, N. Daltrophe, Electrodialysis of brine solutions discharged
discharge plant, Power Pollution Control, vol. 121, Aug 1977, pp. 23–28. from an RO plant, Desalination 242 (1–3) (2009) 215–227.
[10] R. Rautenbach, J. Gebel, Desalination v. 76 (1989) 107. [18] L. Katzir, Y. Volkmann, N. Daltrophe, E. Korngold, R. Messalem, Y. Oren, J. Gilron,
[11] T. Pankrantz, K. Johanson, Hybrid zero liquid discharge treatment system, WAIV — Wind Aided Intensified eVaporation for brine volume reduction and
American Society of Mechanical Engineers, International Gas Turbine Institute generating mineral byproducts, Desalination and Water Treatment 13 (1-3)
(Publication) IGTI, v 7, 1992, pp. 455–461. (2010) 63–73.
[12] Anita Seigworth, Rodi Ludlum, Eugene Reahl, Case study: integrating membrane [19] S. Adham, Development of a Model for Brackish and Reclaimed Membrane
processes with evaporation to achieve economical zero liquid discharge at the Desalination Costs, Proceedings of International Conference on Desalination
Doswell Combined Cycle Facility, Desalination v. 102 (1995) 81–86. Costing, Published by Middle East Desalination Research Center, Limassol, Cyprus,
[13] R. Rautenbach, R. Habbe, Seeded technique for “zero-discharge” processes, 6–8 Dec. 2004.
adaptation to electrodialysis, Desalination 84 (1991) 153. [20] P. Glueckstern (private communication).
[14] R. Rautenbach, W. Kopp, C. Herion, Desalination 72 (1989) 339. [21] R. Messalem (private communication).
[15] 15. “Wind Aided Intensified Evaporation”, PCT-W00075078-A1, 2003. [22] Global Water Intelligence, 19 November 2009.
Update
Desalination
Volume 266, Issue 1–3, 31 January 2011, Page 291

DOI: https://doi.org/10.1016/j.desal.2010.09.019
Desalination 266 (2011) 291

Contents lists available at ScienceDirect

Desalination
j o u r n a l h o m e p a g e : w w w. e l s ev i e r. c o m / l o c a t e / d e s a l

Corrigendum

Corrigendum to “Pilot studies on high recovery BWRO-EDR


fornear zero liquid discharge approach”
[Desalination 261 (2010) 321–330]
Y. Oren ⁎
Ben-Gurion University of the Negev Zuckerberg Institute for Water Research Department for Desalination and Water Treatment P.O. Box 653, 84105 Beer-Sheva, Israel

In this article Fig. 7 and its legend should be replaced by the following:

120
NaCl in tap water
Cell-pair resistance (ohm x cm2)

100 Exp. 4 (0.45m2)


Exp. 35 (5m2)
Exp. 62 (5m2)
80 Exp. 79 (5m2)

60

40

20

0
0 2 4 6 8 10 12 14 16 18
EDR diluate conductivity (mS x cm-1)

Fig. 7. Electrical resistance per cell pair vs EDR diluate conductivity with RO brine and NaCl solution (5289 ppm Cl− in tap water) as feeds.

Accordingly, the discussion in page 325 related to this figure should be replaced by the following one:
“The change of cell pair resistance of the EDR stack with diluate compartment conductivity for the different experiments is shown in Fig. 7.
As expected, the resistance of each cell pair and, consequently, of the whole stack decreases as the diluate conductivity increases.”

DOI of original article: 10.1016/j.desal.2010.06.010.


⁎ Tel.: +972 52 5793088.
E-mail address: yoramo@bgu.ac.il.

0011-9164/$ – see front matter © 2010 Elsevier B.V. All rights reserved.
doi:10.1016/j.desal.2010.09.019

You might also like