Status of Elevetor Units

Building Unit Current Progress Ongoing Work Planed Pending Work Remark
PL 1.1 Scaffolding erection work on going. Sub contractor will be mobilized once scaffolding Waiting for Entrance and cabin Materials and Cabin and Entrance approval pending. HKN has to advice regarding entrance finishing. Hoistway lighting is pending
PL 1.2 erection is completed. Work possible only upto without
entrance and cabine
PL 1.3 -
PL 1.4
PL 1.5
1
PL 1.6
Complted upto Roping - - Waiting for Entrance and cabin Materials. Cabin and Entrance approval pending
PL 1.7
PL 1.8 - Shaft Inspection Report is being prepared for due rectification and submitted Subcontractor available Cabin and entrance material delay (Cabin material visually approved but drawings and MSB have to be approved). HKN has to advice regarding entrance finishing
SL 1.1 Scaffolding erection work from 1st of Nov 2021
- - Installation is possible without entrance. HKN has to advice regarding entrance finishing
SL 1.2 onwards, Subcontractor need to be finalized

PL 2.3
Completed upto Roping - U Angle (Waiting for Inverter Board) Waiting for Cabin and Entrance Materials. Sample materials submitted for visual approval
PL 2.4
PL 2.6
PL 2.7
PL 2.8
Entrance Installation. Hoistway Lighting - Hall call looping
PL 2.9
PL 2.10
PL 2.11
PL 2.12
Entrance completed without 4 floors - Hall call looping
PL 2.13 Waiting for Cabin and Entrance Materials. Sample material submitted for visual approval. HKN need to provide through holes to intall Hall lantern and call button back
PL 2.14 boxes in levels.
PL 2.15
Entrance Installation. Hoistway Lighting - Hall call looping
PL 2.16
PL 2.17
PL 2.18
PL 2.19
Entrance Installation Hoist way Lighting as per schedule Hoistway Wiring including T cable. Hall call looping
PL 2.20
PL 2.21
PL 2.24 Waiting for cabin materials. Sample material submitted for visual approval. HKN need to provide through holes to intall Hall lantern and call button back boxes in
Entrance Installation - Hoistway lighting
PL 2.25 levels.
2 PL 2.28 Entrance Installation - Hoistway Lighting
Need Chipping in level 24 and 29. Waiting for Cabin and Entrance Materials. Sample material submitted for visual approval. HKN need to provide through holes to
PL 2.32 intall Hall lantern and call button back boxes in levels.
Roping parcially completed Balance roping work, Entrance and Platform installation. Hoistway Lighting -
PL 2.33
PL 2.34 Roping Completed - Hoistway Lighting Waiting for Cabin and Entrance Materials. Sample material submitted for visual approval. HKN need to provide through holes to intall Hall lantern and call button back
PL 2.35 boxes in levels.
Entrance Installation. Hoistway Lighting - -
PL 2.36
SL 2.1
T&C Work Hoistway lighting as per schedule -
SL 2.2
SL 2.3 Cabin installation Hoistway lighting as per schedule Cabin door, Balance of Hoistway Wiring and onwards
SL 2.7 Cabin installation. Hoistway lighting Entrance Doors Installation -
SL 2.8 Roping Completed Balance chipping works. Hoistway lighting as per schedule -
SL 2.9 Entrance Installation Need to complete the balance work. Hoistway lighting as per schedule. -
Running Condition. Some parts removed for
FSL 2.1 urgent requirement of BD4, BD6 Hoistway Lighting as per Schedule Parts have to be fixed once those delived

FSL 2.2
FSL 2.3
FSL 2.4
FSL 2.5 Running Condition Hoistway Lighting as per Schedule -
FSL 2.6
FSL 2.7
FSL 2.8

PL 3.1
PL 3.2
Completed up to Roping - Hoistway Lighting Waiting for Cabin and Entrance Materials. Sample materials submitted for visual approval
PL 3.3
PL 3.4
FSL 3.1
3
FSL 3.2 Final T&C Work. Hoistway lighting. Running
-
FSL 3.3 condition
-
FSL 3.4
FSL 3.5
Final T&C Work and Running condition Hoistway Lighting
FSL 3.6
Status of Escalator Units

Building Unit Current Progress Ongoing Work Planed Pending Work Remark Cladding Status
ES 1.3 A/B Steps removing for truss cleaning Ongoing T&C work temporary stopped until machined expoused to rain water is being dried. Peole Subcontractor will be back to site for balance T&C once machine will be dried Approval need for special cladding. Claddind work pending
1 deployed for waterwork
cleaning
ES 1.4 A/B Final T&C work completed Planning cladding and sub contractor Cladding work is pending Default/Delivered

ES 2.1 A/B Final T&C work completed Default/Delivered


ES 2.2 Final T&C work completed Planning cladding work and sub contractor Cladding work is pending Default/Delivered
ES 2.3 A/B Final T&C work completed Default/Delivered
2
ES 2.4 A/B Final QC completed - - Cladding Sample has to be submitted for approval. Cladding work is pending
ES 2.6 A/B Final T&C work completed - - Cladding Sample has to be submitted for approval. Cladding work is pending
ES 2.7 A/B Final T&C work completed Planning cladding work and sub contractor - Cladding work is pending Default/Delivered

ES 3.1 A/B
Draft Lifting plan submitted to HKN. Hoisting and placing can be done but HKN has to get remedial actions for any possible damage due to
3 ES 3.2 A/B Balmond inspection for lifting gears Chipping has been requested from HKN Hoisting and Placing delay of constructing top roof after placing escalators. T&C and Cladding work pending. Cladding sapmle
ES 3.3 A/B completed has to be submitted by Abans for approval. Escalator lighting design has to confirm by HKN