Professional Documents
Culture Documents
WAPDA
(PLD 2000 SC 841)
A brief Case Study on the Future of Int’l Arbitration in
Pakistan
Introduction to Int’l Arbitration
International Commercial Arbitration has evolved to be one of the most exclusive ways of
dispute settlement outside of realm of national courts. The corporate interests like its
efficiency as there is far better possibility of achieving a relatively economical solution and
provides finality through a quick and less formal procedure. The parties are able to maintain
confidentiality which is important especially when they wish to protect their trade secrets
and commercial interests. These factors are essential when dealing with cross border
transactions involving foreign investment where neutrality in terms of venue, the law and the
arbitrators are considered prime by the parties in settling their disputes. The neutrality ensures
that the arbitral tribunal deciding the matter at hand is detached from any direct national
influence therefore giving loyalty primarily to the parties. Thus such mechanism provides a
level playing field for both parties involved.
Following are the notable Institutions working for International Arbitration.
• ICSID (International Centre for Settlement of Investment Dispute)
• UNCITRAL (United Nations Commission on International Trade Law)
• ICC (International Chamber of Commerce) Rules
Bench of Hon’ble Judges of Supreme Court of Pakistan
It was agreed that all the disputes arising between the parties were to be brought before the Int’l Arbitration Courts i.e., ICC or ICSID or
the matters arising to be solved according to the Laws of England.
• The original agreement cost of the plant was $1,275 million which was subsequently raised by HUBCO to more than $1500 million.
• In the original agreement the debt-equity ratio was fixed as 80-20 per cent which was changed as 75-25pc.
• The payment of IRR on the equity amount was allowed retrospectively from Nov 17, 1993, by providing that the actual amount shall be
deemed to have been injected on the said date though the same was allegedly injected later on.
• The amount of CPP and rates of tariff had been allegedly unreasonably raised without any plausible reasons.
• Prolonged negotiations between HUBCO and WAPDA had taken place as WAPDA had been resisting and opposing the demands of
HUBCO.
• After the installation of new government in October 1993, the disputed documents were executed.
• No steps were taken to get this schedule regularized by HUBCO by insisting that the same should be got signed by some authorized
person.
• Schedule 1(A), 1(B) and 1(C) which were placed in place of the previous schedule containing rates of tariff etc., were not signed by
WAPDA .
• According to the original arrangement between the parties, at the expiry of the contract period, the ownership of the plant was to vest in
the WAPDA whereas, subsequently, it was decided that the same would vest in Hubco, prima facie, without any consideration or benefit
to WAPDA.
Main Issues in the Case
• Whether the Doctrine of Separability is applicable to the
Arbitration Agreements where corruption, and illegality is
involved ?
VERSUS
• Suggested that the award favorable to one party or another shall obviously be brought to
Pakistan for execution .
• It would be then challengeable in case any party choose to on any grounds of validity.
• In view of the complicated nature of the case, parties were left to bear their own costs.
Decision in the Appeals
Majority View
Sh. Ijaz Nisar,
Munir A. Sheikh,
• Restrained HUBCO from invoking the arbitration clause of the agreement proceeding with
arbitration in ICC Arbitration Case No. 10045/OLG
• Held that the supplemental deed, the first amendment and the second amendment to
the PPA were not arbitrable and should be decided by a court of law.
Brief grounds for Majority Decision
• The original agreement cost of the plant was $1,275 million which was raised by HUBCO to more than $1500 million.
• In the original agreement the debt-equity ratio was fixed as 80-20 per cent which was changed as 75-25pc which gave undue
advantage to HUBCO.
• The payment of IRR on the equity amount was allowed retrospectively from Nov 17, 1993, by providing that the actual
amount shall be deemed to have been injected on the said date though the same was allegedly injected later on, burdening
WAPDA.
• The amount of CPP and rates of tariff had been allegedly unreasonably raised without any plausible reasons.
• Prolonged negotiations between HUBCO and WAPDA had taken place as WAPDA had been resisting and opposing the
demands of HUBCO.
• After the installation of new government in October 1993, the disputed documents were executed.
• Allegations of corruption were disclosed in the FIRs lodged by WAPDA.
• The supplemental deed reference has been made to new schedule 6.
• No steps were taken to get this schedule regularized by HUBCO by insisting that the same should be got signed by some
authorized person.
• Schedule 1(A), 1(B) and 1(C) which were placed in place of the previous schedule containing rates of tariff etc., were not
signed by WAPDA .
• According to the original arrangement between the parties, at the expiry of the contract period, the ownership of the plant was
to vest in the WAPDA whereas, subsequently, it was decided that the same would vest in Hubco, prima facie, without any
consideration or benefit to WAPDA.
• According to the original agreement and its schedule 6, such matters were to be referred to Expert, in case of difference of
opinion, whose decision was to be final and such matters were kept beyond the pale of the arbitration clause.
• "These circumstances prima facie do establish the case of misuse of power by public functionary for extraneous
considerations requiring detailed examination and decision by a court of law after full-fledged trial.“
Relevant Laws Discussed
• The Law and Practice of International Abitration , 3rd ed. 1999, pp.5-33 to 5-36
• ICSID Rules
Book:
• PLD 1990 SC 48
While more recently it has been accepted that arbitral tribunals can resolve
claims of corruption, bribery and related illegality mainly due to the
doctrine of separability presumption. There have many cases to this date
that explain this point e.g.,
For free flowing capital investment, the foreign investor needs to have faith in the
Pakistan legal system which is clearly not the case as discussed. The above
discussed decisions highlight one main important point and that is simply the fear
amongst the investors that the arbitration agreements will not be respected.
Thus the reality is that their capital will flow elsewhere to a much safer neutral
destination where courts are not using a suffocated approach towards
international commercial arbitration.
It’s Never too Late!
• To enhance Pakistan image in the global arbitration arena serious steps need to be
taken to overcome the wrong precedents set.
• The Pakistani courts need to redefine the approach of its courts to international
arbitration. There is a need for the reform of law especially in the field of arbitrable
disputes. A criteria needs to be set that specifically defines the stage at which the
courts could interfere in determining matters of public policy.
• Most importantly there is a need of changing judicial mindset towards the arbitral
process.