We are the student of Pabna University of Science and Technology ,
Department of Geography and Environment, session ( ) have made a total station field survey at the independent square of PUST on 10-02- 2020 We have used theodolite and a prism for the survey. The process is conducted by the wave movement analysis. The theodolite gives the reading of the distance and different angles at the different points.
Area Calculation of Total Area Measurement:
We placed the total station instruments at three different points –A, B,
C and got three different distances and angels. The theodolite machine gives us the reading of different points through the reflection of light from Theodolite to the prism. Integrating the 3points A, B, C. We have gotten the area calculation by the machine Total station area measurement calculation: Points-3 S.A. 129.978yd2 (Southern Areas) H.A. 129.977yd2 (Horizontal Areas)
Total Area calculation = A+B+C
Total calculation off any area = Horizontal distance of every point and vertical distance of every point.
Offset Distance:
We have also set up theodolite for getting the vertical distance at a
point of the Administration Building, PUST.
Measurement: V.A. 0o19’53” H.A. 0o18’58” Offset/Distance: S 45.82ft. ZA 270o39’00” HA 56o51’5”