Grouping of MEP Fixes:

1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals


(Column/Slab)

2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling
i) Fixing supports, installation of Firefighting, Chilled Water piping,
drainage pipes, water supply(hot & cold), rain water, cable ladders, G.I
Conduiting, AC ducting
ii) Pressure tests and insulations
iii) Installation of FCUs, water heaters
(Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd
Fix)

3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People


i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures,
fire stopping and identification works etc.
(Note: False Ceiling people will close ceiling tiles and MEP people will
connect their diffusers in position on the ceiling tiles - too much
coordination is required at this stage)

MEP 2nd Fix: Other Areas


Installation of all equipments like AHUs(Floor mounted), all pumps, heat
exchangers(if any), bus bars, generators, water tanks etc.,

4. MEP Final Fix


Installation of Air terminals, sprinkler heads, wiring accessories, low
current devices, CCTV, Public Address System (PAS), Isolators, fire fighting
equipments(Hydrants), Sanitaryware, DBs, SMDBs & Dressing, SMA TVs,
Structured Cabling, All Switch Points

External and other MEP works


i) Connections to Main lines of Govt. Authority, water supply and
drainage.
ii) LV Room installations (MDBs, SMDBs, DBs)
iii) Installation of external piping, Manhole construction
iv) Installation of lightning protection, Backup System, Intercom System
etc.,

MEP First fix


Plumbing & drainage - u/g drainage, fire-protection pipes & water supply.
HVAC-CHW pipe sleeves.
Electrical sleeves-Electrical sleeves & conduit in GF slab.
MEP First fix in columns & wall.
Plumbing & Drainage - Embedded water supply , drainage & fire protection.
HVAC-CHW Pipe sleeves.
Electrical works- Conduits, back boxes in columns & walls.
MEP 1st fix in blockwork - install conduits & back boxes in wall.
M & E 2nd fix
Plumbing & drainage - Isolation values.
Plumbing - cold & hot water supply.
Drainage - WC’s, WHB’s & Urinals etc.
HVAC Ducting & CHW pipe.
HVAC - HVAC values
HVAC - FCU, AHU valves.
Electrical works - Wiring for internal lights, small power, sockets.
Electrical works - Wire pulling to jn box’s & electrical DB’s
Electrical works - Installation of DB’s & MDP’s
Electrical works - DB dressing.
Electrical works - Cabling for fire alarm system.
Electrical works - Cable tray & trunking.
M & E final fix
Installation of sanitary wares.
Installation of lights, switches, sockets etc.
ELV outlets & equipmemt.
Installation of fire alarm devices & fire alarm panel & repeater panel.
Installation of fire hose reel cabinet.
Installation of split unit AC’s