RATIO CEMENT SAND COURSE Ag

Sr.No Description Quantities Units


C : S : C.A bags cft cft
1 EXCAVATION 12,175.092 CFT : :
2 BACK FILL 1830.471 CFT : : 1830.471
3 P.C.C 400.29 CFT 1: 4: 8 38 189.67 379.35
4 R.C.C 9827.095 CFT 1: 2: 4 1729.5 4323.92 8647.84
5 BRICK WORK 5383.215 CFT 1: 6: 184.52 1357.44
6 PLASTER 28440.339 SFT 1: 4: 240.79 1203.97
7 TILES 5527.502 SFT : :
8 SKIRTING 1425.299 RFT : :
9 EXTERNAL PAINT / WEATHER SHEET
7465.704 SFT : :
10 INTERNAL PAINT / DISTAMPER
19408.726 SFT : :
11 WOOD WORK 453.25 SFT : :
12 ALUMINIUM WORK 606.44 SFT : :
BRICKS TILES SKIRTING PAINT wood workAluminium work
no sft rft sft sft sft

59634.16

5527.502
1425.299
7465.704
19408.73
453.25
606.44
Quantity Surveying And Estimation Assignment No 2

Rate per unit


S.No Description Quantity Unit
in (PKR) Amount

Group B rate analysis for excavation


Quantity Surveying And Estimation Assignment No 2

Rate per unit


S.No Description Quantity Unit
in (PKR) P.C

Group B rate analysis for P.C.C