Professional Documents
Culture Documents
DOCUMENT
Healthtown Project #83
March 2004
Introduction
These Owners’s Project Requirements (OPR) are meant to capture the most
important goals and objectives presented herein of this project from the Owner’s
perspective. This document has been issued at the start of the design development and
will be updated to reflect all significant changes at the 50% and 95% construction
document design submissions. The goals and objectives are specific to this site and
project, but draw upon many lessons learned from previous projects, and reflect not only
corporate objectives but also the goals the community in which the project is being
developed. The OPR cites specific performance and achievement criteria whenever this
criteria is known to reflect best current practice and minimum acceptable standards,
although many of specific baseline benchmarks are not cited herein in anticipation of
their development by the design team. In cases where specific criteria are not cited, the
This OPR is for a 12, 500 ft.2 pharmacy/convenience store to be built on the site
developed and the store is to be built and leased back to Healthtown Corporation by the
developer. The lease shall be five years with first right of refusal renewals to Healthtown
in 5 year increments.
• Background
• Contracts, budget, schedule
• Overarching goals
• Functional uses and program requirements
Background
The agreement between Healthtown and QualPro sets the upper limit of the costs
of site development and project construction costs, as well as the leaseback costs. The
leaseback costs have a range with actual costs to be set after the final cost of construction
is known.
otherwise existed, Healthtown and QualPro have structured a creative contract which
allows them to both benefit from lower up front construction costs as well as from
The agreement will reflect cost savings below the maximum rate by reducing the
leaseback. The cost saving share ratio is 35% to Healthtown and 65% to QualPro. This
allows the contractor to retain 65% share of any cost savings and the owner to see 35% of
the savings via a reduced lease over two five years terms. The developer is paid a
quarterly fee to maintain the site and building and incurs all energy and maintenance
allowance at a 65% share rate. This allows the contractor to retain 35% of the difference
between the O&M allowance and the actual O&M costs. There is a detailed scope of
work for the O&M contract. The developer must retain ownership of the building for a
QualPro was selected as the developer due to the ability to secure the site, local
community relations, and the willingness to accept Healthtown’s project contract terms.
The contracts between Healthtown and QualPro are for site development, shell
and core, and O&M. Healthtown has negotiated national agreements with a specified list
of equipment suppliers for specific materials. There are building protypical drawings and
on-line construction bulletins capturing lessons learned from previous projects. The
Overarching Goals
4. The project shall reflect the community needs of a “college town” such as
safe traffic/pedestrian patterns, considerations beyond ADA minimum
provisions, and sustainable design.
5. QualPro O&M staff and Healthtown staff must be jointly trained with
regard to O&M and the contractual relationship of the two parties.
6. Project Quality shall result in a building shell and core with a thirty year
life cycle.
Programming Requirements
Ft.2
• Pharmacy 1500
Healthtown and QualPro have a mutual interest in reducing first cost and
Healthtown is concerned with integration into the community as well as with safety and
aesthetics. Both have perceived costs. QualPro has the additional concern of longevity
for the building and its infrastructure because they will own this project. This is
different than most projects which QualPro constructs for others, but does not own.
However, increased first cost associated with higher quality products and systems works
After much research and discussion, Healthtown and QualPro agree on the following
• During construction all vehicles leaving the site will be safety inspected and
• During construction there shall be community impact and safety meetings twice
project team.
• The building envelope shall be designed for fifty years life, requiring CMU versus
• The envelope shall be designed and build with extra care with regard to water
• Exterior finish metals shall be chosen for minimal maintenance and maximum
longevity.
• All flashing design details shall receive a peer review. Healthtown is concerned
• The HVAC system serving the grocery/refrigerated case area will be selected
based upon a 50% relative humidity set point and shall be equipped with a
humidistat and reheat in order to ensure low humidity levels around refrigerated
display cases.
• All rooftop equipment shall be mid to high quality with an expected life of twenty
years.
• The local gas and electric utility shall be consulted relative to the availability of
high efficiency rebates. The guideline for deciding to participate shall be a 5 year
simple payback ROI based upon net costs after rebates and must include all
However, Healthtown will consider the use of alternative energy efficient fixtures
visited to review the lighting quality of the alternative. Exterior lighting shall be
• All equipment in the store shall be Energy Star rated if such a rating is available.
• The landscape design shall minimize lateral views of the store. Existing oak and
maple trees at the rear of the property shall be retained and protected during
construction.
• Designers shall specify low flow plumbing fixtures and shall design a roof drain
• Rooftop equipment shall not be visible from the street level of adjacent property
lines.
• A commissioning agent shall be hired and these costs will be split by Healthtown
and QualPro. This agent will be hired early in construction and will provide
• The designers, Healthtown, and QualPro will meet with the sustainability
committee of the college to review the project for additional project concepts.