Task 1: Create a Mind Map for a proposed solution to the Breakfast Cereal TV Advert scenario
Task 2: Create a Project Schedule for the three stage of the Breakfast Commercial
Remember the project will run for four weeks and you should include Contingencies and Milestones
Contingencies
Milestones
Task 3: Monday.com Gantt Chart
Production schedule
Apr-2021 May-2021
Start End 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
group - Pre-Production group - Pre-Production
Research(Research) 03-May-2021 04-May-2021 Research (03-May-21 - 04-May-21)
Concept(Concept) 04-May-2021 04-May-2021 Concept (04-May-21 - 04-May-21)
Storyboard(Storyboard) 05-May-2021 07-May-2021 Storyboard (05-May-21 - 07-May-21)
Script(Script) 07-May-2021 09-May-2021 Script (07-May-21 - 09-May-21)
Budget(Budget) 10-May-2021 11-May-2021 Budget (10-May-21 - 11-May-21)
Hire equipment and location(Hire equipment
11-May-2021
and location)
11-May-2021 Hire equipment and location (11-May-21 - 11-May-21)
Resources(Resources) 12-May-2021 13-May-2021 Resources (12-May-21 - 13-May-21)
Meeting(Meeting) 14-May-2021 14-May-2021 Meeting (14-May-21 - 14-May-21)
group - Production group - Production
Set up equipment(Set up equipment) 17-May-2021 17-May-2021 Set up equipment (17-May-21 - 17-May-21)
Film the advert(Film the advert) 18-May-2021 20-May-2021 Film the advert (18-May-21 - 20-May-21)
Record audio(Record audio) 18-May-2021 20-May-2021 Record audio (18-May-21 - 20-May-21)
Meeting(Meeting) 21-May-2021 21-May-2021 Meeting (21-May-21 - 21-May-21)
group - Post-Production group - Post-Production
Editing(Editing) 24-May-2021 25-May-2021 Editing (24-May-21 - 25-May-21)
Effects(Effects) 25-May-2021 25-May-2021 Effects (25-May-21 - 25-May-21)
Focus groups evaluation(Focus groups26-May-2021
evaluation) 26-May-2021 Focus groups evaluation (26-May-21 - 26-May-21)
Client evaluation(Client evaluation) 26-May-2021 26-May-2021 Client evaluation (26-May-21 - 26-May-21)
Adjustments(Adjustments) 27-May-2021 28-May-2021 Adjustments (27-May-21 - 28-May-21)
Distribution(Distribution) 29-May-2021 29-May-2021 Distribution (29-May-21 - 29-May-21)
Meeting(Meeting) 30-May-2021 30-May-2021 Meeting (30-May-21 - 30-May-21)