No.

: L45201RJ2003PLCO18049
HGIEL(4)

DATE: 01-09-2020
2020-21/DV PKG-8/01
REF NO. HGIEL/JPR/

Work Order
To,
Pathway Enterprises
D-23, Lower Ground Floor,
Sec-50, Noida (U.P.)

Thenua
Kind Attn.: Mr. Prashant Singh
9557585472
Contact No: +91-9719079555,
in section of Delhi-
carriageway from Km 214+260 to 245+310 (PKG-8)
Construction of Eight Lane in the state of
Project: under Bharatmala Pariyojna
Vadodara Greenfield alignment (NH-148N) on EPC mode
Rajasthan.
Culverts.
Construction of Pre-Cast Box
Sub: Work Order for
terms and conditions.
discussion and mutualy agreed rates,
Ref: As per your quotes, subsequent

Dear Sir, Work Order for


we are pleased to place
reference to your offer and subsequent discussions,
With as per enclosed drawings.
Culverts for our above said project,
construction of Pre-Cast Box

Item/Rate are as following:

UOM Quantity Rate Amount


S. Description of Items
No.
desired
and dressing up to the
Labor for Levelling 10442 39 4,07,238
beneath the proposed pre cast box Sqm
1 level before PCC

segment.
with needle/plate vibrator
Laying and Compacting culvert at the
excavated bed of the
PCC M-15 at the Cum 1157 210 2,42,970
for laying pre cast
2 desired level and alignment
shall be supplied by
segmentsi/c shuttering. (RMC
HGIEL free of cost).

Cer
For-PathwaFnterprises
akan

Page 1 of 10

H. G. INFRA ENGINEERING LTD.


C-cheme Tel.:+91 1414106040-41
Plaza, A-1, Tilak Marg.
www.hginfra.com Corp. Office : Floor, Sheel Mohar Fax:+91 141 4106044
Visit us at
Jaipur-302001 (Raj.) 2000307
Jodhpur-342001 (Raj.)Tel.:91291
Email info@hginfra.com
Regd. Office 14,Panchwati Colony,Ratanada, Fax:01291 251531
Rate Amount
. Description of Itemns UOM Quantity
No.
machine mixed and needle
Laying in position
vibrated design mix of M-30/35 for Precast
Concrete box segments, L
Reinforced Cement
slab of various sizes, but the weight
segments and
not exceed 11MT including
of each segment shall
shuttering, de-shuttering, 9190 1600 1,47,04,000
the cost of centering, Cum
direction of
3 complete as per
curing, finishing all
Rate are inclusive of labor,
Engineer in charge.
plants, etc. involve in above
curing, machinery, tool, and
in all respect. (RMC
tem description complete
by HGIEL free of
reinforcement shall be supplied

cost). reinforcement grade


of
Labor for Placing in position
for pre-cast box segment i/c
Fe-500 HYSD/TMT Bars
straightening, cutting, bending,
placing in position j
steel of binding wire all
and binding with mild Ton 886 6000 53,16,000
chairs and spacer
4 complete. The actual lap length,
as per the site
bars shall be paid separately
shall be supplied by
conditions, (Reinforcement
however the cost of binding wire
HGIEL free of cost,
is included).

and Launching of
Pre-cast
Stacking, Transportation
and slab from the casting
box segments, Lsegments
location (up to a lead of 20Km) i/c
yard to the site
of boxes by filling with
placing, fixing and joining suitable
bituminous mastic
sealant or any other
Pre-cast box segments
shall be
methodology. The
5 on the prepared bed of
transported/ placed
slope by using
structure in the proper alignment &
and c r a n e of suitable|
appropriate trailer/trucks
boom length and weight
carrying capacity for
to a
the pre-cast box segments
lowering and fixing
From the existing level.
depth of 5 Met.
and Precast L 1400 87,50,000
For Segment of 2mx2m
Precast Box Cum 6250
5a Slab for 3mx3m.
Segment and
Cum 2940 1500 44,10,000
and Slab for 4mx3m
5b For Precast L Segment

of RCC of any grade in cast-


Laying and Compacting
for stitching portion of L
in-situ with needle vibrator 2174 550 11,95,700
Cum
including shuttering,
6 Segments and top slab ofBox
de-shuttering, dressing, ramming, curing,
finishing
all complete as per direction of site Engineer

Ce For-PathwayEntefBA,
Pags
S.
Description of Items UOM Quantity Rate Amount
No.

Providing and fixing weep holes in RCC precast


boxes with 100mm dia. PVC Pipe, extended through
the full width of the box as per drawing and Rmt 4742 245 11,61,790o
direction of Engineer in charge of HGIEL.

Total Amount in Rupees (Excluding GST) 3,61,87,698

Following8 specific terms have been agreed upon,

A. sCOPE OF WORK

Design Chainage No Proposed TYpero


km) Span(m Culver
22 1x2x2
Km 214+260 - to 10 1x3x3
RCC BOX
km 235+000 3 1x4X3
3 1X5X3

Sub-Contractor'sScope:
1) The Scope of the work comprised Construction and Launching of Pre-Cast Box Culverts as per
Km
design& drawing (herein after referred to as "Subcontract Work") at Eight Lane from
214+260 to 292+950 (PKG 8 & 9) in section of Delhi-Vadodara Greenfield alignment (NH-148N) on
EPC mode under Bharatmala Pariyojna in the state of Rajasthan
Subcontract Work is Rs. 3.62 Crore as per details in
2) The approximate Subcontract Price for the
above. The Subcontract price is exclusive of GST and inclusive of IT, Duties, Royalty and other
statutory charges etc.
and submission of Layout for
3) Preparation of casting yard, including laying of PCC for bed yard
of

yard (Area is according to the quantity of work) to the HGIEL for approval.
4) Providing of Labour (with all Tools & Tackles) for Levelling and dressing of soil in the excavated
area (Excavation and compaction for Bed shall be done by HGIEL) before doing PCC beneath the
instructed by Site In-charge.
proposed Pre Cast Box segments as
of RMC M-10/15 at the excavated bed of the
5) Laying and compaction (with needle/plate vibrator)
Pre-Cast segments. Including the cost of
culvert at the desired level and alignment for laying
of concrete, Machinery, Tools &
labour, shuttering, Centering, De-shuttering, Finishing, curing
Tackles all complete
as specifications and drawings. (RMC shall be supplied by the HGIEL free
per
of cost).
Laying in position
6) Reinforced machine mixed and needle vibrated design mix of M-30/35 for Precast
Cement Concrete box segments, L segments and slab of various Sizes including the
cost of Labour, Shuttering, Centering, De-shuttering, Finishing Curing of concrete, Machinery,
Tools and Tackles all complete as per specifications and drawings. (RMC and reinforcement shall
be supplied by the HGIEL free of cost).
Fe-500 HYSD/TRbars for Pre-Cast Box
7) Labour for placing in position reinforcement of grade
placing inposition and
Segments. Including the cost of Labour for straightening, cutting, bendiny
technical spRcificatonsr as directed by Site In
binding with binding wire all complete as per
Páge 3 of 10
ForPathway Enterorises
charge. The actual lap length, chairs and spacer bars shall be non-payable and will be taken into
account only for reconciliation, (Reinforcement shall be supplied by the HGIEL free of cost, and
however the cost of binding wire is in Sub- contractor's scope).
8) Stacking. Transportation and launching of Pre-Cast Box Segments, L-Segments and slab from the
casting yard to the site location. Including the cost for placing, fixing and joining the boxes by
filling with bituminous mastic sealant or any other suitable methodology. The pre-cast box
segments shall be transported/ placed on the prepared bed of structure in the proper alignment,
slope by using appropriate trailer/trucks and crane of suitable boom length and weight carrying
capacity for lowering and fixing the pre-cast box segments to the desired depth all complete as
per technical specifications or as instructed by Site in charge. Lifting hook provided in the
segments during casting for erection purpose to be cut post completion of erection with
necessary tools and tackles at no extra cost and scrap reinforcement to be returned &
submitted to steel yard. The same will be taken into account during reconciliation of steel
9) Laying in position machine mixed and needle vibrated design mix of any grade for stitching
portion of L segments and Top slab of box. Including the cost of Labour, Shuttering, Centering
De-shuttering, Finishing, Curing of Concrete, Machinery, Tools and Tackles all complete as per
specifications and drawings. (RMC and reinforcement shall be supplied by the HGIEL free of cost).
10) Providing and fixing of 100mm dia. PVC pipe for Weep holes extended through the full width of
the RCC wall as per technical specifications or as directed by Eng. In Charge of HGIEL.
11) Providing of Vibrators, Electricity/diesel for vibrator, Shuttering oil, Nuts & Bolts, Binding wire
(annealed, conforming to IS 280), Sealant (for joining segments) including all consumables will be
in sub-contractor's scope.
12) Curing of structures shall be done by sub-contractor by using Water. Only water will be provided
by HGIEL free of cost at a single point, rest all arrangements for curing (Pump, Hessian cloth,
labour) shall be in Sub-contractor's scope.
13) GP-2 and cement will be given by HGIEL free of cost, rest all other works related to jointing are in
the scope of Sub-contractor.
14) Providing of Cranes, Trailers, Machineries and Labour for stacking of Segments, its transportation
to the site and installation all complete.
15) The quantities mentioned above is tentative & may vary based on actual site condition & revised
drawings, however the rate shall remain the same.

HGIEL'S Scope:
1) Excavation for the culvert and compaction of the bed (after levelling and dressing of soil done by
the sub-contractor) by Baby roller (if required) is in HGIEL's scope.
2) Providing of RMC of any grade as per requirement to the Casting Yard and Culvert location at free
of cost (arrangement for unloading and laying of RMC will be in sub-contractor's scope)
3) Providing of TMT for Pre-cast segments and for Cast in-situ structures at free of cost. But
arrangement for loading and unloading, shall be in sub-contractor's scope. Trailor for this will be
given by HGIEL free of cost.
4) Providing of electricity at a single point in casting yard.
5) Providing of water for Curing at a single point in casting yard and at site for qast in situ.
6) Backfilling around structures after installing of segments with Filter mepia including cost of
Labour, material and machinery all complete as per technical specifictians.
7) Concrete pump if required will be provided to Sub Contractor
labour gang needed for its operations, will be in sub-Contractors
y HGHEL free of cost however
scade.
C o

For-PathwayEnterpEses
eroPsge 4 of 10
B. GENERAL TERMS & CONDITIONS: satisfaction
Work is required to be carried out as per
relevant IRC/MORTH specifications with the
1)
of HGIEL. Contractor should work as
The approved Designand Drawing will be provided by HGIEL and Sub
2) not be tolerated. If any
and technical specification. Any deviation will
per the approved drawings
should be removed from the site at your Cost and risk.
work is rejected by HGIEL, the same
area surroundings will be in
sub-contractor scope. All internal roads
3) Housekeeping of casting
the
sub-contractor.
around casting yard will be maintained by
Bellies for labour hutment shall be in Sub-contractor's scope, however the
4) CGI sheet, Tents and labour huts, etc., shall be provided by HGIEL.
land for the establishment like casting yard,
inclusive of IT, Duties, Royalty and other
The Ratementioned in above is exclusive of GST and
5)
statutory charges etc.
sub-contractor in any case.
6) No extra Lead is payable to the care is to be
is in the scope of the sub-contractor. All
7) Planks packing needed in transportation
should not be broken.
be disturbed and edges of structures
taken so that dowels steel should not escalation shall be
mentioned in the above is firm and no deviation or variation or
8) The rate
reason what so ever it
contract under any circumstances for any
allowed during the tenure of this
may be. condition & revised
is tentative & may vary based on actual site
9) The quantities mentioned above
shall remain the same.
drawings, however the rate

CONDITION:
C. SPECIAL TERMS &
the HGIEL
submit work program in advance to
1) Sub-contractor has to Sub-contractor to the HGIEL
shall be submitted by
2) Stacking methodology Segments
of
RA bill. Optimum utilization of
Reconciliation of TMT will be
submitted by sub-contractor in each
3) take back TMT lesser
to minimum wastage. HGIEL will not
leading
TMT is to be done by vendor minimize the wastage
is to be done by sub-contractor to
than 3 meter. For this detailed working and chairs shall be maximum
scrap but excluding laps
of steel. Total allowable wastage including If any deficiency found in
and max.1% for unaccounted wastage).
of 3 % (max. 2% for scrap Market price of TMT + GST to
BBS prepared by HGIEL) then it will be charged
quantity (as per
the sub-contractor.
TMT stock yard to casting yard will
be in the scope of sub-contractor,
4) For Shifting of TMT from
will be given by HGIEL at free of
cost.
However the Trailor for this
submitted by sub-contractor in each RA bill. Allowable wastage of
Reconciliation of RMC will be
5) then it will be charged @ Rs
RMC is 2% of consumption.
If any deficiency found in quantity,
4000/Cum + GST to the sub-contractor.
assign/subcontract the work to anybody else except prior written
Subcontractor shall not further
6)
permission of HGIEL.
consumables and tools and tackles
Rates are inclusive of cost of labour, shuttering, machineries,
7)
etc. for transportation
Subcontractor shall adequate Capacity of Crane/s; Trailer/s
mobilize
8) & Tackles; Slings, D-shackles; Chain
Manpower; Tools
&Shifting/Erection; Skilled/Un-Skilled work.
etc. for carry out construction
Blocks, Ropes, Consumables, "HGIEL" on demand. During
shall be submitted with
9 Methodology of agency which
material shall be adopted to avoid any damage, if any
Transportation best method of securing
free of cost by sub-contractor.
damages shal be replaced
and construction \ovar thé site with proper
10) Subcontractor shall arrange loading, unloading
supports & with safety.
11) Any other vehicle operator
should be competent in the sd@pè öf work to be undertaken.

Page 5 of 10

FoPathway,E n t e r p n i s e s
"Subcontractor shall be submit required certificatlon & copy of valid license of operator.
issues relating to Work
at site and intimating agency for any urgent
12) Arranging for quality checks
Order labour and other additional resources as directed by
13) The Subcontractor shall mobilize adequate
Work within the stipulated period of time limit as per the
HGIEL to complete the Subcontracted
contract.
the allotted work will be arranged by Subcontractor.
14) All accessories/equipment to execute
Subcontractor will be of 3 months after completion of
15) Defect Liability Period on work executed by
HGIEL to Subcontractor. If the structure is
subcontracted work and Certification given by
case the guaranty will not be of
subcontractor.
damaged in accident or any theft in that

D. PROGRESS OF WORK:
shall put in all efforts to achieve
Time is the of the Subcontract Work and Subcontractor
essence
1) rate of progress is found
within the stipulated time period. If the
overall completion of the project at the risk
to get the work executed by other agencies
unsatisfactory, HGIEL reserves the right
and cost of Subcontractor and
months for Pre-cast Segment construction
2) The time for the completion ofwork is- 6
period i.e. from
at site from commencement
date of work
6months for installation of segments
acceptance of work
order.
of work order. Same will
Subcontractor will submit the
Work Program within 7 days from issuing
3)
basis.
be monitoring on monthly or schedule completion
date within
event that subcontractor fails to achieve work program
4) In the subcontractor to
forth in Clause No. D (2) of work order, it shall pay damages by
the period set recovered
certified work done (i.e. shall be
calculated at the rate of 1% of
the HGIEL of a sum the date
of subcontractor) for delay of each month reckoned from
from RA Bill/Retention money In
is achieved or works are completed.
D (2) and until such milestone
of specified in Clause No. terminate the sub-contract with
HGIEL holds to reserve right of
addition to the above said terms
under the term of Non satisfactory
performance against approved work
notice period of 15Days,
planning/program. of
appropriate written extension
In case of any delays
due to reasons attributable to "HGIEL"; such
5) cost payable in an
"HGIEL". There shall not be any additional
work order shall be granted by
event.

& PAYMENT TERMS:


E. MODE OF MEASUREMENT from approved drawing. The quantities
derived by measurement taken
1) For payment the quantity be approved for payment to
executed shall be measured as per
the MORT&H and the same must

HGIEL
2) Terms of Payment:
No advance payment.
the quantum of works completed,
the monthly basis accessing
Payment shall be made
on
of works and bills are certified by
final payment will only be made after the completion

Engineer in-charge.
first week of succeeding month
his monthly progress bills during
3) The Subcontractor shall submit in a format
for the works executed duly supported
by all quantity calculations and rification
of the HGIEL in respect of quantityexesited
and accepted in
approved by HGIEL. The decision accordance wih Bya. Payment will be made
bill is final and binding. The Payment shall be in
any
certification of RA Bill.
after 20 days from
submitted along with monthly progess piHs are hut ndt limited to)
4) The documents to be
for the executed work.
a) The records/approvals For-PathiwayEnterpiags
gs of 10
b) Quality approvals by HGIEL's Representative.
c)Material reconciliation statements if supplied by HGIEL
d) Any other documents as instructed by HGIEL.
The date on which all required supporting documents are submitted shall be considered as date
of submission of Interim bill.
5) The following deductions shall be made from each bill of the subcontractor before releasing
payments:
a) Recovery of an amount on account of materials supplied by HGIEL.
b) Tax Deduction at Source if any as per prevailing laws of State/Central Government at that
time.
c) Performance Bank Guarantee (PBG) of 5% of the contract value shall be submitted to HGIEL
within 15 Days of the issue of W0, otherwise additional 5% recovery will be made from each
unning bill until total PBG amount reaches to 5% of Contract value. The recovery on account
of performance guarantee can be replaced by submitting equivalent amount of BG at any
point of time.
d) Any other recovery on account of works executed/expenditure incurred by the HGIEL on
behalf of the subcontractor.
6) All arrangements for loading unloading of material received from store, stacking etc. are in your
scope. For transportation of TMT, Trailor shall be provided by HGIEL at free of cost.
7) Applicable Taxes will be deducted from each RA bills of Subcontractor.
8) Applicable GST is excluding in unit rate mentioned in above BOQ and will be Credited subjected
to foliowing conditions if Subcontractor liable to register under the GST Law:
Provide GST Registration Certificate as per 6ST Act 2017.
b) GST shall be paid extra as per prevailing GST rates. In case of any changes in prevailing GST
rates, the same shall be considered separately to the effect.
c)Tax Invoice (Rule 46)/Debit Note & Credit Note (Rule 53) to be issued as per GST Rules. Tax
Invoice/Debit Note/Credit Note must contain all the fields which are required to be
mentioned as per rules.
d) If Any Material/Services issued/Provided by HGIEL to Subcontractor, then HGIEL will raise the
Tax Invoice as per Rules and it should be duly accounted in Subcontractors books before
closure of respective tax periods.
e) Subcontractor is liable to upload details of outward supply made by him at GSTN Portal after
due confirmation of detail from HGIEL before closure of respective tax periods. If in any case
credit will not be shown at 6STN form 2A against our GSTN then Subcontractor is liable to
make the loss good (including towards interest and penalty if any) and it will be recovered
from the subsequent bill to be made.

F. STATUTORY APPROVALS, COMPLIANCES WITH LOCAL LAW, INDEMNITY & LIQUIDATED DAMAGES:
1) The Subcontractor shall comply with all applicable permits, licenses and approvals in accordance
with Applicable Laws in the performance of its obligations, duties, responsibilities or liabilities
under this Work Order. Subcontractor is also required to comply with all prevailing statutory
provisions, enforces in respect of all employees/labours on the Project such as Minimum Wages
ACt, ESI ACt, Payment of wages Act, EPF Act, Employees compensation Act, Contract labour
(regulation and abolition) Act, Payment of bonus Act, Equal remuneration Act, Maternity benefit
Act, etc. Further the subcontractor agrees to comply air, water, environmet laws and laws
relating to disposal/storing of hazardous waste. Subcontractor also agrees,td submit PF, ESI
challan and payment proof thereof in each month to HGIEL. In tha eveaof any failure of the
Subcontractor as regards any of the statutory or legal cgmpliancekthe ubcontractor shal
indemnify and hold HGIEL harmless against and from the conxapebës dany stch failure
Page 7 of 10
ForFathwayEnterDnses
e
2) Subcontractor confirms that in case of any breach and/or failure and/or negligernce on its partin
executed allotted work, HGIEL reserves the right to take over the pending/balance work and to
carry out the same by any other agency at the risk, cost and consequences of the Subcontractor.
3) The Subcontractor shall indemnify and keep indemnified HGIEL against all losses and claims for
injuries or damages to any persons or any property what-so-ever it may arise out of or
inconsequence of the construction and maintenance of the works and against all claims demands
proceedings damaged cost charges and expenses what so ever in respect ofin relation thereto.
4) In case the Subcontractor fails to make payment either to its suppliers, labours or to any other
persons, agencies firms etc. who have done work or supplied material, services etc. to
Subcontractor for the Project, HGIEL shall have right to make payment directly to such persons,
agencies, firm etc. after verifying the amount payable and same will be recovered from the
amount payable to the Subcontractor.
5) t is agreed and understood that, as between the HGIEL and the Subcontractor, the legal
relationship is strictly on a principal to principal basis. Nothing is deemed to constitute or imply
any other legal relationship such as principal-agent, master-servant or otherwise. It is expressly
agreed that there shall be no principal-agent, master-servant or any other relationship between
the HGIEL and the Subcontractor under this Work Order and no representation toanysuch effect
would be made by the Subcontractor to anyone. The Subcontractor shall indemnify HGIEL against
any claims, expenses, liabilities and losses and for any third party claims regarding and/or arising
under or in connection with the relationship and/or misrepresentation thereby by the

Subcontractor.
execution of Works, the Subcontractor its costs, keep the site
shall, at
6) At all times during the
of materials at site in
reasonably free from all unnecessary obstruction and shall arrange storage
of works and
orderly manner or dispose of any unwanted materials. On substantial completion
the Subcontractor shall, at its costs, clear
upon completion of works or earlier determination,
debris etc. and leave the whole of the
away and remove from site all surplus materials, rubbish,
site and works clean to the complete satisfaction of HGIEL. If the Subcontractor fails to remove
the surplus materials, rubbish, debris etc. HGIEL shall engage additional manpower to clean the
same and the amount so incurred shal, without prejudice to any other method of recovery, be
deducted by HGIEL from any amount due or which may become due to the Subcontractor or shal
be recovered as a debt.
7) All matters related to this Work Order, the Works and all other documents shall be regarded by
the Subcontractor as being highly confidential and shall not be disclosed to any party, person or

entity. The Subcontractor shall at time hereinafter use any technical information or
no
intellectual property, in relation to this Subcontract and the Main Contract. The Subcontractor
shall not have the right to advertise or otherwise permit the dissemination of publicity
concerning this Subcontract. This Confidentiality obligation shall survive 3 years after expiry or
termination of this Work Order.

8) The Subcontractor represents, warrants and confirms to HGIEL that:


a) it is duly organized and validly existing under the Laws of India and has full power and
authority to execute and perform its obligations under this Work Order and to carry out the
transactions contemplated hereby;
b) it has taken all necessary corporate and other action under the Applicable Laws and its
constitutional documents to authorize the execution, delivery and peormance of this Work
citOrder
has the financial standing and capacity to undertake the executienf Works subcontracted
to it under this Work Order;
d) There are no actions, suits, proceedings, or investigatipns pegnkg or, to the Subcontractor
knowledge, threatened against it under the Applicable or in auitybéfore any court or
For-PathwaEnterprises
oage 8 of 10
before any other judicial, quasi-judicial or other authority, the outcome of which may result
in the breach of or constitute a default of the Subcontractor under this Work Order or which
may result in any material impairment of its ability to perform any of its obligations, duties,
responsibilities or liabilities under this Work Order;
e) It has no knowledge of any violation or default with respect to any order, writ, injunction or
decree of any court or any legally binding order of any Government or Government
Instrumentalities which may result in any material adverse effect on its ability to perform its
obligations, duties, responsibilities or liabilities under this Work Order and no fact or
circumstance exists which may give rise to such proceedings that would adversely affect the
performance of its obligations, duties, responsibilities or liabilities under this Work Order;
) It has complied with the Applicable Laws in all material respects and has not been subject to
any fines, penalties, injunctive relief or any other civil or criminal liabilities which in the
aggregate have or may have a material adverse effect on its ability to perform its obligations,
duties, responsibilities or liabilities under this Work order.
8)No representation or warranty by the Subcontractor contained herein contain any untrue
statement of material fact or omits or will omit to state a material fact necessary to make
such representation or warranty not misleading;

G. SAFETY & INSURANCE:


1) Subcontractor shall be fully responsible for the security of its manpower, materials (contractor's
assets), material (issued by HGIEL), equipment's and entry in or around the project site.
Subcontractor also responsible to provide accommodation, food and other required amenities at
its cost its manpower, if required. Subcontractor shall arrange water, electricity etc. as required
executing the work from its source.
2) Insurance of personnel and material of the Subcontractor shall be taken by the Subcontractor at
its own cost. Subcontractor's labours should be responsible for work with maintaining safety of
his own, of other HGIEL Staff as well as of other Road users while working at site. Any Damages
occurred due to Accident while working at Site by Subcontractor, same should be
compensated/repaired/ restored by Subcontractor at their risk & cost.
3) PPE's will be provide by the Subcontractor to it's all the staff and used by them by while working
at site.
4) In-case the Subcontractor fail to provide PPE's the same will be provide by the HGIEL and cost
plus 10%will be deduct from the Subcontractor. HGIEL Supply rate PPE's are as followS:
Helmet for workers Rs. 71 per Nos.
b) Jacket- Rs. 110 per Nos.

c)Safety Belt/Full Body Harness-Rs. 1200 per Nos.


5) If any safety violation has to be found by HGIEL or our client, penalty will be imposing which shall
beRs.5000/- per occurrence: and in that case HGIEL supply PPE's and cost will be deducted as
above.
a) Step 1- Warning Memo (2 Times).
b) Step 2 Rs. 5000/- per occurrence.
c)Step 3-1% Bill deduct ofthat day

H. DISPUTE RESOLUTION:
1) All disputes arising between the parties as to the interpretation, operation, onffect of any clause
in this work order or any other difference arising between the partieswhichcannot be mutually
resolved, shall be referred to the arbitration. The arbitrator shall be spahbitratgr as nominated
by Chairman/Managing Director of HGIEL, The decision of such an arbator shaibe binding on
the parties.

gzetHA9 FOr-Pathwa,EnterprSie
Page 9 of 10
2) If the Concession Agreement between Authority and Concessionaire will terminate, the HGIEL
shall terminate this Work Order by giving 10 (ten) days Termination Notice to the Subcontractor.
If Subcontractor fails to fulfil its obligations stipulated in this Work Order, in that case the HGIEL
shall be free to terminate this Work Order by giving 10 (ten) days termination notice to the
Subcontractor.
3) This Work Order is subjected Indian Laws and Jaipur (Rajasthan) Jurisdiction.

This Work Order is issued in two copies of equal status and strength. Please return one copy duly
signed at your end in token of your acceptance.

Accepted by
For M/s H.6. Infra Engineering Ltd. For-Pathway
For M/sPatíwayEnteronses
Entérprises

(Authorized Signatory) Authorized Signatory)

Page 10 of 10