Method Of Procedure
MS1NW – Mop Install SMU on PE Mobile
Site : TTC Lambaro, STO Lhokseumawe, TTC Siantar, TTC Amir Hamzah, TTC Pahoman, TTC Telanai, TTC
DLD Palembang, TTC Belanti, TTC Batam Center, TTC HR Muhammad, TTC Teling, TTC Paniki, TTC
Soekarno Hatta, TTC Dago, STO Tembung, STO Bukittinggi, STO Pangkal Pinang, STO Muarabungo
Node : R1.LBR.PE-MOBILE.1/2, R1.LSM.PE-MOBILE.1/2, R1.STR.PE-MOBILE.1/2, R1.AHZ.PE-MOBILE.1/2,
R1.LPG.PE-MOBILE.1/2, R1.TLN.PE-MOBILE.1/2, R1.DLD.PE-MOBILE.1/2, R1.BLN.PE-MOBILE.1/2,
R1.BTM.PE-MOBILE.1/2, R5.HRM.PE-MOBILE.1/2, R7.TLG.PE-MOBILE.1/2, R7.PNK.PE-MOBILE.1/2,
R3.STA.PE-TSEL.1/2, R3.DG1.PE-TSEL.1/2, R1.TBG.PE-TSEL.1/2, R1.BKT.PE-TSEL.1/2, R1.PGP.PE-
TSEL.1/2, R1.MRB.PE-TSEL.1/2
Version 1.0
February 2022
PT SISINDOKOM LINTASBUANA
Graha Astel
Jalan Pintu Air Raya No. 2A Lt. 3A
Jakarta Pusat 10710
INDONESIA
http://www.sisindokom.com
❖ Document Identification
File Name MS1NW – MOP Install SMU on PE MOBILE
Version 1.0
Document Author Ikrimah
Document control Andrew
❖ Modification History
Version Date Status Revision
1.0 08th February, 2022 1st Version -
1.1. Audience
The document can be used by Telkom and/or Telkomsel engineering teams who will be
responsible for the operating system deployment.
1.2. Comment
Current Method Operation Procedure is designed to Install SMU on router interface due to
request from customer.
3. Topology
Summary Steps
1. Pre-execution verification
2. Install SMU
3. Post-Execution Verification
Fallback plan will be executed if there’s anomally during execution with following criteria :
• If any problem with new policy, restore to the last stable policy
6. Monitoring
• After finish the troubleshoot procedure, report to Telkom and Telkomsel and inform them to
verify.
• Monitoring will be done on 05:00AM and continue with the monitoring team.
• If need escalation, contact and follow-up with Cisco TAC team.