You are on page 1of 2

UVT 2612

Tutorial 3

1. Ali Quarries Sdn Bhd is a local marble and granite producing company headquartered in
Kuala Lumpur. Granite deposits in have recently been discovered on the Gunung Ledang
mountain range. Advise the managers as to the necessary tasks and reports for a successful
application to the government to quarry the said mountains.

S.34A EQA -
(1) The Minister, after consultation with the Council, may by order prescribe any activity which may
have significant environmental impact as prescribed activity.
(2) Any person intending to carry out any prescribed activity shall appoint a qualified person to
conduct an environmental impact assessment and to submit a report thereof to the Director General
in the manner as the Director General may prescribe.
(2A) The Director General shall maintain a list of qualified persons who may carry out an
environmental impact assessment and submit a report thereof.
(2B) The qualified person who submits the report shall--
(a) be responsible for the environmental impact assessment and the recommendations of the
environmental impact assessment;
(b) ensure that the report and the recommendation do not contain any false or misleading
information;
(c) take a professional indemnity insurance for any liability arising from the environmental
impact assessment and the recommendations of the environmental impact assessment.
(2C) The report shall be in accordance with the guidelines as the Director General may prescribe and
shall contain--
(a) an assessment of the impact such activity will have or is likely to have on the environment;
and
(b) the proposed measures that shall be undertaken to prevent, reduce or control the adverse
impact on the environment.

(6) Any person intending to carry out a prescribed activity shall not carry out such activity until the
report required under this section to be submitted to the Director General has been submitted and
approved.
(7) If the Director General approves the report, the person carrying out the prescribed activity, in the
course of carrying out such activity, shall provide sufficient proof that the conditions attached to the
report (if any) are being complied with and that the proposed measures to be taken to prevent,
reduce or control the adverse impact on the environment are being incorporated into the design,
construction and operation of the prescribed activity.
(8) Any person who contravenes this section shall be guilty of an offence and shall be liable to a fine
not exceeding five hundred thousand ringgit or to imprisonment for a period not exceeding five
years or to both and to a further fine of one thousand ringgit for every day that the offence is
continued after a notice by the Director General requiring him to comply with the act specified
therein has been served upon him.

The fact remains that projects do go on without the said approval


as what happened in the case of Tenggara Gugusan Holidays Sdn
Bhd v Public Prosecutori a case regarding a resort project on the
beach of Kampung Pulau Kerengga, Marang, Terengganu. Although
the crux of the decision was the definition of "any person"," the case
was brought to court because the EIA report was completed after the
project itself was completed, thus making a mockery of the process as
well as being in breach of the EQA