Project DESIGN 

AND BUILD OF THE CONSTRUCTION AND INSTALLATION OF DNSC‐DJAL WATER SYSTEM
Owner DAVAO DEL NORTE STATE COLLEGE
Location NEW VISAYAS, PANABO, DAVAO DEL NORTE
Subject PERT CPM ‐ WORK PLAN SCHEDULE

Day to 
Scope of Works Amount LEGEND Duration

CONCRETING WORKS
Start
WORK PLAN
40 
PART A. DESIGN PHASE CD
I. TOPOGRAPHIC SURVEY AND SITE INVESTIGATION 515,970.00 AA 10 1 G
II. SOIL INVESTIGATION 374,692.50 BB 10 11
III. GEO‐RESISTIVITY SURVEY 606,264.75 CC 10 21
10  10  10  30  10  40 120  30  30 
IV. DETAILED ENGINEERING DESIGN SERVICES 393,120.00 DD 30 31 CD
10 
CD CD CD CD CD CD CD CD CD
PART B. CONSTRUCTION PHASE START AA BB CC DD A B C E F H END
I. MOBILIZATION 1,066,952.25 A 10 61
II. GENERAL REQUIREMENTS 543,304.13 B 40 71
III. EXPLORATORY WELL DRILLING 4,175,671.50 C 120 111
IV. CONSTRUCTION OF CONTROL HOUSE 1,127,763.00 D 40 111
40 
V. CONSTRUCTION OF STORAGE TANK 2,734,641.00 E 30 231 CD
VI. PIPELAYING OF DISTRIBUTION/TRANSMISSION LINE 1,288,696.50 F 30 261 D
VII. SUPPLY AND INSTALLATOIN OF RAINWATER CATCHMENT TANK 1,308,966.75 G 40 111
VIII. DEMOBILIZATION 327,395.25 H 10 291
Total 14,463,437.63 300 DESIGN PHASE CONSTRUCTION  PHASE

SUBMITTED BY:

MAYBELYN A. ECO
PRESIDENT - ECOMIXED CONSTRUCTION & SUPPLY CORP.