Professional Documents
Culture Documents
1
Center for Technology and Systems Management, University of Maryland at College Park, MD 20742, USA
E-Mail: blair@eng.umd.edu and ayyub@umail.umd.edu
2
400 E 8th Avenue, Ellensburg, WA 98928, USA. E-Mail: benderw@cwu.edu
defined as the potential for loss as a result of a system uncertainty
failure. Risk can be measured as a pair of the 4. Fuzzy stochastic analysis for cases with both
probability of occurrence of an event, and the outcomes cognitive and non-cognitive types of uncertainty
or consequences associated with the event’s occurrence. where the fourth case can be developed by combining 2
This paring is not a mathematical operation, a scalar or and 3. The MOB has activities whose durations and
vector quantity but a matching of an event’s probability costs can be analyzed as deterministic, stochastic, fuzzy
of occurrence with the expected consequence. or fuzzy stochastic.
probability theory
(ii) Uncertainty and information measures based on Yes
fuzzy sets and possibility theory.
(iii) Uncertainty measures within the framework of Stochastic duration estimate
belief and plausibility based on the theory of
evidence.
Uncertainty can be attributed to vagueness where Input into Simulation
there are ill defined boundaries and ambiguity where module
there are several choices for a given situation (see [9]). Figure 1: Fuzzy Stochastic Application
In structural and reliability analyses the following
methods for cognitive and noncognitive types of
uncertainty are recognized (see [10]): 1. Collect and input subjective information
1. Deterministic analysis for cases without 2. Quantify subjective information using fuzzy sets
uncertainty in basic variables 3. Estimate various parameters of distributions,
2. Stochastic analysis for cases with noncognitive including maximum and minimum values, and the
type of uncertainty mean and variances of the parameters
3. Fuzzy analysis for cases with cognitive type of 4. Examine graphical display of distributions. The
fitted distribution is affected by selection and dominating distribution type. This theorem is applied
membership values of the linguistic variables. If fit to each MOB concept and scenario combination critical
is unsatisfactory, update estimated parameters. path for schedule duration and all activities for cost. In
5. From satisfactory fit obtain stochastic estimate of simulating total schedule duration, only activities on the
the duration critical path are considered while in simulating total
6. Input results into simulation module cost, all activities are considered. Schedule duration is
Quantification of subjective information using fuzzy approximated by a probability distribution with mean
sets is done using the following steps: and variance the sums of the means and variances of
Step1: Variable definition the activities on the critical path, respectively. Total
Step 2: Rule composition cost is approximated by a normal distribution with
Step 3: Translation mean and variance the sums of the means and variances
Step 4: Execution of all activities, respectively. The probability
This quantification creates the fuzzy inference system associated with completing the project within certain
depicted in Fig. 2. time or cost limits can be computed using standard
normal distribution formulae. The central limit
theorem is used as a basis to justify computed schedule
and cost risk probability.
Specify system Macro-level
structure and debugging and
variables analysis
3.2 Risk-Based Decision Analysis
Performing risk analysis may require making various
Fuzzy Inference
System
decisions in order to reduce the risk of the MOB.
Engineering decisions involving risk need to be made
using a systematic framework that considers many
facets of a decision problem. The decision framework is
Specify
membership
Micro-level
debugging and
called the decision model. In order to construct a
functions for each
variable
analysis decision model (see[14]), the following elements of the
decision model need to be defined: (1) objectives of
Specify fuzzy rules
decision analysis, (2) decision variables, (3) decision
outcomes, and (4) associated probabilities and
Figure 2: Fuzzy Inference System consequences.
and Schedule
GB3
GB1
Blocks Blocks Assemble
Lower 6
GB2
Hulls for GB2 for GB3
4
Start 1st 2nd 3rd
Column Outfit
Column Column 2
set set set
0
1st Brace 2nd 3rd Brace 10 12 14 16 18 20
set Brace set set
Number of Shipyards in Concept and Scenario
Figure 3: Rigid Concept Afloat Scenario Model Figure 4: Fuzzy Assessment of Construction
Layout Management Conditions
The network layout in Fig. 3 is the basis for the For example, there are 12 shipyards involved in the
model produced with the Extend software. The heavy rigid afloat concept and scenario, thus the simulated
lines signify the critical path. Each MOB concept and results for cost and schedule are increased by 1.3 % to
general scenario has some common components and account for construction management conditions.
input distributions. There were a total of 9 concept
scenario combinations (see[20], [21]). Only details of 4.3 MOB Design of Experiments
one, the rigid concept with afloat assembly is given in Design of experiments for MOB construction
this paper. simulation involves the determination of the number of
simulation cycles that meet precision and accuracy
4.2 Fuzzy Assessment of Construction Management requirements. To determine the accuracy of simulation
Conditions results the number of cycles necessary to achieve an
Construction management conditions impact a given acceptable error level in the estimate of a given MOB
concept cost and schedule due to the complexity and concept and scenario schedule duration and cost are
dependence of integrating components from several computed from the results of an initial 50 cycle run. A
facilities. The uncertainty involved is subjective and standard 95% confidence level is assumed. Use is
thus incorporated into simulation using fuzzy analysis. made in this design of experiments of cost and schedule
FUZZLE 3.0 a fuzzy logic inference shell for estimates that are preliminary with a precision in the
development of rule-based system applications to 15% order of magnitude. In simulating based on this
control, diagnostics and decision aid system is used. data, a simulation accuracy (e) equal to 1% of the cost
Two variables are defined for this fuzzy analysis. and schedule of any given MOB concept and scenario
The input variable is the number of shipyard involved module is specified which is one order of magnitude
in a given concept and scenario which is a measure of more than the precision of the input data and should
the complexity involved. The output variable is the improve results.
percentage increase in total cost and schedule. With a 95% confidence level and a specified
Membership functions for the variables are accuracy (e), the minimum number of cycles (n) per
formulated by a possibility distribution function taking simulation run are given by:
values between 0 and 1. Three triangular membership σ2
functions, small, medium, and large are defined per n = 2 (1.96) 2 (2)
e
variable. The range of the number of shipyard input
variable is set from 10 to 20. The range of the percent Simulations with 50 cycles are run for each concept
and scenario combination and equation 2 is applied to
765
(Days)
the rigid concept is found that a minimum of 47 and 15 745
740
runs for schedule and cost respectively are required. 735
Thus the minimum required runs for both cost and 730
725
schedule is 47. 0 1000 2000 3000 4000 5000
Having found the minimum number of cycles Number of Simulation Cycles
required per simulation, the stability of the results from Figure 7: Mean Schedule Duration as a Function of the
simulation to simulation are investigated. Convergence Number of Simulation Cycles
tests of the coefficient of variation of the mean are done
to determine the number of cycles required to obtain
stable results. For 2000 cycles, the simulation results for all concept
The variation of coefficient of variation of the mean and scenario combinations are obtained (see[21]).
with number of cycles for the rigid concept afloat These results which apply the central limit theorem and
scenario is shown in Fig. 5. The variation of the mean use the normal distribution are used in the decision
of cost and schedule with number of cycles rigid model for decision analysis.
concept afloat scenario is shown in Fig. 6 and 7
respectively. 5. DECISION ANALYSIS
Cost
0.01
Schedule minimizing labor and safety impact, and minimizing
0.005 environmental impact. As such MOB construction
requires multiple objective decision-making. MOB
0
0 1000 2000 3000 4000 5000 objectives need to be stated in the same units, and
Number of Simulation Cycles weight factors that can be used to combine the
objectives need to be assigned. This requires
Figure 5: Coefficient of Variation of Mean Cost and
determination of objective weighting and utility for
Schedule as a Function of the Number of Simulation
multiple objective decision making.
Cycles
5.2 Objective Weighting
306 The relative weighting shown in Fig. 8 are assigned
Mean Cost (Millions $)
305
304
to the various MOB objectives.
303
302
301
300
299 Total MOB
Construction
298
297
0 1000 2000 3000 4000 5000
Number of Simulation Cycles Cost Schedule Length Labor and Safety Environmental
(35) Duration (20) Impact Impact
(25) (10) (10)
the rules developed for environmental impact analysis Newport News Shipyard
Similar to Figure 11 Total Expected Utility