QUANTITY SCOPE OF ELECTRICAL WORKS

SN ACTIVITY UNIT QTY # OF GROUP

1 Electrical cable pulling (including termination) m 1,325,203.00 4


2 Cable tray installation m 244,630.00 12
3 Electrical equipment and all panel installation set/cub 2,244.00 2
4 Junction box installation set 374.00 2
5 Conduit installation m 244,302.00 20
6 Lighting fixture installation set 11,385.00 10
ECTRICAL WORKS
TOTAL ACCOMPLISHMEN TOTAL DURATION
COMPARISON
MANPOWER T GROUP/DAY ACCOMPLISHMENT /DAY DAYS
200 6000 220 250 220.87
120 720 335 370 339.76
24 48 60 120 46.75
12 12 40 60 31.17
140 800 305 330 305.38
50 100 114 150 113.85
QUANTITY SCOPE OF ELECTRICAL WORKS
SN ACTIVITY UNIT QTY # OF GROUP

1 Electrical cable pulling (including termination) m 335,139.00 2


2 Cable tray & filling installation m 12,231.00 2
3 Perporated cable tray installation m 49,716.00 8
4 Junction box installation each 375.00 2
5 Instrument equipment and all panel installation set 257.00 2
6 Field instrument installation each 2,972.00 2
7 Conduit installation m 2,318.00 1
8 Air piping installation m 9,336.00 3
9 Piping hook-up installation m 9,832.00 3
ECTRICAL WORKS
TOTAL ACCOMPLISHMEN TOTAL DURATION
COMPARISON
MANPOWER T GROUP/DAY ACCOMPLISHMENT /DAY DAYS
80 4000 95 155 83.78
20 100 110 120 122.31
64 240 220 250 207.15
12 24 30 48 15.63
12 12 30 48 21.42
12 36 82 110 82.56
10 40 60 80 57.95
24 60 155 170 155.60
27 75 131 150 131.09