HANDOVER FLOW CHART

A .Installation Phase 1) Inspection of Work Installation 2) Testing for the Installation 3) Pre-Requisite for T&C

1) 3) Pre- 4) Start –
B. Integrated Testing & 2) Installation 5) Operational 6) Functional
Commissioning Functional up & Initial
Commissioning Completion Performance Performance
Plan Checks Checkout
Phase verification Test Test

Phased
Handover

Project License &


Project Records - Records-As Insurance Spare Parts Warranties
Installation Certifications
Built Drawing

C. Closeout Phase

Employer Final O&M


Project Records Leed Cleaning &
Training & Inventory Manuals
- Testing and Certification Punch list
Training (If Applicable)
Commissioning Clearance
Manual