Identification of Stakeholders

A stakeholder is a party that has an interest in a company and can either affect or be affected by
the business. The primary stakeholders in a typical corporation are its investors, employees,
customers, and suppliers. The following are the stakeholders for the project of fixing PE pipe
for water supply line from pump station No: 1 (near KB canal) to Sindh university filter plant.

List of Stakeholders:
1. Government of Sindh
2. Sindh University
3. Contractor
4. Labor
5. Alumni
6. Students
7. Suppliers
Preliminary Design

This is the design of the whole water supply scheme however the project selected is the fixation
of pipe from the KB canal to the filter plant. Therefore the plan of the project is given below:
The bottom purple line of 2x6” dia going from the ponds up to the filter plant shows the pipe
which has been fitted
Economic Calculations:
Sr Items Amount
in Rs
1 Excavation and fitting in trench includes (joints & testing) 7823850
2 Excavation for pipe line and shape leveling of beds to correct 22494
level
3 Cutting joints holes and disposal of surpus earth providing fence 104490
guard light flags and temporary for non-vehicular traffic
4 Excavation of pits in starta of compact coniomeration of 215075
boulders by hammering.
5 Pacca brick work other than building including striking of joints 113169
upto 20ft hieght
6 Cement plaster ¾ Thick 70311

Health and Safety consideration:


1. Providing fence during the construction
2. Guard lights provided for the vehicle and pedestrians
3. Flags for the crossing non vehicular traffic.
4. Disposal of Surplus earth to other location