Professional Documents
Culture Documents
1150
tf i^mfng'o^R. In re M. and N. (Minors) (C.A.) [1989]
I would only add that, in agreement with Butler-Sloss L.J., I regard
injunctive protection of children from publicity which, though inimical to
their welfare, is not directed at them or at those who care for them, but
is an incidental part of life, as being in a special category to which this
judgment is not addressed, but which was considered in In re X. (A
Minor) (Wardship: Jurisdiction) [1975] Fam. 47.
Appeal allowed. B
No order as to costs.
Legal aid taxation.
[COURT OF APPEAL]
1988 Oct. 24, 26, 27, 28, 31; Purchas, Ralph Gibson and Russell L.JJ.
Nov. 2;
Dec. 15 F
A employer and the contractor. If the engineer shall fail to give notice
of his decision as aforesaid within a period of 90 days after being
requested as aforesaid or if either the employer or the contractor be
dissatisfied with any such decision then and in any such case either
the employer or the contractor may within 90 days after receiving
notice of such decision or within 90 days after the expiration of the
first named period of 90 days (as the case may be) require that the
° matter or matters in dispute be referred to arbitration as hereinafter
provided. All disputes or differences in respect of which the decision
(if any) of the engineer has not become final and binding as
aforesaid shall be finally settled under the Rules of Conciliation and
Arbitration of the International Chamber of Commerce by one or
more arbitrators appointed in accordance with the said Rules. The
Q said arbitrator/s shall have full power to open up review and revise
any decision opinion direction certificate or valuation of the engineer
and neither party shall be limited in the proceedings before such
arbitrator/s to the evidence of arguments put before the engineer
for the purpose of obtaining his said decision. No decision given by
the engineer in accordance with the foregoing provisions shall
disqualify him from being called as a witness and giving evidence
D before the arbitrator/s on any matter whatsoever relevant to the
dispute or difference referred to the arbitrator/s as aforesaid. The
arbitrator/s shall not enter on the reference until after the completion
or alleged completion of the works unless with the written consent
of the employer and the contractor provided always (i) that such
reference may be opened before such completion or alleged
£ completion in respect of the withholding by the engineer of any
certificate or the withholding of any portion of the retention money
to which the contractor claims in accordance with the conditions set
out in Part II in the clause numbered 60 to be entitled or in respect
of the exercise of the engineer's power to give a certificate under
clause 63(1) hereof or in respect of a dispute arising under clause 71
hereof (ii) that the giving of a certificate of completion under clause
F 48 hereof shall not be a condition precedent to the opening of any
such reference."
"Part II—Conditions of Particular Application ('P. C.')
"60(4) The contractor shall submit to the engineer after the end
„ of each month a statement showing the estimated contract value of
the permanent work executed up to the end of the month . . . and
the contractor will be paid monthly on the certificate of the engineer
the amount due to him on account of the estimated contract value
of the permanent work executed up to the end of the previous
month subject to a retention . . . (6) Payment upon each of the
engineer's certificates shall be made by the employer within 30 days
H after such certificate has been delivered to the employer and in the
event of failure by the employer to comply with the provisions of
this sub-clause he shall pay to the contractor interest at the rate of 9
per cent, per annum . . . (7) The engineer may by any certificate
make any correction or modification in any previous certificate
which shall have been issued by him and shall have power to
withhold any certificate if the works or any part thereof are not
being carried out to his satisfaction . . .
The Weekly Law Reports 24 November 1989
1158
Ptirchas L.J. Pacific Associates v. Baxter (C.A.) [1989]
By the contract between the employer and the contractor the latter
can only recover sums of money on account of the contract price when
these are certified by the engineer. In the end, subject to retention
money, the ultimate sum earned by the contractor is the initial contract
price as varied under the terms of the contract. The terms of G.C. 12
clearly provided that the additional sum to be paid by the employer shall
represent the additional expense to which the contractor had been put
by reason of the unexpected circumstances together with the proper and
reasonable expense of complying with instructions which the engineer
might issue and of any proper, reasonable measures approved by the F
engineer which the contractor might take in the absence of specified
instructions. The contractor, therefore, was to be protected against
being out of pocket but was not entitled to any profit on the additional
work involved.
Describing the position of the engineer the judge said:
"He was the agent of the employer for those purposes (i.e. the G
administration of the contract); he was contractually bound to his
principal, the employer, and the terms and scope of his agency
would be those to be inferred from what he was employed to do
under the terms of the contract. It also follows that, short of any
fraud or dishonesty on his part, which would be manifestly outside
the scope of his agency, his principal would be liable for the acts of u
his agent, subject to any right of recourse he might have against his
agent for indemnity."
The amended statement of claim asserted that
"the engineer held itself out, and was expected to, and the
[contractor] relied on the engineer so to perform the engineer's
obligations with the skill, etc. . . . "
The Weekly Law Reports 24 November 1989
1161
3 W.L.R. Pacific Associates v. Baxter (C.A.) Purchas L.J.
Although these facts are to be assumed for the purpose of the trial of
the preliminary issue, they are not determinative of the existence of
"proximity" for the purpose of liability in tort for the damage claimed.
On the question of liability the judge took as his starting point the
quotation from the speech of Lord Keith of Kinkel in Governors of the
Peabody Donation Fund v. Sir Lindsay Parkinson & Co. Ltd. [1985]
A.C. 210, 241:
B
"So in determining whether or not a duty of care of particular scope
was incumbent upon a defendant it is material to take into
consideration whether it is just and reasonable that it should be so."
The judge continued his judgment in these terms:
"This, in my view, is especially so where the duties on which a
C plaintiff relies to found a case in tort arise out of a contract, and
there would seem to be no reason why the defendant should not
have been made a party to the contract if that was the intention of
the parties and he had been prepared to assume a liability similar to
that now sought to be attached to him in tort."
He then referred to Tai Hing Cotton Mill Ltd. v. Liu Chong Hing Bank
D Ltd. [1986] A.C. 80, 107, per Lord Scarman:
"Their Lordships do not believe that there is anything to the
advantage of the law's development in searching for a liability in
tort where the parties are in a contractual relationship. This is
particularly so in a commercial relationship. Though it is possible as
a matter of legal semantics to conduct an analysis of the rights and
g duties inherent in some contractual relationships including that of
banker and customer either as a matter of contract law when the
question will be what, if any, terms are to be implied or as a matter
of tort law when the task will be to identify a duty arising from the
proximity and character of the relationship between the parties,
their Lordships believe it to be correct in principle and necessary
for the avoidance of confusion in the law to adhere to the
F contractual analysis: on principle because it is a relationship in
which the parties have, subject to a few exceptions, the right to
determine their obligations to each other . . . "
The judge continued:
"Lord Scarman was there dealing with the liability in negligence of
^ a banker to his customer. However, his words are in my view
equally pertinent to the situation one has here, where the duties
alleged arise out of the participation of the engineer in a contract,
although he was not a party to it, but the person who seeks to make
him liable in tort for his acts under the contract was a party to it.
More than that, the damage which the plaintiffs allege is wholly
comprehended within the ambit of the contract, and the action in
H tort is based on the plaintiffs' entitlement to what they claim was
their due from the employer under that contract. . . . Just as the
implications of the agency relationship between the engineer and
the employer depend on the terms of the contract between the
employer and the contractor (see Lord Morris in Sutcliffe v.
Thackrah [1974] A.C. 727, 747, 752), so also, in my view, must
those of the relationship between the contractor and the engineer.
More than that, the plaintiffs' whole case is based on the contract
The Weekly Law Reports 24 November 1989
1162
Purchas L.J. Pacific Associates v. Baxter (C.A.) [1989]
added obligations in tort. This was particularly the case where those A
provisions expressly provided an exclusion from liability protecting the
engineer or any of his staff from liability for their acts or obligations
under the contract. In support of his respondent's notice Mr. Tuckey
submitted that in any event the engineer was entitled to immunity from
suit in respect of the decision under G.C. 67 because any miscertification
at an earlier stage could then have been corrected at the G.C. 67 stage
and that in acting in pursuance of his duties under G.C. 67 the engineer "
was acting in a quasi-arbitral role.
The sheet-anchor for the consideration of the main issue raised in
this appeal is still Hedley Byrne & Co. Ltd. v. Heller & Partners Ltd.
[1964] A.C. 465. The central issue in that case was, of course, whether a
duty of care could arise in relation to spoken or written words. At the
risk of making a dangerous generalisation the effect of the authority for Q
the present purposes can be culled from the following short extracts
from the speech of Lord Devlin, at pp. 528-529 and 530:
"I think, therefore, that there is ample authority to justify your
Lordships in saying now that the categories of special relationships
which may give rise to a duty to take care in word as well as in
deed are not limited to contractual relationships or to relationships „
of fiduciary duty, but include also relationships which in the words
of Lord Shaw in Nocton v. Lord Ashburton [1914] A.C. 932, 972
are 'equivalent to contract,' that is, where there is an assumption of
responsibility in circumstances in which, but for the absence of
consideration, there would be a contract. . . . I shall therefore
content myself with the proposition that wherever there is a
relationship equivalent to contract, there is a duty of care. Such E
a relationship may be either general or particular. Examples of a
general relationship are those of solicitor and client and of banker
and customer. For the former Nocton v. Lord Ashburton has long
stood as the authority and for the latter there is the decision of
Salmon J. in Woods v. Martins Bank Ltd. [1959] 1 Q.B. 55 which I
respectfully approve. There may well be others yet to be established.
Where there is a general relationship of this sort, it is unnecessary
to do more than prove its existence and the duty follows. Where, as
in the present case, what is relied on is a particular relationship
created ad hoc, it will be necessary to examine the particular facts
to see whether there is an express or implied undertaking of
responsibility."
/-«
Of course, there has not only to be an acceptance of responsibility to
take care on the part of the potential tortfeasor but also a reliance on
that duty by the alleged victim. If it were otherwise the damage would
not have flowed from the breach if established. The engineer is a
professional body and in the context of the contract assumes a
responsibility towards the employer to execute his duties in a professional
manner. It remains, however, to consider whether beyond this the H
engineer accepted a direct duty towards the contractor and whether on
its part the contractor relied on the due performance of his duties under
the contract by the engineer beyond giving rights to the contractor to
proceed against the employer under the contract. This question lies at
the heart of this appeal and depends on whether an appropriate degree
of proximity between the engineer and the contractor beyond the terms
of contract is established. As I have already commented the assumption
The Weekly Law Reports 24 November 1989
1165
3 W.L.R. Pacific Associates v. Baxter (C.A.) Purchas L.J.
A of the truth of the facts pleaded in the amended statement of claim does
not determine this issue.
During the course of argument the court has been referred to a large
number of authorities many of which have considered a duty in tort
based on the Hedley Byrne duty or extensions thereto. It is clear from
these authorities that there is no one touchstone with which to determine
the existence or otherwise of a duty of care in any particular
° circumstance. Various criteria emerge which are capable of adaptation
to the particular circumstances of the case under review. As a
generalisation before a duty can be found to exist the circumstances in
which the parties find themselves must establish a proximity of some
kind that would demonstrate that the lack of care of the one will
foreseeably cause pecuniary loss to the other in the context where the
Q first has accepted responsibility for such loss, if occasioned by his
negligence, and the second has in the same context relied on the
exercise of due care and skill by the first so as to give rise to a direct
duty to be responsible for that loss. The matter does not end there,
however, because superimposed on the foregoing criteria is what has
been called a policy aspect, namely, that before a duty of care will be
held to exist the court should find it just and reasonable to impose such
D a duty: see per Lord Keith in Governors of Peabody Donation Fund v.
Sir Lindsay Parkinson & Co. Ltd. [1985] A.C. 210, 241. This aspect was
also discussed in the judgments in Greater Nottingham Co-operative
Society Ltd. v. Cementation Piling and Foundations Ltd. [1989] Q.B.
71. In that case there was a subcontract between the parties in which
certain liabilities in contract were accepted, namely to exercise skill and
£ care in the design of the concrete piling but nothing mentioned in the
contract of executing the work with care and skill. In those circumstances
it was held that no duty of care would be superimposed on the existing
contractual relationship: see p. 100:
"In order to establish what might be called the Hedley Byrne type
of liability, it must be possible to cull from the close relationship of
the parties the assumption by the tortfeasor of a duty not to cause
pecuniary loss to the victim. In Hedley Byrne & Co. Ltd. v. Heller
& Partners Ltd. [1964] A.C. 465 the relationship was not affected
by a direct contractual relationship and this was also the position in
Junior Books Ltd. v. Veitchi Co. Ltd. [1983] 1 A.C. 520, and there
was, therefore, no contractual influence on the relationship. In the
present case the tortfeasor had contracted to be liable for failure to
G use reasonable skill and care in the design of the pile driving
operation and in the selection of materials and goods (clause
A(l)(a) and (b)); but the contract was significantly silent as to
liability for the manner in which the work was executed. Once it is
established that there is no general liability in tort for pecuniary loss
dissociated from physical damage (see per Robert Goff L.J. in
Muirhead v. Industrial Tank Specialities Ltd. [1986] Q.B. 507 and
Bingham L.J. in Simaan General Contracting Co. v. Pilkington
Glass Ltd. (No. 2) [1988] 2 W.L.R. 761) it would be difficult to
construct a special obligation of this nature in tort to which liabilities
created by a collateral contract did not extend:" per Purchas L.J.
The facts of the present case are, of course, clearly distinguishable
from those in the Greater Nottingham Co-operative case but from the
policy point of view there may be a useful analogy, namely that where
The Weekly Law Reports 24 November 1989
1166
Purchas L.J. Pacific Associates v. Baxter (C.A.) [1989]
carried out. He was to exercise his care and skill in so ensuring. But A
his function differed from that of one who had to decide disputes
between a building owner and a contractor. When interim certificates
were issued it was necessary to have regard to the contract terms
and to exercise care and skill in certifying the value of work done.
/ / the contractor thought that the sum certified was too little the
contractor could call for arbitration. If the employer paid the amount
certified and later found that there was over-certification as a result of "
the architect's negligence I can see no reason why, if loss resulted to
him, he should not sue his architect.
"As parties to a building contract or to a contract of sale are in
general free to introduce whatever terms they wish into their
contract it follows that it is quite possible for them to arrange that
someone who at one stage is the agent of one party may at another Q
stage become an arbitrator as between the parties. But this must be
a definite arrangement. The mere fact that an architect must act
fairly as between a building owner and a contractor does not of itself
involve that the architect is discharging arbitral functions." (Emphasis
provided.)
Lord Morris said, at pp. 752-753: D
"In summarising my conclusions I must preface them by the
observation that each case will depend upon its own facts and
circumstances and upon the particular provisions of the relevant
contract. But in general any architect or surveyor or valuer will be
liable to the person who employs him if he causes loss by reason of
his negligence. There will be an exception to this and judicial
immunity will be accorded if the architect or surveyor or valuer has E
by agreement been appointed to act as an arbitrator. There may be
circumstances in which what is in effect an arbitration is not one
that is within the provisions of the Arbitration Act. The expression
'quasi-arbitrator' should only be used in that connection. A person
will only be an arbitrator or quasi-arbitrator if there is a submission
to him either of a specific dispute or of present points of difference F
or of defined differences that may in the future arise and if there is
agreement that his decision will be binding. The circumstance that
an architect in valuing work must act fairly and impartially does not
constitute him either an arbitrator or a quasi-arbitrator. The
circumstance that a building owner and contractor agree between
themselves that a certificate of an architect showing a balance due is
to be conclusive evidence of the works having been duly completed G
and that the contractor is entitled to receive payment does not of
itself involve that the architect is an arbitrator or quasi-arbitrator in
giving his certificate."
Viscount Dilhorne adopted the same approach and made no specific
reference to the existence or otherwise of any duty owed by the architect j ^
to the contractor. He referred to the effect of the arbitration clause,
however, in the following terms, at p. 757:
"It began with the words 'Provided always that, in case any
question, dispute, or difference shall arise between the proprietor,
or the architect on his behalf, and the contractor.' That, to my
mind, shows that the parties to the contract recognised that the
architect in performing his duties under the contract would be
The Weekly Law Reports 24 November 1989
1171
3 W.L.R. Pacific Associates v. Baxter (C.A.) Purchas L.J.
binding upon all parties.' It seems to me that this architect may well A
have been put in the position of an arbitrator under the exceptional
terms of the contract. Moreover, since there was no contractual
relationship between the architect and the builder, it is difficult to
see how any action based on a duty of care could be got up on its
feet against him; in those days the law of negligence was in a very
early stage of its development."
With great deference to Lord Salmon the reference to his view of the
position which would have arisen in Sutcliffe v. Thackrah had there been
under-certification rather than over-certification, may not be of such
compelling authority as if it had been a central matter for consideration
when delivering his speech in the earlier case.
This analysis of Sutcliffe v. Thackrah would, in my judgment, dispose Q
of two submissions that were made during the course of argument,
namely, the submission by Mr. Tuckey that when refusing to review the
contractor's application under G.C. 67 the engineer was acting in an
arbitral role. I am quite unable to accept the proposition that the role
played by the engineer under G.C. 67 was anything other than a review
of an earlier executive decision made in the course of his function as
supervising engineer and subject to arbitration under the latter provisions D
of G.C. 67. To adopt the words of Viscount Dilhorne in a similar
position in Sutcliffe v. Thackrah to view the function of the engineer
under G.C. 67 as an arbitral function would be to construct an
arbitration upon an arbitration. The second submission which I think is
at least damaged by the attitude taken by their Lordships in Sutcliffe v.
Thackrah was that made by Mr. Scrivener in pursuit of the "just and p
reasonable approach" that if there was a duty in tort owed by the
engineer to the employer so there ought also to be a similar duty owed
by the engineer to the contractor. Mr. Scrivener relied on the dismissal
by Lord Salmon in Arenson v. Arenson [1977] A.C. 405, 438, of the
"shot at from both sides" argument. In my judgment, however, this
submission is flawed because it ignores the distinction between the
contractual basis of the relationship between the employer and the F
engineer as opposed to the relationship between the contractor and
the engineer which can only be constructed in tort arising out of the
contractual structure accepted by the contractor. Although not central to
the considerations with which in Sutcliffe v. Thackrah Lord Morris of
Borth-y-Gest was concerned in his speech the extract already cited in
this judgment in which he refers to a right to sue the architect enjoyed
by the employer arising out of his duties to the employer and the right
of the contractor to go to arbitration if he disputed any certification or
action which affected him in a financial way points the distinction
between the remedies available to each.
Mr. Scrivener in support of his submission that a duty of care was
owed by the engineer to the contractor referred to a number of decisions
at first instance. These emanate from judges of great experience and H
merit consideration. They are conveniently assembled in the judgment
of Judge Fox-Andrews Q.C. in Michael Salliss & Co. Ltd. v. Calil
(unreported), 3 July 1987 of which we have been given a transcript. The
judgment was delivered on 3 July 1987 in the Official Referee's Business
List of the Queen's Bench Division. The first of the other two cases was
Lubenham Fidelities and Investments Co. Ltd. v. South Pembrokeshire
District Council in which the judgment at first instance was given by
The Weekly Law Reports 24 November 1989
1173
3 W.L.R. Pacific Associates v. Baxter (C.A.) Purchas L.J.
A Judge Newey Q.C. on 26 May 1983 and in the Court of Appeal is
reported at (1986) 33 B.L.R. 39. The third case was Shui On Construction
Co. Ltd. v. Shui Kay Co. Ltd. (1985) 4 Constr. L.J. 305, a judgment of
Hunter J. in the High Court of Hong Kong on 29 March 1985. Judge
Newey came to the conclusion that the architects, Wigley Fox, as they
were the architects appointed under the contract, owed a duty of care to
Lubenham, the contractors, as well as to the council. There was an
° alternative claim in tort based on an assertion that by issuing certain
certificates the architects were liable to the contractors for procuring a
breach of contract by the council. It was this latter issue, apart from the
construction of the contract itself, which attracted the attention of the
Court of Appeal and to a large extent the attention of the official
referee. The question of a duty of care in tort received only passing
C reference in the judgment of May L.J. (1986) 33 B.L.R. 39, 61. This
issue does not appear to have been argued in any detail in the Court of
Appeal.
The judgment of Hunter J. in Shui On Construction Co. Ltd. v. Shui
Kay Co. Ltd., 4 Constr. L.J. 305 is a skilfully structured and careful
judgment. After rehearsing the two questions posed by Lord Wilberforce
in Anns v. Merton London Borough Council [1978] A.C. 728, 751, and
D considering other cases "in the wake of Hedley Byrne & Co. Ltd. v.
Heller & Partners Ltd. [1964] A.C. 465," the judge took comfort from
the decision of the Court of Appeal in Esso Petroleum Co. Ltd. v.
Mardon [1976] Q.B. 801 on the question of legal proximity. Turning to
the second question, the judge considered Sutcliffe v. Thackrah with
particular attention to the reference to that case made by Lord Salmon
E in Arenson v. Arenson [1977] A.C. 405, 438, and described Lord
Salmon's remark as "admittedly an obiter but in my judgment a plainly
considered view of a very distinguished judge in this field." Hunter J.
also relied on the views of Lord Denning M.R. in the Arenson case in
the Court of Appeal [1973] Ch. 346, 365. However, Lord Denning M.R.
at the passage to which reference is made was dealing with the position
p of a professional man carrying out a valuation or a weighing operation:
b
see Glanzer v. Shepard (1922) 135 N.E. 275; 233 N.Y. 336, per Cardozo
J. With respect to Hunter J. this latter reference is of little assistance to
the application of the second question in the Anns case as it is now
applied in the circumstances of the present case. Summarising the
position in what may well be a sage comment, Hunter J. said, at p. 309:
„ "One is minded to suspect that architects will prove to be unable to
resist the tide which in the last 20 or 30 years has successively
submerged accountants, solicitors, barristers, surveyors and valuers
in the sense that they have all been held to owe duties of care to
persons other than their own clients. When one adds that support to
the statute (sic) of Lord Salmon and Lord Denning, it does seem to
be impossible for me to conclude that the case advanced on the
H pleading is unarguable."
Hunter J. was dealing with an application to strike out the claim. In
fairness to him since he delivered his judgment in 1985 there has been
an extensive and dramatic reconsideration of the whole area of tortious
liability for pecuniary loss arising from negligent misstatements and the
like: see the judgment of Bingham L.J. in Caparo Industries Pic. v.
Dickman [1989] 2 W.L.R. 316, 320 et seq. With respect to Hunter J., in
The Weekly Law Reports 24 November 1989
1174
Purchas L.J. Pacific Associates v. Baxter (C.A.) [1989]
A time when its relationship with the engineer was established, namely, at
tender stage, and to pose the question: Did the contractor rely on any
assumption of liability in tort appearing to be accepted on the part of
the engineer which would afford to the contractor remedies beyond
those which it acquired under the terms of the contract in respect of
which it was to tender? One must start with the proposition that if the
contractor had required an indemnity or extra-contractual protection in
" respect of defaults by the engineer or insolvency on the part of the
employer then it was open to the contractor to have stipulated for such
protection. On the contrary, by accepting the invitation to tender on the
terms disclosed in the document "Instructions to Tenderers" and the
contractual documents submitted therewith the contractor must be taken
to accept the role to be played by the engineer as defined in the
Q contract.
The terms of the contract provided a three-stage process under which
the contractor obtained payment for his work, the third stage of which
(G.C. 67) included a reference to one or more independent arbitrators who
are given the power "to open up review and revise any decision opinion
direction certificate or valuation of the engineer." In the case of withholding
by the engineer of any certificate the resort to arbitration is not postponed
D until after completion of the works. However in this case, as a matter of
history, the claim under G.C. 67 was not made until after second certificate
of completion. The opening words of G.C. 67 are extremely wide: "If any
dispute or difference of any kind whatsoever shall arise between the
employer or the engineer and the contractor . . . " No function of the
engineer under or in connection with the contract was mentioned to the
g court during the course of argument which would escape this clause.
Clause P.C. 84 refers to P.C. 83 (deduction of sums certified due from the
contractor to the employer) and other matters in which the engineer's
decision is made final by the contract but the purpose of the clause is to
ensure that the engineer "will act independently of and entirely unfettered
by the employer." It was not argued that this clause affected in any way
the operation of the arbitration provisions in G.C.67.
F P.C. 85 gives very wide discretionary powers to the engineer in the
discharge of his function under the contract which are quite incompatible
with the role of an arbitrator. Wide as they may be, however, they are
subject to the provisions of G.C. 67, and it is under this clause that
arbitration is introduced. In my judgment, as I have already indicated,
there is no question of arbitral immunity being enjoyed under the terms
P of this contract by the engineer.
It remains only to consider shortly the significance of P.C. 86. This is
admittedly an important part of the contractual structure against which
the contractor accepted the engineer in his role under the contract. The
clause provides specifically that "neither the engineer nor any of his staff
shall be in any way personally liable for the acts or obligations under the
contract." This can only refer to his own acts in performing the
H obligations imposed on the engineer under the contract. The question is
whether the protection of this clause extends to the negligent performance
of those functions. In this context it is not necessary to establish that the
negligence on the part of the person relying on the exclusion clause is
the only negligence to which reference can be made as is the case with
such a clause in ordinary contracts. The presence of the reservation is
given its normal role to play in the overall1 consideration of what
responsibility was accepted by the proposed tortfeasor. This is dealt with
The Weekly Law Reports 24 November 1989
1176
Purchas L.J. Pacific Associates v. Baxter (C.A.) [1989]
in the speech of Lord Reid in Hedley Byrne & Co. Ltd. v. Heller & \
Partners Ltd. [1964] A.C. 465, 492-493:
"It appears to me that the only possible distinction in the present
case is that here there was no adequate disclaimer of responsibility.
But here the appellants' bank, who were their agents in making the
inquiry, began by saying that 'they wanted to know in confidence
and without responsibility on our part,' that is, on the part of the g
respondents. So I cannot see how the appellants can now be
entitled to disregard that and maintain that the respondents did
incur a responsibility to them.
"The appellants founded on a number of cases in contract where
very clear words were required to exclude the duty of care which
would otherwise have flowed from the contract. To that argument
there are, I think, two answers. In the case of a contract it is C
necessary to exclude liability for negligence, but in this case the
question is whether an undertaking to assume a duty to take care
can be inferred: and that is a very different matter. And, secondly,
even in cases of contract general words may be sufficient if there
was no other kind of liability to be excluded except liability for
negligence: the general rule is that a party is not exempted from p
liability for negligence 'unless adequate words are used'—per
Scrutton L.J. in Rutter v. Palmer [1922] 2 K.B. 87, 92, C.A. It
being admitted that there was here a duty to give an honest reply, I
do not see what further liability there could be to exclude except
liability for negligence: there being no contract there was no
question of warranty."
E
In accepting the invitation to tender with the complete contractual
framework including the disclaimer in P.C. 86, it would, in my judgment,
be impossible either to support the contention that the engineer was
holding himself out to accept a duty of care with the consequential
liability for pecuniary loss outside the provisions afforded to the
contractor under the contract, or to support the contention that the
contractor relied in any way on such an assumption of responsibility on ^
the part of the engineer in any way to bolster or extend its rights. I
think that I should say that even if P.C. 86 were not included in the
contract in this case, the provisions of G.C. 67 would, in my view, be
effective to exclude the creation of any direct duty on the engineer
towards the contractor.
Before leaving the question of disclaimer I should refer to the speech G
of Lord Brandon of Oakbrook in Leigh and Sillavan Ltd. v. Aliakmon
Shipping Co. Ltd. [1986] A.C. 785, 817. Lord Brandon was commenting
on the speech of Lord Roskill in Junior Books Ltd. v. Veitchi Ltd.
[1983] 1 A.C. 520 in which Lord Roskill was considering whether an
exclusion clause in the main contract might affect the position as
between one party to that contract and a third party. Lord Roskill said,
H
at p. 546:
"My Lords, that question does not arise for decision in the instant
appeal, but in principle I would venture the view that such a claim
according to the manner in which it was worded might in some
circumstances limit the duty of care just as in the Hedley Byrne case
the plaintiffs were ultimately defeated by the defendants' disclaimer
of responsibility."
The Weekly Law Reports 24 November 1989
1177
3 W.L.R. Pacific Associates v. Baxter (C.A.) Purchas L.J.
A With reference to this passage Lord Brandon in the Leigh and Sillavan
Ltd. case said, at p. 817:
"As is apparent this observation was no more than an obiter
dictum. Moreover, with great respect to Lord Roskill there is no
analogy between the disclaimer in Hedley Byrne & Co. Ltd. v.
Heller & Partners Ltd. [1964] A.C. 465, which operated directly
P between the plaintiffs and the defendants, and an exclusion of
liability clause in a contract to which the plaintiff is a party but the
defendant is not. I do not therefore find in the observation of Lord
Roskill relied on any convincing legal basis for qualifying a duty of
care owed by A to B by reference to a contract to which A is, but
B is not, a party."
Q There can be no doubt of the force of Lord Brandon's comment as it
stands. However, with great respect to Lord Brandon the absence of a
direct contractual nexus between A and B does not necessarily exclude
the recognition of a clause limiting liability to be imposed on A in a
contract between B and C, when the existence of that contract is the
basis of the creation of a duty of care asserted to be owed by A to B.
The presence of such an exclusion clause whilst not being directly
D binding between the parties, cannot be excluded from a general
consideration of the contractual structure against which the contractor
demonstrates reliance on, and the engineer accepts responsibility for, a
duty in tort, if any, arising out of the proximity established between
them by the existence of that very contract.
I have come to the conclusion, for the reasons already stated, that no
g liability can be established in tort under which the engineer owed a
direct duty to the contractor in the circumstances disclosed in this case. I
emphasise, however, that in coming to this conclusion it does depend on
the particular circumstances of the case not the least of which were the
contractual provisions in the contract which afforded an avenue enabling
the contractor to recover from the employer. I see no justification for
superimposing on this contractual structure an additional liability in tort
F as between the engineer and the contractor. In coming to this conclusion
I have taken into account: (i) that although there was a degree of
proximity established in the obvious sense that the contractor under the
terms of the contract relied on the engineer performing his duties in
supervising the execution of the works, this is not the same quality of
proximity required to establish a duty of care in the Hedley Byrne sense;
Q (ii) that the duty on the engineer to perform in accordance with the
contract arose out of some contractual relationship, unspecified, existing
between the employer and the engineer, which give rise to that duty;
(iii) that there was no direct contractual relationship between the
engineer and the contractor; (iv) that under the contract, the contractor
could challenge in the fullest sense the performance of his duties by the
engineer by claiming against the employer for sums due to the contractor
H including extra expenses and interest on outstanding sums due; (v) that
the contractor, when tendering for the contract, was content to offer for
the works on the terms set out in the invitation to tender which
incorporated the full terms of the proposed contract. In these
circumstances the following propositions appear to me to be established.
(i) The engineer remains under contractual obligations to the employer,
which give rise to a duty to exercise skill and care and in appropriate
circumstances to act fairly between the employer and the contractor. If
The Weekly Law Reports 24 November 1989
1178
Purchas L.J. Pacific Associates v. Baxter (C.A.) [1989]
A Mr. Scrivener also contended that this was a case in which, even if the
engineer could not be treated as having voluntarily assumed a responsibility
to the contractor to use proper care, and therefore could not be treated as
having known that the contractor was relying on that assumption of
responsibility, nevertheless the relationship between the contractor and
engineer was so close and so direct that a duty to take care, owed by the
engineer to the contractor, must be imposed by the law.
" There are, in my judgment, two main questions to be answered in this
case. The first is whether the relationship between the contractor and the
engineer, as alleged in the statement of claim, was such that the engineer
became under a duty to the contractor to act with due care to avoid
economic loss to the contractor under the contract with the employer,
assuming for that purpose, in the first instance, that there was no such
Q exemption clause or statement as is contained in P.C. 86 of the conditions
of particular application. The text of it has been set out by Purchas L.J.
The second main question is whether any such duty of care is to be
imposed having regard to the presence of that exemption clause even if the
answer to the first question is that, in the absence of such a clause, the
engineer would have become under such a duty. Since the exemption
clause is present in the contract, and since, for reasons which I shall give, it
D would be decisive against the imposition of any such duty of care, in my
judgment, even if, in its absence, the law would impose such a duty of care
on the engineer; there is no necessity for this court to reach a final
conclusion on the first question. This court should, however, I think,
express its view as to what the answer to that first question should be. The
professional firms engaged in construction work as architects or engineers
£ or surveyors, and the companies which carry out such work, are concerned
to know whether in the relationships between contractor, employer and
engineer under a contractual relationship like to that set out in this
contract, but ignoring the disclaimer clause, the law imposes a duty of care
on the engineer to the contractor, not to cause economic loss to the
contractor in the process of certifying and of accepting or rejecting claims
under the contract. Of course, each case will depend on its own facts and
F circumstances and on the particular provisions of the relevant contract: see
per Lord Morris of Borth-y-Gest in Sutcliffe v. Thackrah [1974] A.C. 727,
752G. But it is likely that a large number of contracts are placed for
construction or engineering works in which the contractual relationship of
contractor and employer and the contractual duties of the engineer are
substantially similar to those present in this case and it should be possible
^ to determine whether in general a duty of care does or does not arise in
such a case. Further, in considering the effect which may properly be given
to the exemption clause it is relevant to know whether there would be a
duty of care but for the presence of that clause.
' For my part, I would answer the first question by saying that, on the
facts as they are in this case assumed to be, there was "no express or
implied undertaking of responsibility" (see per Lord Devlin in Hedley
H Byrne & Co. Ltd. v. Heller & Partners Ltd. [1964] A.C. 465, 530) on
which the alleged liability of the engineer could be founded, according to
the primary submission by Mr. Scrivener based on Hedley Byrne. It seems
to me that the facts in Hedley Byrne were markedly different and that the
principle there applied is not capable of direct application in this case. A
feature of Hedley Byrne, in my judgment, is that there was an approach,
made to the defendant bank by or on behalf of the plaintiffs, inviting the
bank to provide a service of advice and information directly to the
VOL. 3 50
The Weekly Law Reports 24 November 1989
1182
Ralph Gibson L.J. Pacific Associates v. Baxter (C.A.) [1989]
plaintiffs. Hence it was, to deal with some of the passages relied on by Mr. A
Scrivener, that Lord Reid said, at p. 486:
"A reasonable man, knowing that he was being trusted or that his skill
and judgment were being relied on, would, I think, have three courses
open to him. He could keep silent or decline to give the information
or advice sought: or he could give an answer with a clear qualification
that he accepted no responsibility for it or that it was given without g
that reflection or inquiry which a careful answer would require: or he
could simply answer without any such qualification. If he chooses to
adopt the last course he must, I think, be held to have accepted some
responsibility for his answer being given carefully, or to have accepted
a relationship with the inquirer which requires him to exercise such
care as the circumstances require."
C
Hence it was, also, that Lord Morris of Borth-y-Gest said, at p. 495:
"If someone who was not a customer of a bank made a formal
approach to the bank with a definite request that the bank would give
him deliberate advice as to certain financial matters of a nature with
which the bank ordinarily dealt the bank would be under no obligation
to accede to the request: if, however, they undertook, though -.
gratuitously, to give deliberate advice (I exclude what I might call
casual and perfunctory conversations) they would be under a duty to
exercise reasonable care in giving it. They would be liable if they were
negligent although, there being no consideration, no enforceable
contractual relationship was created."
Further, Lord Devlin said, at pp. 525-526: g
"It would be surprising if the sort of problem that is created by the
facts of this case had never until recently arisen in English law. As a
problem it is a by-product of the doctrine of consideration. If the
respondents had made a nominal charge for the reference, the problem
would not exist. If it were possible in English law to construct a
contract without consideration, the problem would move at once out
of the first and general phase into the particular; and the question
would be, not whether on the facts of the case there was a special
relationship, but whether on the facts of the case there was a contract.
The respondents in this case cannot deny that they were performing a
service. Their sheet anchor is that they were performing it gratuitously
and therefore no liability for its performance can arise. My Lords, in
my opinion this is not the law." G
In this case there was no request to the engineer by or on behalf of the
contractor for the engineer to render any service of any kind to the
contractor. The contractor came into that relationship with the engineer, as
Purchas L.J. has demonstrated, which was the result of the contractor
entering into the contract with the employer and of the engineer having
been engaged by agreement with the employer to perform the functions of H
the engineer under the contract. The engineer assumed the obligation
under his agreement with the employer to act fairly and impartially in
performing his functions. He was under a contractual duty to the employer
to act with proper care and skill. Such risk as the engineer could reasonably
foresee of the contractor suffering loss as a result of any want of care on
the part of the engineer is, in my judgment, remote: the contract provided
for the correction by the process of arbitration of any error on the part of
The Weekly Law Reports 24 November 1989
1183
3 W.L.R. Pacific Associates v. Baxter (C.A.) Ralph Gibson L.J.
A the engineer and it has not been suggested that there is any real scope for
an error on the part of the engineer which would not be at once detected
by the contractor. The court should, I think, at least in the absence of any
factual basis for the engineer to have foreseen any other outcome, proceed
on the basis that the contractor would recover by arbitration the sums
which it ought to recover under the contract. It is, I acknowledge,
foreseeable that a contractor under such an arrangement may suffer loss by
® being deprived of prompt payment as a result of negligent under-
certification or negligent failure to certify by the engineer but arbitration
should secure interest on the unpaid sums.
The contractual duty of the engineer, owed to the employer, to act
fairly and impartially is a duty in the performance of which the employer
has a real interest. If the engineer should act unfairly to the detriment of
Q the contractor claims will be made by the contractor to get the wrong
decisions put right. If arbitration proceedings are necessary the employer
will be exposed to the risk of costs in addition to being ordered to pay the
sums which the engineer should have allowed. If the decisions and advice
of the engineer, which caused the arbitration proceedings to be taken were
shown by the employer to have been made and given by the engineer in
breach of the engineer's contractual duty to the employer, the employer
D would recover his losses from the engineer. There is, therefore, not only
an interest on the part of the employer in the due performance by the
engineer of the duty to act fairly and impartially but also a sanction which
would operate, in addition to the engineer's sense of professional obligation,
to deter the engineer from the careless making of unfair or unsustainable
decisions adverse to the contractor.
£ I have had in mind the submission of Mr. Scrivener based on the
opinion of Lord Salmon in Arenson v. Arenson [1977] A.C. 405, 438F and
of Lord Fraser of Tullybelton, at p. 442, and on the decisions of the judges
a^ first instance which have been reviewed by Purchas L.J. It is,
nevertheless, in my judgment, plain that, assuming the truth of the
allegations set out in the statement of claim, there is no material on which
it could properly be said that the engineer voluntarily assumed any
F responsibility to the contractor to take care in the discharge of the duties of
the engineer under the contract.
There was, as I have said, nothing in the nature of the engineer being
asked to render any service to the contractor, or of undertaking to do so.
As must have been obvious, in my judgment, to the contractor, the
position was that the engineer had agreed with the employer to perform
~ the functions of engineer under the contract and the proper performance of
those functions required that the engineer act fairly and impartially. I find
it impossible to hold that the engineer in fact assumed any relevant
responsibility to the contractor or that he said or did anything which
objectively considered could properly be regarded as an express or implied
assumption of such responsibility. The law may impose a duty in the
absence of any actual assumption of responsibility by a defendant in a case
H of economic loss but, if it is to do so, it should in my judgment be on the
ba'sis of an imposed duty and not by the assertion of an implied assumption
when there was in fact none.
I have, in reaching that conclusion, also had in mind the decision of this
court in Caparo Industries Pic. v. Dickman [1989] 2 W.L.R. 316, a case
concerned with the relationship of a statutory auditor of a company to a
shareholder and to an investor in the company. Bingham L.J. said, at p.
326:
The Weekly Law Reports 24 November 1989
1184
Ralph Gibson L.J. Pacific Associates v. Baxter (C.A.) [1989]
"The Hedley Byrne case [1964] A.C. 465 shows that the relationship A
of A and B may be sufficiently proximate if, independently of contract,
A assumes the responsibility of giving B deliberate advice: if A
engages B contractually to give advice to C, the relationship of B and
C is no less proximate, however that expression is interpreted."
The statutory auditors had been retained by contract by the company to
give an independent report to shareholders about the financial state of the B
company. Bingham L.J. concluded, at p. 327, that it was inescapable that
the auditor had voluntarily assumed direct responsibility to individual
shareholders. I cannot regard the engineer as being in a similar position to
that of the statutory auditors. In agreement with Purchas L.J., I would
hold that the engineer was not employed by the employer to exercise due
care in the interest of the contractor, so that the engineer could be Q
regarded as assuming responsibility to the contractor so to act. The
engineer was employed by the employer to act for the employer as
engineer under the contract and the duty thereby assumed by the engineer
to act fairly and impartially was a responsibility assumed only to the
employer.
As to the second basis of Mr. Scrivener's argument, I would again, for
the following reasons, answer the first question by saying that, if the
disclaimer clause were not present, the law should not, on the facts set out
in the statement of claim, impose a duty of care on the engineer owed to
the contractor in respect of the matters set out in the statement of claim. It
has been accepted that in a case of pure economic loss there may be
imposed by the law a duty to take care although there has been no
"voluntary assumption of responsibility": see per Bingham L.J. in Caparo E
Industries Pic. v. Dickman [1989] 2 W.L.R. 316, 326, citing Ministry of
Housing and Local Government v. Sharp [1970] 2 Q.B. 223, per Lord
Denning M.R. at pp. 268-269, per Salmon L.J. at p. 279E and per Cross
L.J. at p. 291A. Further, in Ross v. Counters [1980] Ch. 297 the defendant's
solicitors had undertaken to their client, the testator, to act with care with
reference to the effective making of the testator's will, including the p
conferring of a benefit on a named beneficiary. That beneficiary was held
entitled to recover against the solicitors in respect of the benefit lost
through the solicitors' negligence although there had been no direct
assumption of responsibility by the solicitors to the beneficiary or reliance
by the beneficiary. It was common ground on the argument of this appeal
that, for imposition of such a duty of care, the three requirements must be
satisfied, namely of foreseeability, of proximity, and that it is just and G
reasonable to impose the duty. In considering whether it is just and
reasonable to impose the duty it is necessary, or course, to take into
account the nature, extent and likelihood of any harm, foreseeably resulting
from any want of care.
As to foresight of harm, I have stated above that such risk as the
engineer could reasonably foresee of the contractor suffering loss, as a H
result of any want of care on the part of the engineer such as is alleged
in the statement of claim, is, in my judgment, remote, because the
contract provided for the correction of any such mistake by the process
of arbitration; and any risk of loss through an event such as the
insolvency of the employer, causing the contractor not to recover some
payment which it would have recovered if such payment had been
earlier certified by the engineer, was at least equally remote. No
The Weekly Law Reports 24 November 1989
1185
3 W.L.R. Pacific Associates v. Baxter (C.A.) Ralph Gibson L.J.
A allegation is made that such insolvency or other event should have been
in contemplation by any party.
Next, as to proximity, namely, "such close and direct relations that
the act complained of directly affects a person whom the person alleged
to be bound to take care would know would be directly affected by his
careless act:" see per Lord Atkin in Donoghue v. Stevenson [1932] A.C.
562, 580, 581, 582, cited by Lord Keith in Yuen Kun Yeu v. Attorney-
B
General of Hong Kong [1988] A.C. 175, 192. It is clear that the
contractor in entering into the contract placed reliance on the engineer
performing properly his obligations under the contract and the engineer
knew that the contractor would be initially affected by the way in which
the engineer performed those obligations; but, for the reasons already
stated, the engineer would not expect the contractor to be in the end
Q directly affected by the careless act of the engineer in performing those
obligations because of the way in which the contract provisions would be
expected to operate. The engineer is giving an opinion, or advising on,
matters on which the engineer has information, or access to documents,
not available to the contractor as in the case of the bankers in Hedley
Byrne and of the certifying accountants in such cases as Caparo Industries
Pic. v. Dickman. In such a case as this, the contractor will know at once
D whether he agrees with the action of the engineer and the contractor has
the information on which to judge whether he can or sensibly should
dispute the engineer's decision. That fact, not unlike the expected
intermediate examination before use of a defective chattel which may be
sufficient to negative any duty of care in a producer of the chattel to the
injured user (see the cases cited in Charlesworth and Percy on Negligence,
£ 7th ed. (1983), para. 8.33) seems to me to be of importance. The
producer, when that principle is applied, is not under a duty of care to
the ultimate user because he is entitled to suppose that the defective
state of the chattel, resulting from any want of care on his part, would
be detected and any risk of injury thereby prevented. Similarly, the
engineer in this case should be entitled to suppose that the contractor
will detect any error on the part of the engineer, caused by want of
F care, and take appropriate action. Further, the engineer has an
opportunity to correct any error which he has made and which is
pointed out to him by the contractor. If the engineer persists in his error
the process of arbitration should correct it and provide to the contractor
the reward which should have been allowed by the engineer together
with appropriate interest.
Q As to the third requirement, namely, that it should be just and
reasonable in all the circumstances to impose liability, I have no doubt
that, assuming the disclaimer clause to be absent, it would not be just
and reasonable. Mr. Scrivener drew attention to the fact that in certain
textbooks the existence of a duty of care on the part of an engineer or
architect to the contractor, in the circumstances of contractual structures
similar to that in this case, has been considered or assumed. The
H presence of the disclaimer in P.C.86 in this case indicates that attention
has been given to the possibility. I will assume that the engineer could,
and perhaps did, obtain such insurance cover as was thought to be
necessary. Mr. Scrivener also asserted that, if a duty of care should be
imposed in such a case as this, it is unlikely that attempts will be made
with any frequency to pursue similar claims hereafter because of the
great difficulty of proving that a decision made by a professional man is
capable of being characterised as negligent, in the sense of being outside
The Weekly Law Reports 24 November 1989
1186
Ralph Gibson L.J. Pacific Associates v. Baxter (C.A.) [1989]
assumption that the contractor had in law a valid basis of claim against A
the engineer I would have difficulty in accepting that the settlement of
their claim against the employer could provide the basis for holding that
the contractor should be prevented from pursuing that claim against the
engineer.
Lastly, as to the contention that the loss alleged in the statement of
claim could not, on the facts pleaded, be held to have been caused by
any negligence alleged against the engineer, I agree with Purchas L.J. °
that there is much force in the submissions made by Mr. Tuckey. The
statement of claim sets out the alleged acts of negligence in failing to
allow the contractor appropriate additional compensation, extensions of
time and the other relief claimed by it under the contract. It is then
alleged that, by reason of matters set out in the statement of claim, the
contractor has suffered loss and damage. Under the particulars, it is Q
alleged that the rejection of the contractor's claim forced the contractor
to commence arbitration proceedings against the employer. There is
then the bare statement that those proceedings were settled on the terms
described by Purchas L.J. Nothing suggests that the alleged negligence
of the engineer was a cause of the contractor choosing to settle its claim
as it did. If the engineer was not to blame for the circumstances which
caused the contractor to choose to settle the claim for a fraction of what D
was properly due to the contractor, and if such an outcome was not a
foreseeable consequence of any negligence on the part of the engineer in
dealing with the contractor's claims—and it is not alleged that it was—
the negligence of the engineer in rejecting the contractor's claims could
be regarded as relegated to no more than part of the history and
circumstances in which the contractor's decision was made to settle those g
arbitration proceedings: see Minister of Pensions v. Chennell [1947] 2
K.B. 250 cited in Banque Keyser Ullmann S.A. v. Skandia (U.K.)
Insurance Co. Ltd. [1989] 3 W.L.R. 25. Since, for the reasons given, the
contractor has failed to demonstrate any arguable cause of action against
the engineer it is not necessary to decide whether this point of lack of
proof of causation could be held by itself to justify striking out the
contractor's claim. F
RUSSELL L.J. This case is concerned with (a) the existence and
(b) the extent of any tortious duty owed, where purely economic loss
has resulted from negligent conduct on the part of an expert professional.
In this field Hedley Byrne & Co. Ltd. v. Heller & Partners Ltd. [1964]
A.C. 465, was a watershed and since that case the problem has Q
crystallised in a number of authorities in the Court of Appeal and the
House of Lords. The instant appeal is yet another illustration of the
problem.
As my starting point I take what is to be gleaned from Hedley Byrne.
The headnote reads, at p. 466:
"a negligent, though honest, misrepresentation, spoken or written,
may give rise to an action for damages for financial loss caused
thereby, apart from any contract or fiduciary relationship, since the
law will imply a duty of care when a party seeking information from
a party possessed of a special skill trusts him to exercise due care,
and that party knew or ought to have known that reliance was
being placed on his skill and judgment."
Lord Morris of Borth-y-Gest said, at pp. 502-503:
The Weekly Law Reports 1 December 1989
1189
3 W.L.R. Pacific Associates v. Baxter (C.A.) Russell L.J.
With those words in mind I examine some of the facts in the instant
case. The engineer presented the contractoi with the contract documents,
and the contractor freely chose to enter into the contract with the
employer. The contractor was aware that the engineer was not a party
to the contract, and that accordingly any complaint that might arise H
against the engineer at the suit of the contractor would be an extra-
contractual one which would have to be resolved by a process other
than a claim for breach of contract.
In the event of non-certification or under-certification the contractor
was entitled to arbitrate along the well defined processes to be found in
G.C. 67. Although for the reasons given by Purchas L.J. in his judgment
the engineer is not able to claim immunity from suit as a result of any
The Weekly Law Reports 1 December 1989
1191
3 W.L.R. Pacific Associates v. Baxter (C.A.) Russell L.J.