Scope of work:

1) Visual survey of structure


2) Verification of area statement
3) Verify load carrying capacity of each building

For point no. 1 and 2


Engineer No. of Days (working Days Total days Per day Total charges
type engineers on site) (travelling) charges (Rs.)
(Rs./engg)

Senior 3 5 2 7 ₹ 5,000.00 ₹ 105,000.00


Junior 4 5 2 7 ₹ 3,000.00 ₹ 84,000.00
Total amount (Rs.) ₹ 189,000.00

For point no. 3 - load capacity of structure


Total buildings (nos.) = 14
Total area (sq.ft) = 4,200,000
Rate (Rs./sq.ft.) = 0.125
Total amount (Rs.) = ₹ 525,000.00

Grand total for point 1 to 3 (Rs.) = ₹ 714,000.00 Plus taxes as appplicable