Professional Documents
Culture Documents
Project Topic:
The client is looking for consultants to provide a report bid outlining how they
would produce a study that outlines the following:
A feasibility study needs to be undertaken to assess if the goal of 50% of the
contract value can be realized via the UK supply chain. The project will need to
enable the client to understand the current UK supply chain capability,
including future capacity, to contribute to the Lagoon’s needed 6 mile walkway.
Page 1 of 32
CONTENTS
Headings Page
The first marine based hydropower in the world is the Swansea Bay Tidal Lagoon Power Station. This hydropower station in
question is being set up in Wales by the government of the United Kingdom. This hydropower station will function based on
the ocean waves of an artificially built 9.5 km breakwater wall, which will be constructed to contain 16 sluice-gated turbines.
Once the ocean waves are allowed to flow, they will run the turbines through the wicket gates. Electricity will then be
generated through the moderation of the water levels between both the lagoon and the sea. The Lagoon Power project is
expected to generate electricity in the range of 320 MW, making it a new innovation in the United Kingdom and Wales (CITB,
2016). A development consent order was also assented to, and this is aimed at generating electricity to serve 150, 000
households for over a century. This electricity supply grand plan is supported by the Infra-Red and Prudential Equity Funders,
who have put in place competitive traditional procurement systems on the project’s diverse areas of work. The Tidal Lagoon
project is a first of its kind project (FOAK) whose construction plan is laid across 5 years (Lilley and Evans, 2016). The
project, upon completion, is projected to prevent the emission of over 200,000 metric tonnes of CO2, as it uses carbon
minimally. This will also help the UK government achieve its ambition of generating 15% of its energy through renewable
sources by the 2020 (White & Miller 2016). Apart from this major achievement, the project will also positively influence the
rate at which direct and indirect job opportunities are made available in Wales, and also serve as a model for future tidal lagoon
projects worldwide in general and in the United Kingdom particular (Tidal Lagoon Power, 2016). The UK government has an
interest in reducing the UK’s carbon emission through the Tidal Lagoon’s innovative technology. It is expedient to have a
working knowledge of the UK supply chain’s capabilities in comparison to the realization of 50% of the sum for the project’s
Page 3 of 32
contract, thanks to the supply chain, as contained in a feasibility study report on how the UK supply chain is managed
(Osmond and Cohn, 2015; Mukherjee and Roy, 2017). The report talks of a structured preliminary assessment that was
conducted at the start of the project at the raising of controversies about the prospective project development, in order for the
UK government to decide whether it would move to the project’s next stage or opt for an alternative. It is essential to prepare
the findings and recommendations in a storable, shareable format that could be used for a long-term basis, as the project
requires. The feasibility report was written based off data which were collated from secondary sources and have been analysed.
First Objective (Functional requirement): An investigation of the capacities and strength of the present UK supply chain, and
how ready it is to support the Tidal Lagoon Project. Also, identify the possible openings for employment and the likely-to-be-
faced roadblocks.
Second Objective (Structural requirement): An assessment of the extent to which the Project on the Tidal Lagoon has
Analysis of Stakeholders
Third Objective (Resource requirement): Identification of the financial resources and execution procedure required for the
successful completion of the project, through the use of the current chain of supply.
The report is basically required to assess the ability of the current supply chain in the United Kingdom to aid the Project Tidal
Lagoon and point out proposed chances to create employment for the people, with the roadblocks for the supply chain. This
report shall include an analysis of the current supply chain, skills currently possessed by the workforce, and how future
workers from higher institutions will be hired and retained, and the beginning of competitive edge for successfully completing
the project (Jerkins, 2017). The present expenses of the United Kingdom’s public sector on goods procurement, with the
annual expenses for works and services culminating in £238 billion, which is equally one-third of the public sector’s total
expenses (HMG, 2011). In the IBM United Kingdom’s recent research, it was agreed to that the UK supply chain is capable of
delivering several components, especially the non-nuclear systems and infrastructure. However, the success of that will be
The construction of the tidal lagoon in such a location creates the chance to enlarge supply chains in the UK to accommodate
the commercialization of turbines, housing facilities, and generator production to boost the UK’s capacity in civil engineering
and boost the industrial workforce’s skill to enormously sell to the international and local markets (Tidal Lagoon Power,
2016). While the supply chain may seem like it has capacity in the said areas, there are great worries about how competitive
the competition for other infrastructural projects will be in the future, based on a constant reduction in the number of skilled
As expressed in the view of Beamon (1998), the supply chain assessment involves the examination each level of the supply
chain, from procurement natural resources to the supply of the finished product to consumers. Simchi – Levi et.al (2004)
elaborated that the examination of supply chain examination incorporates the revision of qualitative versions differentiating
numerous economic trade-offs that border the supply chain and bid the firm foundation instrumental to tactical arrangement,
strategy formation, and making decisions. In order for this aim to be accomplished, the study shall focus on working
assiduously with the Independent Tidal Lagoon Industry Advisory Group, ideal level-one contractors, government institutions,
authorities of the locStruResal, and several industrial associations so as to guarantee the incumbent local supply chain’s
The essential goal that resulted in making the client aware of the competency of the United Kingdom’s present supply chain
which will be arrayed on the Project Tidal Lagoon is the focus of this research. To achieve this objective, the study will give
Page 6 of 32
access to the usage of the supply chain capability model which AT Kearney (2017) said would offer an exceptional economic
benefit by assisting to generate a lasting description for supply chains in the case of the general strategy employed in the
business and questioning the present and soon-to-come supply chain urgencies.
Aligned with the acknowledged model, the Energy & Climate Change department began a process for the planning of the chain
of supply in conjunction with the Business Innovation and Skills department which offered a responses relating to competition,
skills and questioning a widespread notion likely propounded for the chain of supply so as to mark out the percentage of each
of the contract’s tier whose production will be done in the UK/Wales as well as assess the relationship between how the 65%
minimum UK content and the 75% verdict (Department of Energy & Climate Change, 2016).
The Independent Tidal Lagoon Industry Advisory Group and the favoured bidder delivered an evaluation of the chain of supply
centred on the task delivery packages which constitutes the entire project. This comprises all procedures, from the unprocessed
materials, to producing and accumulation, to operations and maintenance, all of which can be deduced from the discoveries of
White & Miller (2016). As at when this report was made, the study exposed the cost of the forecast labour to be over 1200 full-
time jobs for the various work packages during the contract interval lasting for 26 months.
The report evaluated the ability of the recent supply chain and its necessity in Wales, and revealed how the labour demand in
trades such as steel casting and metal works might be unable to meet the supply that businesses in the Welsh region make
available to the consumers (CITB, 2015). More than 800 businesses have been set apart in related sectors in the Welsh vicinity,
which presently have over 20,000 employees in their workforce. It is also said that this figure may not be enough for the
benchmark number of employees the Project Tidal Lagoon requires (Department of Energy & Climate Change (2016)). This
Page 7 of 32
has proven that the markets in Wales will in meeting the demands of the Project Tidal Lagoon undoubtedly face imminent
challenges, especially as it relates to the acquisition of a skillset or the employment of technical staff.
The effects of the Project Tidal Lagoon on the chain of supply in the UK/Wales and Swansea will be focused on in this session,
following the functional requirement classification. The Manufacturer (2018) gave insights on the impacts of the project on the
UK communities, so as to achieve supportable energy, reduced investing in the tidal power and supply chain openings all over
the country, if ultimately, the United Kingdom government wouldn’t allow the project to commence. Jones and Morgan (2018)
appended that given the fact that there is a vital role for the government to play in the catalysation of novel technologies and
supporting the launch of new industries through the elimination of risk, the expenditure, and the risk concerned would
nonetheless make it an utterly different proposition over the coming 120 years to wind and solar – systems with a lesser
functioning lifecycle.
The construction project is outstanding, filled with several risks from diverse sources considered generally to be costly in
combination to the socio-political, economic, and cultural risks added to the project risk (Zavadskas et.al, 2010). The Risk
Management Model as explained by Oslon et al. (2011) is an effort combined to ascertain and scrutinise a prospective
occurrence (project) that has the proclivity of having negative effects on individuals, communities, and the environment. It also
extends further to picturing out suggestions on the level of tolerance of the risk at the centre of the risk examination, as one
Page 8 of 32
simultaneously bears in in mind the impelling influences and present control measures to abolish future prospective risk-related
penalties.
In the research inputs of Mohammed, Janaka and George (2007), the risk factors attuned to the Tidal Lagoon Project lifespan
are known via stakeholders devising the Delphic method, the risk estimation checklist of the expert, sporadic review of the
formation process, including the opinions of Rutkauskas and Ginevioius (2011), who decided on a risk register for the
determination of the extent of the risk’s effect on a project, while also advising some likely risk response or adjustment tactics
Many risks are related with the supply chain as recognised in the preceding paragraph, which is an essential factor that has the
potential to influence the project and determine if it would fail or succeed. Risks, according to this theory, are usually
considered as dangers holding an unimaginable and detrimental aftermath on the goals of the project. The readings of
Tazehzadeh et.al (2018) enlighten the significance and recognise several probable risks which may have negative effects on the
delivery of the project, but Smith et.al (2006) stress the importance of knowing how the risks are connected as it concerns the
supply chain and specify that delays in projects have the tendency to rise if companies depend on external influences to control
Adding to the approach of risk management given in the preceding paragraph, the Tidal Project has environmental impacts,
which Mackinnon et al (2017) explained as the process of appraising the possible effects of a prospective project on the
environment, including the interwoven socio-economic, cultural and human–health consequence, favourable and unpleasant.
Page 9 of 32
The United Nations Environment (n.d) complemented the definition by saying that this assessment ranks among the essential
ones because it envisages how impactful the project will be on the environment, right from the planning and designing stage of
the project, proposes measures to reduce unfavourable impacts and moulds the project in a way that befits the local
Usually, suppliers are subjected to environmental pressures dissimilar to the clientele instigating bigger connections on the supply
chain due to stakeholders’ inability to differentiate one environmental effect from the other as it concerns the project and the
suppliers (Rao, 2005). The project’s size gets more attention than the supply chain’s suppliers (Epstein and Roy, 1998).
Conclusively, pressure wielded by the legislature in terms of duty of care related to production, processing and control of storage
Numerous bodies in the United Kingdom are bothered about how stable the construction industries’ chain of supply is, and
also the government of the United Kingdom has been accentuating on Constructions that would be sustainable (Environment
Agency, 2003) by tackling the hindrances and encouraging the system of environmental management as well as the
The sustenance of the Project Tidal Lagoon on the supply chain can be comprehended as an offshoot of the initiation of
environmental tools such as the assessment of the environment and the system of environmental management (Ofori et al,
2002) at the project’s formation stage, having the intention of classifying favourable options such as supplies and the quality of
materials, as the quality of materials oversees substantial impacts of the environment on the project in its construction phase, so
It is the opinion of Morton et.al (2002) that the process of the chain of supply are affected by the types and qualities of the
resources and are directly associated directly to different tasks but indirectly associated to the community’s socio-economic
growth, thereby describing Sustainable Construction as one of the endeavours aimed bringing improvements to the products
and services related to environmental performance and recognising the combined advantages and dangers (Hanfield et.al,
2005) via the addition International Standards Organization policies aimed at establishing the suppliers’ consciousness of
The environment as described by Hall (2001) possesses its own accountabilities within the supply chain and being reliant on
the project type, it shares both in the direct and indirect impacts between suppliers, organizing suppliers’ activities to go in
tandem with the thoughts of Hanfield et.al (2005) who specified the gains of the company from the stream of waste made from
the of procuring whatever commodities and services, and also the consequences of its responsibility.
The tactics of the procedure involve the portions of environmental policy which improve related environmental performances
and redirect the inaccuracies of a wide environmental outline which the project currently implements. Sheldon and Yoxon,
(2006) added that according to the mode of supervisory agreements, environmental-based dealings, environmental-based
reviews (Glasson et.al 2015), control of site waste, EMS certification and contrary logistics plans comprise collecting,
arranging and conveying used products for recycling. For example, the China Harbour Engineering Company, supported by
CIRIA, has worked in the past few years regarding the execution of the EMS, in conjunction with their Tier 1 providers (Tidal
This surveys the result of the planned project connected with the construction, developing and operating stages of the
economy, commonly measured in KPIs such as profits, business revenue, and wages/jobs terms (Hussain and Kumar, 2014).
The upward movement of the Project Tidal Lagoon in the United Kingdom and Wales shall provide a massive opportunity to
improve on and combat economic deterioration, particularly among the underprivileged sections and provide existing jobs
through the United Kingdom. The Tidal Lagoon Power (2006) ascertained that the project would boost the United Kingdom
GDP by £27bn while it is being constructed, and it will further boost the GDP by an additional £3.1bn as it functions for
production yearly.
An examination of the economic effect is best carried out utilizing currently existent economic archetypes and also prospective
economic archetypes in Wales, which comprises of the outline of the attributes of the economic effects to back the modelling
of economy’s labour under the Centre for Economics and Business Research’s macroeconomic impact models (Mundry and
Jones, 2013). This procedure is focused on aiding the economic impact on the program of the supply of ONS and using board
to depict the interrelationships within segments of the economy, final users, and the international market to generate the
nation’s Gross Domestic Product and income (Munday and Jones, 2013).
The union of the profits allowed for an outstanding chance for the United Kingdom government, a government that has
currently presented an array of reforms in the electricity market via the Energy and Climate Change department in a bid to
strengthen its production portfolio, and make provisions for substantial last request encouragement to the economy, using
investment programmes. This then gives assurance of the supply security, assigns the obligations to carbon targets (Committee
Page 12 of 32
on Climate Change, 2017), and based on reasonable cost to accomplish the long-term climate change goals among the end
users
Agreeing to (BBC, 2015) the financing of a £300m deal to erect a wall which is six miles out of the given £1bn lagoon project, is
going to definitely allow for the reservation of half of the investment within Wales’ economy, and among the country’s construction
and supply chain-related industries, leading to about 0.02% - 0.25% boost to Wales’ GVA during the period of constructing it. These
verdicts (Centre for Economics and Business Research’s Analysis, 2014) should massively affect the economy, following the
evaluation of the input and output representation on the Welsh economy by the Centre for Economic and Business Research.
The Centre’s assessment discloses that the Tidal project will produce close to 1, 850 jobs for people who work on-site, and these
would consist of jobs from direct, indirect and induced employment, from procurement of goods, services and supply chain from
Wales and currently appraised companies located in the country, to having an annual overall impact to the tune of £76m for 120
years the project is proposed to last, including a yearly increase of 0.14% in Wales’ GVA. The BBC further said that the project
shall create up to 200 full-time jobs every year, coupled with a prognosis of providing close to 70, 000 direct jobs in the supply
chain, and prompted effects, resulting to an estimated 0.22% of the United Kingdom’s employment rate, if ultimately, the Six
Blair et.al (1990) see stakeholders’ analysis as assessing a project, policy or embarkment’s importance from the perspective of
the organisation by questioning the status, interest and other characteristics of the stakeholders related to the organisation’s
Page 13 of 32
capabilities – past, or present. (Gan & Guo, 2014) think there no compromise exists in the approaches of formulating an outline
for stakeholder analysis. They rather decided on a common benefit of three elements: power, significance and involvements.
At the conceiving of a project, it becomes required to ascertain who the stakeholders are and what their roles are in the delivery
of the project, so as to commence planning based on their needs and expectations. This is necessary because each stakeholder’s
significance concludes at what level the project will hold the needs of stakeholders in that category, during the formulation of
Stakeholder management is identified as a vital tactic used to engage the external or internal grouping that is related to the
project and can affect the project’s output (Tidal Lagoon Power, 2016). White and Miller (2016) identified the Tidal Lagoon
(Swansea Bay) Plc; Andritz Hydro; General Electric, the Tidal Lagoon Industry Advisory Group; the Government of Wales;
and the Funders and Vendors of the broader supply chain as the main stakeholders. These stakeholders have the capacity to
discuss manufacturing and component type, including the formation of the data collection procedures for other stakeholders in
the industry.
The effects of stakeholders on project is measured using the “Stakeholders impact index analysis” (Olander, 2007). This is
unavoidable, because the stakeholder’s contentment equals a successful launch and completion of the project execution. This then
After knowing the project’s fundamental necessity through the identification of the execution methods and the financial funds
to set the project in motion based on the present supply chain, and handling related supplemented cost, the resource necessity
comes after.
Project planning as described by Al Nasseri, (2015), is any activity involving the advancement of the root for handling any one
project (here, the United Kingdom’s supply chain management). This also involves the planning project goals, interim work
products, processes, timing, finances, etc. so as to provide the preferred new goods or services, and incorporate these new
goods and services into a thorough project management plan, dependent on the plans of and how complicated the work
package comprising noteworthy milestones contributory to the project conclusion are. However, Maher & Hadidi (2017)
explain project planning as the fraction of the time budgeted for the completion of the project (in this case – 6 months),
financial expenses, the plan for how the work will be done by utilizing the Gantt Chart, Network Diagram etc. to craft the
According to (Miller 2002), the strategic approach of supply chain planning includes the development and planning of demand
forecasting, supply chain union, network design, definition of supply base, monitoring of supplier operations and key
performance metrics while scheduling functions includes manufacturing, purchasing, planning, production and ensuring cost
efficiency. (Chen and Hall, 2007). These scheduling apps track the physical condition of items, material monitoring, and
Life cycle cost analysis is a procedure that enables clients to understand the financial obligations of a project to establish the
feasibility of the project. Fuller (2016), compares the cost of ownership and prospects of a project with an alternative project
that meets the same performance requirements but has a different original operation to determine the total cost of ownership of
the facility or the cost of a project in operation. It is also seen as a strategy devised to calculate the economic value and
maintenance costs to use in selecting the project with the highest net savings (Lee, 2002). In short, it provides prerequisites for
analyzing the costs and benefits of a project and analogy tools based on the time value of money. Infrastructure projects, as a
one-time investment with operational complexity and energy consumption, impose more difficult cost controls than other
institutions and are combined with supply chain management to ensure business survival. It requires tedious life cycle cost
management and control (Feng, 2011). As a result, life cycle cost analysis is more accurate for greater construction cost
savings compared to other design alternatives, if carried out early in the project before major design decisions are made.
Commonly used indicators in life cycle cost analysis include net savings, investment savings, payback times, internal rate of
return, and other costing methods for making wrong decisions such as sensitivity. Analysis and analysis of the breakeven point
(Fuller, 2016).
A Gantt chart is a graphical representation of a series of project tasks related to the time allocated for each task, where
dependencies are easily identified, parallel activities are displayed, and total project time is defined and tracked to simplify
management. This Gantt chart ensure that the project is completed on time (Wilson, 2003). These actions are listed in a tabular
composition that displays the taskbar and indicates their duration. The actions are listed on the left, with a timeline above them.
Page 16 of 32
Each activity is visually represented by a bar, the location and duration of which indicate the start and end dates, as well as the
location and number of activities that overlap with other activities. Although Gantt charts are not decision strategies, they
provide networks of communication between analyst and user, and are also a competent tool to guide collaboration in project
planning. Using a Gantt chart in supply chain management in traditional construction will involve five main project stages,
which include project initiation (concept), planning (procurement), execution (production and installation) and completion
(winding up) (Mun, et al, 2017). This shows the five stages of supply chain planning, procurement, execution, distribution and
returning (Beamon, 1998). For the purpose of this study, the client wants to assess the capabilities of the existing UK supply
chain available to support the Tidal Lagoon project over a 6 month period, as shown in the figure below.
The definition of the following Gantt chart begins with the task names, which are the individual functions shown in the Task
List column. These functions are set in bold to represent the summary function, while the rest are indented to represent the
summary function's sub functions. Further down the column, you can see the start and end dates, which indicate the starting
and finish time of each taskbar. To add to the 26-week period, the length of each taskbar represents the task duration in weeks.
Percentage describes the development of each task, which is usually completed and shown in a different color, and finally, task
dependencies, which indicate that some tasks can only be started when previous tasks have been completed (critical path tasks),
while others continue simultaneously as indicated in the schedule (floating time). The Gantt chart begins with a kick-off
meeting, during which the team leader's strategy of the project charter determines the success of the project and serves as a
solid incentive for others to relate. The key stakeholders were presented, along with a summary of the project charter, as well
as the scope, possibilities, deliverables, challenges, expectations, budgets and deadlines (Sampietro, 2016).
Page 17 of 32
It aims to ensure that everyone on the board has a common understanding of the project and its delivery and agrees with the
project management procedures. The data collected for each purpose starts from week 2 and continues till week 23, while the
data is suggested to be 24 per week. Tendering of the first proposal report (draft) to be appraised by key stakeholders before final
submission to the client at week 25, pending bidding and defense of the results of the report with the client for consent and
adjudication at 26 weeks. It should be noted that at the end of each deliverable task, there will be regular meetings to inform
stakeholders about the results, and more steps will be prepared, and more important steps will be taken to avoid changing the
4.0 Contributions
Annual construction output in Wales was declining prior to 2012, but has increased by more than 10% and
current performance in the infrastructure sector should increase by approximately 7.1% over the next eight
years, leading to an increase in employment for the next eight years (a supply chain problem for the tidal
project). These data suggest that the demand for construction specialists in Wales will rise to an expected
employment growth of 4.7 per cent, with an income accounting rate estimated at over 5,000 a year, which
is higher than the UK average of 1.7 percent (CITB, 2016). To promote these new business and training
opportunities, government, supply chain, construction and other types of industries must work together to
make the project a success. More specifically, all UK supply chain opportunities will be identified if the
global investor digs into the project in terms of size, number and construction schedule before diving into
it. However, the company has been warned against external pressure from the short supply chain if the
project faces financial constraints, which in most cases are long-term artificial economic movements
(CITB, 2016)
Tidal Lagoon Power News (2015) announced some initiatives introduced by Tidal Lagoon Swansea Bay
Plc in collaboration with Welsh Construction and Construction in order to boost the project's regional
resources and give these businesses the opportunity to understand more about the proposed purchasing
systems on the project. According to Roger Evans in (Powerinfotoday, 2016), for Wales to maximize the
prospects of a flourishing sector, the supply chain must be engaged with necessary skills and capability.
The following discoveries were made based on the findings of (White and Miller, 2016) on the projecting
adjustment of the supply chain necessity for the Swansea Bay Tidal Lagoon;
Page 20 of 32
The Welsh territory may be viewed as a productive breeding ground for the implementation of a
£1.3 billion investment, but there must be ongoing efforts to capture the supply chain and
During this critical phase for the Swansea Bay Tidal Lagoon Project, Wales will maintain about
1200 full-time employment in 5 years and an additional 28 jobs per year for the next 120 years
(probable project life span). Thousands of jobs in Wales would be supported for many years,
effectively.
Currently, sufficient of competent labor for most components can be sourced in Wales regionally;
labor required for massive steel fabrication may involve outsourcing; and robust skill development
Government approval for the expansion of multiple Tidal Lagoon Projects would mean more job
opportunities and possibly new export businesses, in addition to the solid metal fabrication history
that needed to be upgraded with the Government and industry's obligation to ensure competence
equals capacity.
The construction of tidal lagoons, of which Lyddon et al. (2015) discussed that they have the potential to
reduce rising sea levels as part of their uniform risk management methods, which is one of the most
globally recognized methods for coastal flooding and seismic safety, risk versus safety flooding; generating
renewable energy and releasing less carbon. These techniques were modeled on severe flood events in
Colwyn Bay, North Wirral and its surrounding areas, respectively, with the construction of the Tidal
Lagoon Base to Wales. The fear of using observational data to determine the effect of tidal lakes on loose
deposits from wind-blown sands to beaches, coastal mud pits, coastal areas and sites of scientific interest is
The tidal project is designated a National Significant Infrastructure Project (NSIP) under the 2008 Plan Act,
along with the 2009 Infrastructure Plan Regulation; The Environmental Impact Assessment is required to be
implemented in the analytical evaluation of the Tidal Lagoon project to certify that the Marine Works
Regulations 2007, and the factors affecting it are affected. In spite of the many governmental requirements
outlined in the tidal project, many environmental concerns in the supply chain (Tidal Lagoon Cardiff, 2015),
including the effects on traveling fish, Aquatic mammals, birds, terrestrial ecology, shoreline and landscape,
biodiversity to name a few have been observed in the findings (NRW, 2018),
Apart from employment and tourism-generated income, rebuilding of area economies, and improved leisure
opportunities, the Tidal project assists in addressing the United Kingdom's requirement for inexpensive low-
carbon energy to the Welsh economy. According to Munday and Jones (2013) accounts, more than 2,000
straight engineering-related jobs are linked to the project, providing thousands of additional jobs to citizens
throughout Wales, with an estimated £316 million GVA produced plus an annual £76 million respectively in
120 years of management from the Welsh economy while constructing the project (Centre for Economics and
According to Hendry Review, potential economic profits associated with Tidal projects range from flood
defense to tourism growth, and are aided in the distribution of decarbonisation obligations, export
opportunities, and the additional education sector. However, the profits from the supply chain are linked to
the goal of this finding, which is to provide opportunities from regional communities and businesses
(Hendry, 2016). The study included that, on the basis of establishing more than 2 000 full-time jobs,
mainly in metal production, steel forming and so on, supply chain mechanisms and materials from a
Page 22 of 32
possible location in Wales or in the UK, with an object of 65% and 50% respectively, from the United
The evaluation connected with the ideas of (Munday and Jones, 2013; Mohr and Iloyd, 2014) determined that
for the UK government to enhance the UK benefit, a specific strategy for the support of the tidal lagoon project
should be based on its associated supply chain openings and broader economic values, instead of enforcing
burdens on customer bills (Vaughan, 2017). However, the aforementioned points are linked with the possibility
of accompanying hazards, which can develop as a result of the initiative locating cheaper products from
Stakeholder’s Analysis is now a universal programme to make sure there is the participation of everyone
signified by their thoughts, sentiment, and power etc. about affairs regarding the execution of the project
(Buertey, et.al 2016, Yang, et.al, 2011). Poor execution is not the cause of the failure of many projects after
implementation but predominantly the stakeholder’s exemplification, discussion and participation. Many
stakeholders find it difficult to participate precisely in project conferences, sending the wrong impression to
the project execution team about the stakeholders' reluctance to participate in decision making (Project
Management Institute, 2013). Instead, Yosie and Herbst (1998) advocated that every stakeholder should
have the ability to make major contributions as well as the ability to voice their concerns with the
implementers in order to elicit significant involvements in order to ensure a fruitful project delivery.
Lilley and Evans (2016) offered some basic aspects to be examined in the case of the Tidal lagoons project
as a model and the foundation of dialogue with stakeholders relevant to the aims of these lessons (CITB,
Intense discussions between regional skills development partnerships, labor market analysts, and
the Government of Wales on potential skills development required for projects, anticipating delays
Make labor market analysis reports available to other stakeholders by focusing on professional
training to address supply chain and skill gaps that can lead to project cost overruns.
In Wales, all construction projects utilize the same workforce, resulting in high embedding rates, so
the Wales government is taking a more constructive approach based on data provided by local
Because some oceanic employment is located outside of the production tasks, the need to outsource
outside of Wales may arise on a temporary basis, with the goal that the stakeholders involved will
find ways to ensure that trainings like that to polish skills in the marine occupation are pursued in
Finally, we will adopt labor supply and demand surveys to ensure the strongest support for
integrating these analyzes into the Government of Wales' annual regional skills development and
According to (Bryson, 2011; Mentzer et al., 2001), supply chain strategic is becoming more extensive and
complex, recounting your current situation, ambition, and methods of achieving it in terms of capacity,
opportunity, flowing with the rapidly developing business, the state of the market, and project construction. As
a result, a unified planning board is required to house the full scope of strategic and effective planning
processes (Love et al, 2004; Thunberg, 2016). lost sales, out of stocks, working principal requirements while
planning for the Tidal lagoon project this great, delivers gratifying cycle times and a determined platform by
Tactical planning requires decisions about the available resources (tools, people, objects, landscapes, etc.) or
features of the activity, especially work tasks (time series planning) within a time, that might affects the
finances of the project (Viadianathan, 2002). As a result, efficient strategic planning is critical for Tidal Lagoon
projects of this size to ensure that the project is completed in terms of supply time, cost savings, customer
Page 24 of 32
satisfaction and high quality. The Material Requirements Plan (MRP) system (Kim, 2014; and Ram et al., 2006)
has been established in the Tidal Lagoon project for supply chain production scheduling and supply
management to utilize resources for production. Continuous cascade, where product availability, low cost and
Maximizing technology produced by the ocean tides’ energy to create electricity has been found to be the
most economically sustainable choice compared to other substitutions while reducing carbon emission and
fuelling economic development in littoral locations. The economic evaluation of the tidal technologies is
vital concerning the clear approximation of the expenses while also drawing supposed investors to the
technologies (Segura et.al, 2017). The cost configuration systems associated with the tidal energy project's
life cycle are the concept, design development, manufacturing, installation, operation, maintenance, and
cost neutralization. The viability analysis of these costs using various economic and mechanical guides to
achieve profit in the project when compared to other renewable energy bases (Astariz and Iglesias, 2015).
According to O'Connor et al. (2013), lifecycle costing analysis on the Tidal Lagoon project will benefit
stakeholders by allowing investors to understand early actions to lower costs, generate more income, and make
good decisions based on verified convincing approximations of incomes and expenses related to each phase of
the project life cycle. According to Magagna and Uihlein (2015), lifecycle estimation is a long-term satisfying
inventiveness that provides a complete outline for stakeholders who are required to achieve the project's goals
but are confronted with insufficient funds and a difficult purchasing procedure to determine the sales outcome
and the effect on expense and profit while defining the total increment cost of the lifecycle of a project.
Heralova (2018) thus concluded that, in addition to the benefits of cost reduction in life cycle estimation, it
inspires more environmental resources that are proven to be economical solutions to environmental effects
on the project.
Concisely, it is understood that this report provides a vigorous and understandable style to examine the
competencies of the current and future UK supply chain presented to aid the erection of the Tidal Lagoon
Project, classify the potential job opportunities and the project will encounter, evaluate the effect of the Lagoon
on the UK/Wales/Swansea Communities supply chain, and finally, detect the executive. This general style was
derived from minor data of numerous investors' accounts and findings to address specific goals that
meticulously pay attention to the Client's condition and offer a Gantt chart for the Client's better understanding
of the factors taken into consideration and the timelines for the completion of the report. As a result, it is
expected that the report's findings and recommendations will dispel the client's and key stakeholders' reluctance
to move forward with the project's next phase, albeit with some introspection, as discussed in the report.
Page 26 of 32
References
Ajayi, O.V. (2017). ‘Distinguish between primary sources of date and secondary sources of data’, a
doctorate paper presentation of the Department of Curriculum and Teaching. Benue State
University, Makurdi, [Online]. Available at https://doi:10.13140/RG.2.2.24292.68481 (Accessed:
3 July 2021)
Akintoye, A., McIntosh, G. and Fitzgerald, E. (2000) ‘A survey of supply chain collaboration and
management in the UK’, European Journal of Purchasing and Supply Management, 6, pp 159
– 168.
Al-Nasseri, H.A. (2015) ‘Understanding Applications of Project planning and scheduling in
Construction Projects’, a doctoral thesis of the Lund University Sweden. [Online]. Available
at https://lup.lub.lu.se/search/ws/files/4293873/7767270.pdf (Accessed: 27 May 2021)
AT Kearney (2017) ‘Supply Chain Strategy and Capability Assessment: Creating a stronger voice
of Australia’s FMCG supply chain practitioners’, The Publication of the Australian Food &
Grocery Council. [Online]. Available at
https://www.atkearney.com.au/documents/711784/14360738/Supply+Chain+Strategy+and+
Capability+Assessment+2017.pdf/985e564d-701d-999e-9840-71ed435c7304 (Accessed: 27
May 2021)
BBC, (2015) ‘£300m deal for Swansea Bay Tidal Lagoon wall’, BBC News. [Online]. Available at
https://www.bbc.co.uk/news/uk-wales-south-west-wales-32993437 (Accessed 15 May 2021)
Beamon, B.M. (1998) ‘Supply Chain Design and Analysis: Models and Methods’, International
Journal of Production Economics, 55(3), pp 281 – 294. [Online]. Available at
https://pdfs.semanticscholar.org/8468/37663dd843c63e314998fd22a96575b81dae.pdf
(Accessed: 27 May 2021)
Blair, J.D., and Fottler, M.D. (1990). Challenges in health care management strategic perspectives
for managing key stakeholders. San Francisco, CA: Jossey – Bass.
Bowen, F., Cousins, P., Lamming, R., and Faruk, A. (2001) ‘Horses for Courses: Explaining the
Gap between the Theory and Practice of Green Supply’, Greener Management International,
35, pp 41 – 60
CarbonBrief, (2017) ‘Autumn Budget 2017: Key climate and energy announcements’ [Online].
Available at https://www.carbonbrief.org/autumn-budget-2017-key-climate-energy-
announcements (Accessed: 24 June 2021)
Centre for Economics and Business Research (2014) The Economic case for a Tidal Lagoon
Industry in the UK: A scenario-based assessment of the macroeconomic impacts of tidal of
tidal lagoons for power generation on the UK economy, the report for Tidal Lagoon Power
Limited. [Online]. Available at
http://www.tidallagoonpower.com/wp-content/uploads/2016/08/The-Economic-Case-for-a-
Tidal-Lagoon-Industry-in-the-UK_final.pdf (Accessed: 26 May 2021)
Chen, Z. L. and Hall, N.G. (2007) ‘Supply Chain Scheduling: Conflict and Cooperation in
Assembly Systems’, Operations Research Journal, 55(6), pp 1072 – 1089. [Online].
Available at http://citeseerx.ist.psu.edu/viewdoc/download?
doi=10.1.1.532.6899&rep=rep1&type=pdf (Accessed: 2 July 2021)
Page 27 of 32
CITB (2015) Workforce Mobility and Skills in the UK Construction Sector. [Online]. Available at
https://www.citb.co.uk/documents/research/workforce%20mobilty%202015/wales%20mobili
ty%20report%202015.pdf (Accessed: 31 May 2021)
CITB (2016) Construction Skills Network Wales 2016 – 2010. [Online]. Available at
http://www.britishdrillingassociation.co.uk/user_uploads/construction%20skills%20network-
2016-uk.pdf (Accessed: 31 May 2021)
CITB (2016) Construction Skills Network Wales 2016 – 2010. [Online]. Available at
http://www.britishdrillingassociation.co.uk/user_uploads/construction%20skills%20network-
2016-uk.pdf (Accessed: 31 May 2021)
Committee on Climate Change, (2017) Advice on the design of Welsh carbon targets. [Online].
Available at https://www.theccc.org.uk/wp-content/uploads/2017/04/Welsh-Carbon-Targets-
Committee-on-Climate-Change-April-2017.pdf (Accessed: 23 May 2021)
Department of Energy & Climate Change (2016). A feedback letter on the Tidal Lagoon (Swansea
Bay) Plc Supply Chain Plan. [Online]. Available at
https://www.parliament.uk/documents/commons-committees/business-energy-and-industrial-
strategy/Correspondence/1-BEIS-TLSB-26-February-17-19.pdf (Accessed: 27 June 2021)
Environmental Agency (2003) Position Statement Sustainable Construction. DEFRA Version 1
Epstein, M and Roy, M.J. (1998) ‘Managing Corporate Environmental Performance: A
Multinational Perspective’, European Management Journal, 16(3), pp 284 – 296
Feng, Y. (2011) ‘Life cycle costing management of construction projects based on value
engineering’, IEEE Xplore Digital Library. [Online]. Available at
https://ieeexplore.ieee.org/document/6002895?reload=true&tp=&arnumber=6002895
(Accessed: 3 June 2021)
Fuller, S. (2016) ‘Life – Cycle Cost Analysis’, whole building design guide of the National Institute
of Standards and Technology. [Online]. Available at https://www.wbdg.org/resources/life-
cycle-cost-analysis-lcca (Accessed: 2 June 2021)
Gan, X, and Guo, L. (2014) ‘A framework for stakeholder analysis in a construction project’,
Conference paper of the International Conference on Management Innovation and
Information Technology, 61. [Online]. Available at
https://www.researchgate.net/publication/271451115_A_framework_for_stakeholder_analysi
s_in_construction_projects/citations (Accessed: 27 April 2021)
Glasson, J., Therivel, R., and Chadwick, A. (2005) Introduction to Environmental Impact
Assessment, 3rd ed. Routledge Publishing, London
Hall, J. (2000) ‘Environmental supply chain dynamics’, Journal of Cleaner Production, 8, pp 455 –
471
Heralova, R.S. (2018) ‘Importance of life cycle costing for construction projects’, Conference Paper
of the Engineering for Rural Development, 23. [Online]. Available at
http://www.tf.llu.lv/conference/proceedings2018/Papers/N405.pdf (Accessed: 2 June 2021)
HMG (2011). Strengthening UK based supply chains: Construction and Infrastructure. A business
report of the HM Government on Industrial strategies: government and industry in
partnership. [Online]. Available at
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/
attachment_data/file/34712/12-1329-strengthening-supply-chains-construction-and-
infrastructure.pdf (Accessed: 26 July 2021)
IBM (2005). An evaluation of the capability and capacity of the UK and global supply chains to
support a new nuclear build programme in the UK. A business report of the IBM Business
Page 28 of 32
http://www.tidallagoonpower.com/wp-content/uploads/2016/08/Turning-Tide-the-economic-
significance-of-the-Tidal-Lagoon-Swansea-Bay.pdf (Accessed: 26 May 2021)
NRW, (2018) ‘Swansea Bay Tidal Lagoon’, a newsletter of the Natural Resource Wales [Online].
Available at https://naturalresources.wales/about-us/news-and-events/statements/swansea-
bay-tidal-lagoon/?lang=en (Accessed: 21 June 2021)
O’Connor, M., Lewis, T. and Dalton, G., (2013). “Operational expenditure costs for wave energy
projects and impacts on financial returns. Renewable energy, 50, pp. 1119 – 1131. [Online].
Available at https://www.sciencedirect.com/science/article/pii/S0960148112005290
(Accessed: 2 January 2019)
Ofori, G., Gang, G., and Briffet, C., (2002) ‘implementing environmental management systems in
construction: lessons from quality systems’, Building and Environment, 37, pp 1397 – 1407.
Olander, S. (2007) Stakeholder impact analysis in construction project management. Construction
Management and Economics Journal, 25(3), pp 277-287. [Online]. Available at
https://doi.org/10.1080/01446190600879125 (Accessed: 30 April 2021)
Oslon, D.L. and Wu, D. (2011) ‘Risk Management Models for supply chain: a scenario analysis of
outsourcing to China’, Supply Chain Management: An International Journal, 16(6), pp 401 –
408. [Online]. Available at https://doi.org/10.1108/13598541111171110 (Accessed: 17 May
2021)
Powerinfotoday, (2016) ‘Tidal Lagoon Swansea Bay begins a series of Supply Chain Awareness
Events in Wales’, Press Release of the Powerinfortoday. [Online]. Available at
http://www.powerinfotoday.com/Tidal-Energy/tidal-lagoon-swansea-bay-plc-begins-a-series-
of-supply-chain-awareness-events-in-wales (Accessed: 3 January 2019)
Pye, K. and Blott, S. (2014) Comments and Advice relating to the proposed Swansea Bay Tidal
Lagoon, with particular reference to changes in coastal processes and potential impacts.
KPAL report no 16033. Kenneth Pye Associates Limited: Solihull. [Online]. Available at
www.kpal.co.uk/reports.html (Accessed: 30 May 2021)
Rao, P. (2005) ‘The greening of suppliers in the South East Asian context’, Journal of Cleaner
Production, 13, pp. 935 – 945
Rutkauskas, A.V. and Ginevioius, A. (2011) ‘Integrated management of marketing risk and
efficiency’, Journal of Business Economics and Management, 12(1), pp 5 – 23
Sampietro, M. (2016) ‘Project Team Members and Project’, PM World Journal, 5(5). [Online].
Available at https://pmwj46-may2016-Sampietro-Project-Team-Members-and-Project-
Meetings-Series-Article.pdf (Accessed: 3 January 2019)
Segura, E., Morales, R., and Somolinos, J. (2017) ‘Cost Assessment Methodology and Economic
Viability of Tidal Energy Projects’, Energies Journal, 10(11) pp 1806. [Online]. Available at
https://www.mdpi.com/1996-1073/10/11/1806/htm (Accessed: 2 January 2019)
Sheldon, C. and Yoxon, M. (2006) Environmental Management System: a step by step guide to
implementation and maintenance, 3rd ed. Earth scan Publishing, London
Shen, L. Y and Tam, V. (2002) ‘Implementation of environmental management in the Hong Kong
Construction Industry’, International Journal of Project Management, 20, pp 535 – 543
Simchi-Levi, D., Wu, S.D., & Shen, Z.M. (2004) Handbook of Qualitative Supply Chain Analysis:
Modelling in the E-business Era. Kluwer Academic Publisher. [Online]. Available at
http://shen.ieor.berkeley.edu/handbook/Chapter1.pdf (Accessed: 27 May 2021)
Smith, N.J., Merna, T., and Jobling, P. (2006) Managing Risk: In Construction Projects, Blackwell
Publication, USA
Page 30 of 32
Tazehzadeh, M.N., Rezaei, A. and Kamali, S., (2018) ‘Supply Chain Risk Management in the
th
Canadian Construction Industry’, A conference paper at the 11 International Congress on
Civil Engineering. [Online]. Available at
https://www.researchgate.net/publication/327645157_Supply_Chain_Risk_Management_in_
Canadian_Industry (Accessed: 14 May 2021)
Tidal Lagoon Cardiff (2015) Proposed Tidal Lagoon Development, Cardiff, South Wales:
Environmental Impact Assessment Scoping Report. [Online]. Available at
http://www.tidallagoonpower.com/eia-scoping-report/ (Accessed: 23 June 2021)
Vaidyanathan, K. (2002) ‘Case study in the application of project scheduling system for
construction supply chain management’, Conference proceedings at the IGLC conference,
Gramado, Brazil. [Online]. Available at
https://iglcstorage.blob.core.windows.net/papers/attachment-d9411387-561d-4a36-b497-
b67ca26f42fa.pdf (Accessed: 2 March 2021)
White, S. and Miller, N., (2016) A study to forecast the manufacturing and assembly labour requirement
for the Swansea Bay Tidal Lagoon. [Online]. Available at
https://businesswales.gov.wales/skillsgateway/sites/skillsgateway/files/documents/sg_-
_sbtl_manufacturing_study.pdf (Accessed: 5 May 2021)
Wilson, J.M. (2003). ‘Gantt charts: A centenary appreciation’, European Journal of Operational
Research, 149, pp 430 – 437. [Online]. Available at https://doi:10.1016/S0377-2217
(02)00769-5 (Accessed: 3 January 2019)
Zavadskas, E.K, Turskis, Z., and Tamosaitiene, J. (2008) ‘Contractor selection of construction in a
competitive environment’, Journal of Business Economics and Management 9(3), pp 181 –
187. [Online]. Available at https://doi:10.3846/1611-1699.2008.9.181-187 (Accessed: 12
April 2021)
Page 31 of 32
APPENDIX ONE
A3 Map