Professional Documents
Culture Documents
Question 1
Product unit based:
Product A – Total Cost – RM684,000; Cost Per unit – RM76
Product B – Total Cost – RM825,000; Cost Per unit – RM55
Batch based:
Product A – Total Cost – RM78,000; Cost Per unit – RM8.67
Product B – Total Cost – RM77,500; Cost Per unit – RM5.17
Product sustaining:
Product A – Total Cost – RM18,600; Cost Per unit – RM2.07
Product B – Total Cost – RM15,400; Cost Per unit – RM1.03
Factory sustaining:
Product A – Total Cost – RM72,000; Cost Per unit – RM8.00
Product B – Total Cost – RM120,000; Cost Per unit – RM8.00
Question 2
(a) (i) Expected enrolment (students): Undergraduate – 3,528; Graduate – 1,890
(ii) Total credit hours (hours): Undergraduate – 88,200; Graduate – 37,800
(iii) Full-time equivalent enrolment (students): Undergraduate – 2,940; Graduate – 1,575
(iv) Number of faculty members needed (members): Undergraduate – 123; Graduate – 105
1
LEARNING CURVE
Question 1
7th assignment time = 1.615 hours
Question 2
(d) 1 – 1,000 hours; 2 – 800 hours; 4 – 720 hours; 8 – 648 hours; 16 – 583.20 hours
Question 3
15.15 hours
Question 4
(a) 0.33 minutes
Question 5
Learning rate - 73 %
Question 6
Learning rate – 83.5 %
Question 7
Selling Price per bike: Quotation 1 – RM2,280; Quotation 2 – RM2,064;
Quotation 3 – RM2,121.60
2
Question 8
(a) 90%
(c)
4 months = 92 normal workings days / 120 with overtime
Used day = (10.0+8.1+7.4+7.1) = 32.6 days = 33 days
Up to 15 boats:
- Cumulative average time per unit = 6.6257 days
- Total cumulative time = 6.6257 days x 15 boats = 99.38 days / 99.4 days / 100 days
Time needed to complete boat 15th = Total time up to 15th boat - Total time up to 14th boat
= 99.39 days – 93.74 days
= 5.65 days / 6 days
Comparing remaining normal day and time needed to complete remaining 11 boats, 67 days
– 59 days, short of 8 days.
Up to 14 boats:
- Cumulative average time per unit = 6.6956 days
- Total cumulative time = 6.6956 days x 14 boats = 93.74 days / 93.7 days / 94 days
Comparing remaining normal day and time needed to complete remaining 10 boats, 61 days
– 59 days, short of 2 days.
Up to 13 boats:
- Cumulative average time per unit = 6.7714 days
- Total cumulative time = 6.7714 days x 13 boats = 88.03 days / 89 days
Comparing remaining normal day and time needed to complete remaining 9 boats, 56 days –
59 days, extra 3 days.
3
Question 8