Professional Documents
Culture Documents
Faisal H. Alnaseef, Mohammed K. Almedallah, and Stuart R. Clark, UNSW; Stuart D. C. Walsh, Monash University
This paper was prepared for presentation at the International Petroleum Technology Conference held in Dhahran, Saudi Arabia, 13 – 15 January 2020.
This paper was selected for presentation by an IPTC Programme Committee following review of information contained in an abstract submitted by the author(s).
Contents of the paper, as presented, have not been reviewed by the International Petroleum Technology Conference and are subject to correction by the author(s). The
material, as presented, does not necessarily reflect any position of the International Petroleum Technology Conference, its officers, or members. Papers presented at
IPTC are subject to publication review by Sponsor Society Committees of IPTC. Electronic reproduction, distribution, or storage of any part of this paper for commercial
purposes without the written consent of the International Petroleum Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of
not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented.
Write Librarian, IPTC, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax +1-972-952-9435.
Abstract
Artificial Islands are often an effective strategy to develop shallow-water fields. However, their layout
and design are affected by numerous drilling and surface facility constraints, such as water depth, number
of wells, proximity to shore, and well spacing. When these constraints cannot be honored, conventional
offshore wellhead platforms must be installed instead. This paper reviews previous artificial island projects
to identify their key constraints, and then proposes a numerical model that accounts for these constraints
when determining whether artificial islands or offshore platforms would generate the highest Net Present
Value (NPV) configuration.
The model uses a combination of discrete and continuous mathematical algorithms to find the optimum
development plan in shallow-water fields. Specifically, the model analyses the water depth, drilling and
surface facilities of the field to suggest the optimum facility type to drill the wells using a k-means algorithm
and Mixed-Integer Linear Programming (MILP). Then, a local optimization routine is used to connect
islands to well targets. The model accounts for limitations on well spacing and the well paths to ensure
that wells conform to the available drilling-rig capabilities and well-pad design requirements. The overall
field configuration is optimized using a stochastic-perturbation method that adjusts the field network to
maximize the NPV of the development.
The model explores the numerous possible scenarios that exist when planning shallow-water offshore
field developments, especially when a high number of wells is required. The coupling of continuous and
discrete optimization techniques provides a quick and effective method to analyze these possible scenarios
and select an optimal strategy. Results from the model indicate that offshore wellhead platforms are not
always favored over artificial islands in offshore field developments, particularly when extended reach
wells are present. This is illustrated with a case study that demonstrates each stage in the integrated model
starting from the analysis of the reservoir simulation model, through to well planning, and design of
the facility network. The study highlights how such integrated analysis can aid in the selection of the
highest development NPV plan in shallow-water fields by not only minimizing the cost associated with the
development but also reducing the time required to generate the optimum plan.
2 IPTC-19598-MS
Introduction
Use of artificial islands can be traced back to the early days of the offshore oil and gas industry in the 1930s
(Geography, 1959; Pratt et al., 1997). In the years since, numerous projects have employed artificial islands
to support drilling and production operations as opposed to using conventional offshore platforms. Despite
this long history, artificial islands for oil and gas developments were not always favored against platforms.
When selected, they have also exhibited a wide variety of different design configurations and sizes. In part,
this variability can be attributed to the niche nature of these field developments, but it is also a consequence
of the unique circumstances of each field: their age and size; the available drilling technology; and the
physical and environmental conditions affecting the development. The objective of this paper is to outline
an approach to select the optimum field development strategy (i.e. offshore platforms or artificial island).
The selection is based on a numerical model that can explore different possible subsurface and surface plans
and suggest the optimum development type with the highest NPV. In doing so, the paper provides a review
of different types of island installations for offshore oil and gas fields to categorize and include the most
common constraints in the numerical model. Results and discussion of case studies based on real-world
conditions are provided to validate the model.
To date, artificial island mathematical optimization has not received extensive consideration in the
literature, especially compared to the optimization of offshore platforms. Although this could be attributed
to the lower number of artificial-islands, the magnitude of expenditure and the complexity of island
development necessitates a computer-based approach to maximize the profitability of the project. Offshore
platform optimization modeling dates back to Devine and Lesso (1972), who developed one of the earliest
trial and error optimization model to choose a platform position. Since then, numerous models have been
proposed (e.g. (Grimmett & Startzman, 1988), (Rosa & Ferreira Filho, 2012), (Walesca et al., 2016)) to
tackle the offshore development optimization, but in many cases they have overlooked the shallow-water
fields where artificial islands could also be installed.
To consider artificial islands in an integrated development plan, we outline a mathematical model which
suggests the highest NPV field plan by accounting for the water depth, the number of wells required for
the development and the presence of real-world constraints such as well spacing and well path design.
An exhaustive search to find the optimum plan leads to a computationally expensive solution that may
not complete in time. Therefore, in this paper, we suggest a combination of algorithms to improve the
convergence time and the chances of finding an acceptable approximation to the global optimum for the field
development. The methods used include a k-means clustering to estimate the initial position, Constrained
Optimization by Linear Approximation (COBYLA) to generate well path design, optimize drilling and field
cost by Mixed Integer Linear Programming (MILP) to allocate wells, pipelines, and processing facilities
to artificial islands.
Artificial islands used in the oil and gas industry exhibit a wide variety of forms and functions. Beyond
housing oil and gas wellheads, they also include equipment to support drilling and production, oil and
gas separation equipment, water injection facilities, and accommodation (El-gharbawy, Seddik, Khaled, &
Sarhan, 2011; Wu, Zhao, & Gao, 1992). The form of the islands varies based on their specific drilling,
construction, and design requirements. To identify the primary design constraints, we studied and reviewed
distinctive examples from six different regions: the California Coast Islands in USA; the Beaufort Sea
Islands in the United States and Canada; the Caspian Sea Islands in Kazakhstan; the Bohai Sea Islands
in China; the Arabian Gulf Islands in Saudi Arabia; and the Abu Dhabi Islands in United Arab Emirates.
While this list is by no means exhaustive, it nevertheless illustrates the scope of these developments and
some of the design changes that have occurred over the years. Each region has been chosen due to their
variation in design, objective, challenges, construction year, and geographic locations. The aim of studying
and reviewing these islands is to identify the main design constraints that distinguish artificial islands from
other offshore structures.
IPTC-19598-MS 3
Table 1—Background Data for Worldwide Examples of Artificial Islands Constructed for Oil and Gas
Based on our review, the area and the water depth of each island vary greatly, as does the resulting size
of the island. The wide variation in sizes is shown in ascending order in Figure 1.
Figure 1—The relative sizes and layouts of artificial islands in oil and gas operations
The following key design points were found to be significant contributors to the total size: water depth;
island layout; number of wells and islands; the well path design; and the pipeline network. We provide a
detailed illustration of each of these items below, and outline how they are accounted for in the numerical
model.
4 IPTC-19598-MS
Water depth
The water depth at the location of artificial islands installation varies from as low as one to two meters
as in the Kashagan islands in Kazakhstan (Sarybekova, 2004) to up to 20m for the Issungnak island in
Canada (Boone, 1980). However, Modavi (2011) noted that water depth is not the sole determinant of island
placement as other factors such as the presence of existing infrastructure must also be factored in the final
decision. Technological advancements are enabling the construction of artificial islands in deeper waters.
For example, the 18 islands built in the Beaufort Sea started in low water depths (i.e. 1-2 meters). Following
the initial construction of exploration islands in this area, the industry moved into water depths of 14 to
15 meters (Gadd, Leidersdorf, & Hearon, 2012). However, there is no consistent trend over time to deeper
waters as shown in Figure 2. This limit suggests that alternative development strategies (i.e. platforms)
become economically competitive at these depths.
In our suggested model, we have the flexibility to vary the maximum water depth for artificial islands
and offshore platforms, but we set the default maximum to 10 meters, whereas the minimum water depth is
1 meter. Below this minimum water depth, the model assumes that the surface facilities can be placed in the
mainland, hence, there is no need for reclamation work. Beyond the maximum water depth, the artificial
island is deemed infeasible from construction aspects, and thus, offshore platforms should be installed.
We assume that well targets have been determined using a full reservoir simulation, which determines
the optimum placement and number of wells in the reservoir according to the performance of the reservoir
and production constraints. The present model then determines which islands will produce each well and
the 3D paths required to drill them based on their allocation to each island or platform.
Well Spacing
We introduce a constraint that allows to select different well spacing and to be able to see its impact on the
total NPV of the Project. Reducing the well spacing increases the NPV as this would mean a higher number
of wells per island or less overall size of islands if the number of wells is kept the same.
(1)
Where q(t) is the production rate at a specific year (t), q(i)is the initial production rate at the first year, b
is the degree of curvature of the line where b=0 is the exponential decline, and Di is the initial decline rate.
6 IPTC-19598-MS
The model also requires a bathymetry data and a field boundary which serves as water depth and location
constraint for the wells, surface facilities, and pipelines. Once this data is supplied, the model is initiated
by applying a k-means clustering technique to provide an initial guess for both the number and position of
surface facilities required to drill the given number of wells. A Mixed-Integer Linear Programming is then
used to allocate the wells to platforms or islands optimally and then to processing facilities based on the
minimum drilling and pipeline cost.
At each optimization run, the model outputs a detailed 3D well path trajectory for each well, including its
measured depth, inclination angles, and the time to drill the well. Similarly, the model provides an accurate
surface facility output, including the type, number, size, and location of surface facilities. The model also
details the optimum pipeline and causeway/bridges network if needed based on finding the least-cost tree.
From this data, the model estimates the drilling, pipeline, and surface facility costs and determines the
revenue based on the forecasted production from the reservoir model or the decline curve analysis. Finally,
NPV economic analysis using these costs and revenue is conducted. This process is repeated until the highest
NPV configuration is found.
After each run, a stochastic perturbation is conducted to alter the allocation of wells to platforms or islands
and similarly the distribution of islands or platforms to pipelines and surface facilities. The perturbation
causes a re-adjustment of platform positions and field configurations. This allows us to explore the field
space for other possible field networks. A Metropolis-Hastings algorithm is applied once a probability value
is reached to avoid being trapped in a local minimum. Figure 3 shows the flowchart of the process.
We must determine the capital costs, which include drilling and surface facility costs as well as the
operating costs to maintain and service the wells to carry out the economic assessment. Furthermore, we
must estimate the revenue from the generated production portfolio of the reservoir simulation model or using
the decline curve analysis. In the next section, we illustrate how the capital, operating costs, and revenue
are calculated in the numerical model.
Economic Model
A detailed capital and operating cost as well as revenue assessment are needed to ensure sound decisions
during the field development planning. While the oil and gas industry has developed experience in drilling
costs and installing facilities on the onshore and offshore platform developments, island and causeway
construction is not as common. Therefore, we outline generic drilling and surface facility cost models for
artificial islands based on a review of publicly available data. The cost of offshore facilities has been detailed
in Almedallah and Walsh (2019) and is summarized in Table 2.
In this model, the equation of the total capital cost is given by Eq (2):
(2)
Where Ctotal is the total capital (i.e. field) cost, Cdrilling is the drilling cost which accounts of a realistic
drilling cost, n is the number of wells to be drilled. Cfacility is the surface facility cost, and j is the total number
of facilities to be constructed.
8 IPTC-19598-MS
Table 2—Summary of the equations that are used for the artificial islands and the one used for the offshore platforms
In offshore platform developments, the drilling cost is calculated using offshore drilling data while in
the island development, it is calculated using onshore drilling data. The surface facility includes wellhead
platform, tie-in platform, submarine pipeline (both flowline and trunkline) and separation facility. For the
artificial islands, the surface facilities cost includes the island cost in addition to pipeline cost. The pipeline
cost will depend on the transportation option (i.e. using a causeway or offshore submarine pipelines). In
both cases, however, the surface facilities cost will include island cost which is described below.
IPTC-19598-MS 9
Once the drilling and surface facility capital costs as well as the onshore or offshore operating costs are
calculated using the functions above, an economic analysis using NPV can be carried out. In this model,
the parameters used to carry out this analysis is demonstrated in Table 3. The revenue is calculated using
the production portfolio generated from the reservoir simulation model and/or the decline curve analysis
multiplied by the oil price. A shutdown period is included that accounts for field maintenance and well
services activities. The default shutdown period is ten days, although we vary this period later in this
publication as part of the sensitivity analysis.
The spacing constraints imposed on both the offshore platforms and the artificial islands are shown in
Figure 4. The minimum water depth for which an offshore platform can be installed is assumed to be ten
meters while we allow the artificial island to be on top of water depth that is as shallow as one meter. On
the one hand, the minimum exclusion zone for the platform is 500 meters; this sets the distance between
two offshore platforms to avoid unrealistic results and ensure safe passage for offshore vessels and rigs.
Whereas, the minimum execution zone for the artificial island is set to 300 meters since less offshore traffic
is anticipated when islands are in operation. The maximum rig reach for the offshore wells is capped at 8
km while artificial islands’ rig reach is set to 9 km. This complements our review which found that artificial
islands use onshore rigs which has better reach capabilities than offshore rigs.
10 IPTC-19598-MS
Figure 4—Sample graph to explain the minimum allowed water depth, the minimum exclusion zone,
and the maximum drill target reach for a) offshore platforms, b) and artificial islands on the right.
Using these constraints, we introduce below Case-Study A which applies artificial islands and Case
Study-B which uses offshore platforms, compare their results and then determine the highest NPV
configuration. Finally, we provide a discussion section which analyses the sensitive parameters to the results.
At first, the model introduced a single island and tried to reach the wells from this only island; however,
it violated the constraint of the maximum 20 wells per island. Therefore, an additional island has been
introduced.
The k-means clustering method was able to identify an initial position for these two islands based on the
location of well targets but has not yet optimally place the islands as it has not incorporated other factors
such as water depth and the minimum distance between facilities. At the same time, the model applied the
MILP and has generated an initial allocation of wells to platforms. The results of setting this initial solution
are shown in Figure 5.
IPTC-19598-MS 11
Figure 5—Initial allocation and using k-means clustering, a) shows the first attempt with one island which
violated the maximum wells per island constraint while b) suggested two islands satisfying both constraints.
At each iteration, the model allows to calculate a 3D drilling path for each well and adjust the position
of the island, now, based on a weighted capital cost for surface facilities including water depth and drilling
costs. Based on the new capital cost and operating costs, the model estimates the production using declined
curve analysis and computes the NPV. The production decline using the exponential decline curve analysis
is shown in Figure 6.
At the final iteration, the model was not able to generate a better NPV configuration, and hence, the model
reached an optimal plan for this island development. The model was able to identify two islands which can
drill all the 25 wells of the development. These two islands are connected to a manifold by two flowlines
(572 and 300 meters) which then transports the crude to a gas-oil separation facility (GOSP) located onshore
by a trunkline. The location of these two islands as well as this pipeline connection is illustrated at early
iteration and final iteration in Figure 7.
12 IPTC-19598-MS
Figure 7—Results of Case Study-A after a) early iterations and b) at the final iteration, based
on minimum water depth of one meter. [Red lines are the location of well targets, yellow square
is the island location, black square is the manifold area, and blue pentagon is the GOSP]
The model was able to successfully place the islands in a proper water depth subject to the previously
identified minimum and maximum water depth constraints. Island B has been placed in a water depth of
one meter at exactly the minimum water depth constraint as expected since the model will favor lowering
the size of the island. It should be noted that this minimum constraint ensured that the island is not placed
in the mainland. This achieves the objective of placing the islands only in the offshore coast and avoids
the populated mainland area. On the other hand, Island A has been placed at 4.39 meters. The minimum
exclusion zone constraint of 300 meters has enabled to separate the placement of the islands apart which
could otherwise place Island A on also the shallow area closer to the coast, an obvious choice to reduce the
total size of the island. Detailed parameter analysis summary of the number of wells, water depth, flowline
distance, island areas, and island volumes are shown in Table 6.
The MILP has also successfully allocated the 25 wells to the two islands based on the minimum drilling
reach and cost. In this scenario, Island A has accommodated eleven (11) wells, whereas island B has been
allocated with fourteen (14) wells. This allocation has met the maximum drilling reach of 9000 meters and
maximum dogleg severity specified at 8 deg/100ft. Based on the identified maximum number of wells per
row (i.e. 5 wells per row), the wells spacing (i.e. 20 meters) and the row spacing (i.e. 50 meters), Island
A and Island B have placed the wells in three rows. Figure 8 illustrates the placement and distribution of
wells in the two islands.
IPTC-19598-MS 13
Figure 8—The resulting layout of island A and B including well and row spacing, number of wells and their allocation
The algorithm applied the cost functions that we listed earlier to obtain the results. Then, this data was
used by the NPV analyzer to generate a value of almost $4050 million US dollar.
It should be noted that the minimum water depth plays a vital role in the placement and the result field
network. To test the effect of choosing a minimum water depth, we vary the 1-meter minimum depth
restrictions to 3 meters. The field configuration for the 3-meter scenario is shown in Figure 9 when compared
to the 1-meter scenario has resulted in $6MM reduction in NPV. As expected, the higher the minimum
water depth is chosen, the less is the resulting NPV because additional volume of sand and construction
would be needed.
Figure 9—Results of Case Study-A at the final iteration, based on minimum water depth of 3 meters [Red lines are the location
of well targets, yellow square is the island location, black square is the manifold area, and blue pentagon is the GOSP
Figure 10—Resulting configurations of wellhead platforms (Red lines are the location of well targets, yellow triangles
represent the platform locations, black triangle is the tie-in platform location, and blue pentagon is the GOSP)
The NPV of this scenario is $3,168 MM, which is $890 MM less than the artificial island field
development presented in Case Study-A. This is attributed to several factors but mainly due to the higher
cost of platforms in case-study B which totaled $145 MM compared to the cost of artificial islands which
only costed $20.33 MM for both islands. Thus, the cost function that describes the behavior of the effects of
water depth, maximum number of wells per platform and the anticipated size of both platforms and islands
play a vital role in determining the highest NPV configuration of field developments. We show the results
of comparing drilling costs, total facility costs, and the NPV of artificial islands against offshore platforms
in Figure 11. Based on the results of our cost function and the input used for this case study, artificial islands
development is favored against offshore platforms.
Figure 11—Results of Comparing Costs and NPV (in $MM) of Artificial Islands and Offshore Platforms
IPTC-19598-MS 15
However, the artificial island might not always be the most economical configuration as it would be
strongly influenced by the specified constraints. As operators have different criteria and design restriction,
the advantage of this model is that it provides the flexibility to change these constraints to fit the required
operation and determine the economic impact of changing one constraint. For instance, we demonstrated in
Case Study-A how changing the minimum water depth from 1 meter to 3 meters had an impact on the total
net present value. Then, the operator can decide whether this impact is high or low based on their operation
and standards and the difference in NPV.
For our model and based on our assumed cost function and design assumptions, the parameters and
constraints have a variety of impact in the total NPV. In the next section, we present a sensitivity analysis to
highlight the most important factors when considering artificial island and offshore platform developments.
At first, we compare the Base Case which was presented in Case Study-A to the different scenarios
listed in Option-A, B, and C. This is to test and highlight the effect of having a different combination of
assumptions and constraints towards the results.
The bottom row of Table 7. highlights the results and show the wide variation in NPV compared to the
Base case. Because we changed more than one parameter at once, it is not possible to pinpoint a sole factor
to this wide variation. However, it is vital to see how different assumptions had resulted in a change of $246
MM to $188 MM to the NPV illustrating the importance of choosing and carefully studying the constraints.
16 IPTC-19598-MS
To be able to understand the effect of these individual parameters, we develop a tornado chart showing the
sensitivity range of each parameter as shown in.
Figure 12—Tornado chart highlighting the sensitivity of the model to the key constraints related to artificial islands
Based on Figure 12, the most sensitive parameter is the shutdown days per year as this will impact the
revenue and thus the NPV. Increased uptime is reported when using artificial islands over offshore platforms
because the operation and maintenance staff are situated on the islands and hence, they are located closer
to well and facilities -- enabling more rapid, frequent and efficient intervention. Furthermore, the wider
space of wells in the islands allows for less production shutdown time during rig moves (Talbot et al.,
2012). Therefore, this is a critical factor to evaluate and determine when using such models to choose a
development plan.
Another sensitive parameter is the maximum number of wells per island. In offshore platforms, as the
number of wells grows, the structure of the platforms also enlarges to a limit where the cost of procurement
and installation become prohibitive to add more wells. However, this constraint is not that strict in artificial
islands as larger island can be built with less procurement and installation restrictions. Thus, this provides
an advantage to artificial islands to place more wells in islands as can be demonstrated from the NPV results
in Figure 12.
In addition, the transportation and pipeline option has shown a sensitive behavior when varying from
causeway to offshore option. Based on the cost assumption of this model and the data of this case study,
the offshore option is favored when compared to causeway although operating costs as shown in Figure 13.
This is because $168 MM in construction costs is reduced by not building a causeway and its associated
(expensive) bridges. It is encouraging to see that the Thums Islands, which was used as a basis to develop
this case study, has also not applied a causeway option when developing the field. The advantages of this
model lie within its flexibility to analyze both options for any field development to determine the cost
magnitude of conducting both options.
IPTC-19598-MS 17
Figure 13—Results of Comparing Costs and NPV of Artificial Islands and Offshore Platforms
Well spacing and layout shape have a minimal cost impact on the economic result - this is mainly due
to the island cost function. The island cost function has a y-intercept of $10MM, representing fixed capital
costs that are unaffected by the reduction in island area. This behavior matches a realistic construction
project which will incur a fixed cost regardless of the magnitude of the project arising from equipment
mobilization, permits and licenses, and labor charges. Nevertheless, one should not ignore the effect of
reducing the size of an island area. Reducing an island size might have advantages related to minimizing
the environmental and construction impact, which not captured in our model.
There are other factors that could affect artificial islands optimizations, and due to the wide range of
development options, drilling, and facility design, optimization should be combined with other studies
related to the construction and environmental work for the islands to realize the full benefits of artificial
islands.
Conclusion
Artificial islands are employed in shallow-water oil and gas fields across the world. Their design and location
must be carefully selected to maximize the benefits of their use and minimize the associated investment.
Although many scholars optimized the offshore development using different optimization techniques, in the
literature, there is a lack of research on the optimization of artificial islands for the oil and gas industry. In
this paper, we first reviewed six artificial islands taken from six different locations to determine the unique
designs and constraints related to artificial islands and offshore platforms. Then, we used the collected
limitations on artificial island building to feed them to a numerical optimization algorithm to maximize
the NPV.
We show that the model can generate field configurations for both artificial island and offshore
developments in a short computational time, reducing the planning time. A multitude of potential
combinations exist when developing shallow-water fields, and hence, a computer-based approach is vital
to select the optimum combination with the highest NPV.
In summary, compared to offshore platforms for fields located in shallow water depth, the model has
shown that artificial islands have economic benefits in both capital (CAPEX) and operational (OPEX)
costs. CAPEX is lower because fewer islands and hence pipelines are constructed, which complements the
observation made by (A. Modavi, 2011). Moreover, artificial islands allow the use of powerful land-based
rigs capable of drilling more extended wells and reaching more of the reservoir which also supports the
18 IPTC-19598-MS
conclusion drawn by (Alnughaimish, Al-Hamdan, & Al-Shobaili, 2009; C. Modavi, Martin, Al Muflehi,
Walters, & Ismail, 2008).
References
Aldossary, G. (2015). OTC-25663-MS Manifa Oil Field Development Program -- Onshore and Offshore Shallow Water
Development. 4–7.
Almedallah, M. K., & Walsh, S. D. C. (2019a). A numerical method to optimize use of existing assets in offshore natural
gas and oil field developments. Journal of Natural Gas Science and Engineering, 43–55. https://doi.org/10.1016/
j.jngse.2019.04.012
Almedallah, M. K., & Walsh, S. D. C. (2019b). Integrated well-path and surface-facility optimization for shallow-water
oil and gas field developments. Journal of Petroleum Science and Engineering, 174, 859–871. https://doi.org/10.1016/
J.PETROL.2018.11.025
Almedallah, M., Walsh, S. D. C., & Lau, T. H. (2018). A human-computer hybrid approach to offshore field development:
combining virtual reality aided design with stochastic optimization. Asia Pacific Oil & Gas Conference and Exhibition.
Asia Pacific Oil & Gas Conference and Exhibition.
Alnughaimish, F. N., Al-Hamdan, M. R., & Al-Shobaili, Y. M. (2009). SS - Extended Reach Drilling and Causeway
Utilization in the Development Of a Shallow Water Oil Field. Offshore Technology Conference, p. 11. https://
doi.org/10.4043/20112-MS
Ashford, A. A., Co, S. C., & Sea, B. (1984). OTC 4670 Engineering and Construction of Mukluk Island.
Berman, B., & Clarke, D. (1987). Oil Producing Areas in Long Beach: Thums Oil Operations. AAPG Pacific Section.
Boone, D. J. (1980). The Construction Of An Artificial Drilling Island In Intermediate Water Depths In The Beaufort Sea.
Offshore Technology Conference, p. 10. https://doi.org/10.4043/3873-MS
Close, D. A., Brett, D. J., & Dakhil, O. A. A. L. (2009). Manifa Field Causeway and Islands, Saudi Arabia. Terra Et
Aqua, 114, 9–17.
Devine, M. D., & Lesso, W. G. (1972). Models for the minimum cost development of offshore oil fields. Management
Science, 18(8), B--378.
DigitalGlobe. (2018). DigitalGlobe Satellite Imagery.
El-gharbawy, S., Seddik, S., Khaled, M., & Sarhan, H. (2011). OTC 21799 Application of Land Reclamation and Artificial
Island Technology in the Arabian Gulf Petroleum Industry. 2–5. https://doi.org/10.4043/21799-MS
Gadd, P. E., Leidersdorf, C. B., & Hearon, G. E. (2012). The History of Artificial Islands for Oil Exploration and
Development in the Alaskan Arctic.
Grimmett, T. T., & Startzman, R. A. (1988). Optimization of Offshore Field Development To Minimize Investment. SPE
Drilling Engineering, 3(04), 403–410. https://doi.org/10.2118/16297-PA
Hannon, P. J. F., & LeBlanc, J. W. (1987). Artificial Offshore Islands. Mining Society of Nova Scotia Fall Meeting, 22pp.
Huxley, I. C. (1987). Endicott Development: Making the Arctic Offshore Economical. 12th World Petroleum Congress,
8. Houston, Texas, USA: World Petroleum Congress.
Kidd, G. N., Holt, B. M., & others. (2003). Northstar Drilling-A Progressive Arctic Endeavor. SPE/IADC Drilling
Conference.
Kragas, T. K., Turnbull, B. F., & Francis, M. J. (2004). Permanent Fiber-Optic Monitoring at Northstar: Pressure/
Temperature System and Data Overview. SPE Production & Facilities, 19(02), 86–93. https://doi.org/10.2118/87681-
PA
Lyons, E. P., & Mechem, E. (1968). Design and lmplenientation of Directional-drilling Programs THUMS Offshore
Islands Development Wells East Wilmington Fieldt.
Modavi, A. (2011). OTC 22015 A Super-Giant Offshore Field Development Plan Change from Steel Structures to Artificial
Islands.
Modavi, C., Martin, W. W., Al Muflehi, A. H., Walters, J. V., & Ismail, G. (2008). Field Development Expansion of a
Giant Oil Field in Abu Dhabi Using Artificial Islands as Drilling and Production Centers. Abu Dhabi International
Petroleum Exhibition and Conference, p. 10. https://doi.org/10.2118/118379-MS
of Geography, A. of S. of A. (1959). Mineral resources of Azerbaijan. International Geology Review, 1(12), 82–85.
Pratt, J. A., Priest, T., & Castaneda, C. J. (1997). Offshore pioneers: Brown & Root and the history of offshore oil and
gas. Gulf Professional Publishing.
Rosa, V. R., & Ferreira Filho, V. J. M. (2012). Optimizing the location of platforms and manifolds. ASME 2012 31st
International Conference on Ocean, Offshore and Arctic Engineering, 813–818.
Ruzhnikov, A., Alzate, J., Singh, R., Al-Wahedi, K., AL-Kindi, R., & others. (2018). Operational Performance
Improvement Plan: How to Boost the Performance and Reduce the Cost During well Construction. SPE/IADC Middle
East Drilling Technology Conference and Exhibition.
IPTC-19598-MS 19
Sarybekova, L. (2004). North Caspian Project - Challenges and Successes. SPE International Conference on Health,
Safety, and Environment in Oil and Gas Exploration and Production, p. 5. https://doi.org/10.2118/86685-MS
Talbot, R., Al-Ahbabi, S. N., & Bouwmeester, B. (2012). Artificial Islands for a Middle Eastern Oil Field Project. Abu
Dhabi International Petroleum Conference and Exhibition. https://doi.org/10.2118/162611-MS
Toki, T., Benygzer, M., Ahmed Al Wahedi, K., Kumar Anurag, A., Pratap Narayan Singh, R., Sayed, M. I., … Jason
Cocagne, M. (2017). Optimization of the Operation Time Required for Data Gathering Requirement in Extended-
Reach Drilling Well by the Use of Open Hole Tractor in the United Arab Emirates.
US Army Corps of Engineers. (1984). Final environmental impact statement, Prudhoe Bay oil field, Endicott development
project. Anchorage, Alaska: US Army Corps of Engineers, Alaska District.
Vinck, K., Mol, A., & Carnevale, S. (2012). Design and construction of artificial island of Satah al Razboot oil field.
CEDA Dredging Days 2012: Virtue, Venture and Vision in the Coastal Zone, (December 2012), 14.
Walesca, H., Rodrigues, L., De, B., Prata, A., De Oliveira, T., & Assistant, B. (2016). New Integrated Approach for
Location and Sizing of Offshore Multicapacitated Platforms and Location of Oil Wells. Journal of Petroleum Science
and Engineering, 145, 734–741.
Wu, Z., Zhao, A., & Gao, X. (1992). The Unique Artificial Steel/Concrete Islands In China. The Second International
Offshore and Polar Engineering Conference, 5. San Francisco, California, USA: International Society of Offshore and
Polar Engineers.