ID Task Name Duration Start Finish Predecessors

01 March 21 April
15/03 05/04 26/04
1 PEKERJAAN PERSIAPAN 13 days Mon 05/04/21Sat 17/04/21
2 PEMBERSIHAN LOKASI 7 days Mon 05/04/21Sun 11/04/21
3 PEKERJAAN BOWPLANK 9 days Fri 09/04/21 Sat 17/04/21 2FS-3 days
4 PEKERJAAN TANAH DAN PONDASI 47 days Sun 11/04/21 Sun 30/05/21 1FS-7 days
5 PEMANCANGAN BETON TIANG PANCANG 15 days Sun 11/04/21 Sun 25/04/21
6 GALIAN TANAH 9 days Mon 19/04/21Tue 27/04/21 5FS-7 days
7 BETON LANTAI KERJA 10 days Sat 24/04/21 Mon 03/05/216FS-4 days
8 BETON PILE CAP 14 days Thu 29/04/21 Sat 15/05/21 7FS-5 days
9 URUGAN TANAH KEMBALI 7 days Sat 08/05/21 Mon 17/05/218FS-5 days
10 BETON SLOOF 17 days Tue 11/05/21 Sun 30/05/21 9FS-4 days
11 PEKERJAAN STRUKTUR LANTAI 1 29 days Mon 24/05/21Mon 21/06/214FS-7 days
12 BETON KOLOM 15 days Mon 24/05/21Mon 07/06/21
13 BETON RABAT LANTAI 1 9 days Tue 08/06/21 Wed 16/06/2112
14 BETON TANGGA 8 days Mon 14/06/21Mon 21/06/2113FS-3 days
15 PEKERJAAN STRUKTUR LANTAI 2 19 days Mon 14/06/21Fri 02/07/21 11FS-8 days
16 BETON KOLOM 16 days Mon 14/06/21Tue 29/06/21
17 BETON PLAT LANTAI 2 19 days Mon 14/06/21Fri 02/07/21 12FS-2 days
18 BETON BALOK 17 days Mon 14/06/21Wed 30/06/2117SS
19 PEKERJAAN STRUKTUR LANTAI ATAP 21 days Sat 26/06/21 Fri 16/07/21 15FS-7 days
20 BETON BALOK 17 days Sat 26/06/21 Mon 12/07/21
21 BETON PLAT LANTAI ATAP 21 days Sat 26/06/21 Fri 16/07/21 20SS
22 PEKERJAAN PENUTUP ATAP 56 days Sat 03/07/21 Sat 28/08/21 19FS-14 days
23 KUDA KUDA 17 days Sat 03/07/21 Mon 19/07/21
24 GORDING 7 days Sat 17/07/21 Sat 24/07/21 23FS-3 days
25 PAS. ATAP USUK RENG BAJA RINGAN 11 days Fri 23/07/21 Mon 02/08/2124FS-2 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Name Duration Start Finish Predecessors
01 March 21 April
15/03 05/04 26/04
26 PAS. KALSIPLANK 6 days Tue 03/08/21 Sun 08/08/21 25
27 PAS. PENUTUP ATAP GENTENG KERAMIK 14 days Sun 08/08/21 Sat 21/08/21 26FS-1 day
28 PEKERJAAN BUBUNGAN 9 days Fri 20/08/21 Sat 28/08/21 27FS-2 days
29 PEKERJAAN PASANGAN DAN PLESTERAN LANTAI 1 35 days Sat 03/07/21 Sat 07/08/21 22SS
30 PAS. DINDING BATA RINGAN 26 days Sat 03/07/21 Thu 29/07/21
31 PLESTERAN BATA RINGAN 23 days Fri 09/07/21 Sun 01/08/21 30FS-20 days
32 ACIAN DINDING BATA RINGAN 21 days Sat 17/07/21 Sat 07/08/21 31FS-15 days
33 PEKERJAAN KUSEN LANTAI 1 21 days Sat 10/07/21 Sat 31/07/21 29FS-28 days
34 PASANG KUSEN + DAUN PINTU 18 days Sat 10/07/21 Wed 28/07/21
35 PASANG KUSEN TRALIS 12 days Mon 19/07/21Sat 31/07/21 34FS-9 days
36 PEKERJAAN PENUTUP LANTAI 1 42 days Sat 17/07/21 Sat 28/08/21 33FS-14 days
37 PAS. KERAMIK 42 days Sat 17/07/21 Sat 28/08/21
38 PEKERJAAN PLAFOND LANTAI 1 42 days Sat 10/07/21 Sat 21/08/21 33SS
39 PAS. PLAFOND GYPSUM + RANGKA HOLLOW 27 days Sat 10/07/21 Fri 06/08/21
40 PAS. PLAFOND KALSIBOARD + RANGKA HOLLOW 27 days Sat 10/07/21 Fri 06/08/21 39SS
41 PAS. LIST GYPSUM 19 days Tue 03/08/21 Sat 21/08/21 40FS-4 days
42 PEKERJAAN PENGECATAN LANTAI 1 35 days Sun 08/08/21 Sat 11/09/21 38FS-14 days
43 PENGECATAN DINDING 25 days Sun 08/08/21 Wed 01/09/21
44 PELAPISAN WATERPROFING 8 days Mon 30/08/21Mon 06/09/2143FS-3 days
45 PENGECATAN PLAFOND 15 days Sat 28/08/21 Sat 11/09/21 43FS-5 days
46 PEKERJAAN PASANGAN DAN PLESTERAN LANTAI 2 42 days Sat 10/07/21 Sat 21/08/21 38SS
47 PAS. DINDING BATA RINGAN 32 days Sat 10/07/21 Wed 11/08/21
48 PLESTERAN BATA RINGAN 28 days Thu 15/07/21 Thu 12/08/21 47FS-27 days
49 ACIAN DINDING BATA RINGAN 13 days Mon 09/08/21Sat 21/08/21 48FS-4 days
50 PEKERJAAN KUSEN LANTAI 2 21 days Sat 17/07/21 Sat 07/08/21 36SS

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
ID Task Name Duration Start Finish Predecessors
01 March 21 April
15/03 05/04 26/04
51 PASANG KUSEN + DAUN PINTU 18 days Sat 17/07/21 Wed 04/08/21
52 PASANG KUSEN TRALIS 12 days Tue 27/07/21 Sat 07/08/21 51FS-9 days
53 PEKERJAAN PENUTUP LANTAI 2 42 days Thu 22/07/21 Wed 01/09/2138SS+5 days
54 PAS. KERAMIK 42 days Thu 22/07/21 Wed 01/09/21
55 PEKERJAAN PLAFOND LANTAI 2 42 days Sat 17/07/21 Sat 28/08/21 38SS+7 days
56 PAS. PLAFOND GYPSUM + RANGKA HOLLOW 27 days Sat 17/07/21 Fri 13/08/21
57 PAS. PLAFOND KALSIBOARD + RANGKA HOLLOW 27 days Sat 17/07/21 Fri 13/08/21 56SS
58 PAS. LIST GYPSUM 19 days Tue 10/08/21 Sat 28/08/21 57FS-4 days
59 PEKERJAAN PENGECATAN LANTAI 2 35 days Sun 15/08/21 Sat 18/09/21 42SS+7 days
60 PENGECATAN DINDING 25 days Sun 15/08/21 Wed 08/09/21
61 PELAPISAN WATERPROFING 8 days Mon 06/09/21Mon 13/09/2160FS-3 days
62 PENGECATAN PLAFOND 15 days Sat 04/09/21 Sat 18/09/21 60FS-5 days
63 PEKERJAAN ATAP SKYLIGHT LANTAI 2 21 days Sun 22/08/21 Sat 11/09/21 59FS-28 days
64 PAS. RANGKA BESI HOLLOW 15 days Sun 22/08/21 Sun 05/09/21
65 PENGECATAN MENI BESI 5 days Tue 31/08/21 Sat 04/09/21 64FS-6 days
66 PAS. KACA SAFETY 7 days Sun 05/09/21 Sat 11/09/21 65
67 PEKERJAAN FASADE 21 days Sun 22/08/21 Sat 11/09/21 63SS
68 PAS. BATU ALAM 14 days Sun 22/08/21 Sat 04/09/21
69 PAS. LOGO 1 day Sun 22/08/21 Sun 22/08/21 68SS
70 PAS GRC +RANGKA 11 days Wed 01/09/21Sat 11/09/21 68FS-4 days
71 PEKERJAAN MEP 91 days Sat 03/07/21 Sat 02/10/21 29SS
72 PEKERJAAN LISTRIK 88 days Tue 06/07/21 Sat 02/10/21 73FS-42 days
73 PEKERJAAN SEPTICTANK + RESAPAN 45 days Sat 03/07/21 Tue 17/08/21
74 PEKERJAAN PIPA 38 days Sat 03/07/21 Tue 10/08/21
75 PAS. KRAN AIR 15 days Sat 03/07/21 Sat 17/07/21 6FS-5 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
ID Task Name Duration Start Finish Predecessors
01 March 21 April
15/03 05/04 26/04
76 PAS. KRAN + WASTAFEL 13 days Sun 18/07/21 Sat 31/07/21 75
77 PAS. KLOSED 17 days Sat 03/07/21 Mon 19/07/2175SS
78 PAS. KRAN +JET WASHER 4 days Sat 03/07/21 Tue 06/07/21

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 4
21 April 11 June 01 August 21 September
26/04 17/05 07/06 28/06 19/07 09/08 30/08 20/09 11/10 01

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 5
21 April 11 June 01 August 21 September
26/04 17/05 07/06 28/06 19/07 09/08 30/08 20/09 11/10 01

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 6
21 April 11 June 01 August 21 September
26/04 17/05 07/06 28/06 19/07 09/08 30/08 20/09 11/10 01

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 7
21 April 11 June 01 August 21 September
26/04 17/05 07/06 28/06 19/07 09/08 30/08 20/09 11/10 01

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: awalan Milestone Inactive Milestone Start-only


Date: Mon 06/12/21 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress