You are on page 1of 1

Project Report

Project Report:

Day 1 - Finalize floor plan, Start 3D drawings, Clean floor , Finish line Dori, Start laying platforms

Day 2- Continue platform work ( laying and levelling), start concept sketches, continue 3D drawings, drawings and
references for molding work, start dyes for molding

Day 3- Continue platforms, start arches, continue drawings, continue molding

Day 4- Finish platforms , start stairs, start walls, continue arches, start pillar molding, start clay work for sculpture,
continue drawings

Day 5 - Conttinue stairs, continue walls, continue arches, continue pillar work, continue sculpture work, continue
drawings, start props sourcing

Day 6 - Finish stairs, continue walls, continue arches, continue pillar work, start windows, continue sculpture work,
continue prop sourcing, start thermocol work, start stitching, continue drawings

Day 7 - Continue walls, continue arches, continue pillar work, continue windows, continue thermocol work, continue
prop sourcing, continue stitching, finalize drawings for set dressing, continue sculpture

Day 8 - Finish walls, continue arches, continue pillar work, continue windows, start setting thermocol work, start
bringing in props, continue stitching, start work for artworks, continue sculpture, start molding for smaller specific
props

Day 9 - Finish arches, place pillars and windows, continue setting thermocol work, finish prop sourcing, continue
stitching, start painting, continue sculpture, continue other molding, continue artwork

Day 10 - continue placing pillars and windows, finish setting thermocol work, continue stitching, continue painting ,
cast sculpture, continue other molding, continue art work, start fibre work, start flooring

Day11- continue placing pillars and windows, finish setting thermocol work, continue stitching, continue painting ,
continue sculpture, continue other molding, finish art work, continue fibre work, start flooring, finish art work

Day 12- Continue painting, continue fibre work, finish sculpture, finish other molding, fInalize stitching, continue
flooring , start fountain work

Day 13 - Finish painting, finish fibre work, finish sculpture, finish stitching, finish flooring, continue fountain work, start
propping

Day 14 - Finnish fountain , finish touch ups, finish propping

You might also like